This is Amendment A0001 (Standard Form 30) to Invitation for Bid (IFB) 36C24226B0002 for the Renovate 6B for Outpatient Mental Health project at the James J. Peters VA Medical Center in Bronx, NY (Project 526-19-122). The amendment extends the bid opening date to February 26, 2026, at 2:00 PM EST and confirms that only in-person bids will be accepted—no emailed submissions are permitted. The amendment mandates that only firms who attended the mandatory site visit on January 21, 2026, at 10:00 AM are eligible to submit bids. The amendment incorporates a revised Statement of Work that expands asbestos abatement scope to the entire construction area, estimated at approximately 17,000 square feet, and provides a revised bid sheet that includes a $100,000 allowance as a separate line item (line item 2). Revised drawings are provided for only the following: A106.1, A106.2, A106.3, A601, AF106, AF601, AF602, P106.1, P106.2, P601, MV406, M601, E601, E602, E701, E703, EL106, and ES106; all other solicitation drawings remain unchanged.
The amendment consolidates comprehensive Requests for Information (RFI) responses organized into four sets, addressing critical project clarifications including: asbestos abatement scope covering the entire 17,000 SF construction area and structural steel fireproofing; requirements for 1/8-inch acoustical sound barriers and STC 50 assemblies for patient privacy; Stonhard epoxy wall base systems (minimum 4 inches) as mandatory with no approved equals; tamper-proof and suicide-resistant fixtures for patient-accessible areas; single-phase construction with off-hours work required for 5B area and exterior corridor work outside 6B; Hill-Rom equipment specifications (attached); and confirmation that no phasing, LEED requirements, design delegation, or BIM requirements apply. The VA will provide the independent commissioning agent, and contractors must coordinate with the Construction Contracting Officer regarding temporary barriers, facility access (including service elevator use and utility access), and work involving the active adjacent patient clinic in Ward 6C.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority)
THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 02-09-2026 526-19-122 36C242 Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx NY 10468-3904 36C242 Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx NY 10468-3904 To all Offerors/Bidders
36C24226B0002 01-14-2026
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 02-26-2026 2PM EST x This amendment A0001 is for the Renovate 6B for Outpatient Mental Health, Project 526-19-122 at the James J. Peters Bronx VAMC.
This amendment provides the following: Bid extension date is 2/26/2026 @2PM EST -NO EMAILED BIDS WILL BE ACCEPTED.
1. Provide all RFI's and VA Responses submitted for this solicitation. No further RFI's will be accepted.
2. Provide revised drawings for the following: A106.1, A106.2, A106.3, A601, AF106, AF ,P 106.1, P106.2, P601, MV406, M601, E601, E602, E701, E703, EL106, ES106, and AF602. These are the ONLY drawings that have been revised
3. Provide the Site Visit Sign In sheet from 1/21. NOTE: This was a MANDATORY site visit in order to submit a bid.
Bids will not be accepted from firms who did not attend.
4. Provide REVISED SOW to include additional asbestos abatement, and revised Bid Pricing sheet to include a $100,000 allowance as line item 2 on bid sheet. 5. Provide Hill Rom specification as per RFI response (see attached) Patricia Cordero
CONTRACT SPECIALIST
CONTINUATION PAGE
Please see below complete compiling of RFI’s submitted for the Renovate 6B for Outpatient Mental Health. Please note that there are several sets of RFI’s below and they are not numbered continuously. VA responses are provided in red below:
RFI Set 1:
1) We noticed that some of the drawings are in color, which makes them very difficult for us to review clearly. Even after printing these color drawings cannot be read properly, so can the agency please provide clear copies/black and white of all the color drawings.
VA RESPONSE: See updated drawings, they’re all in black & white. Please zoom in on some drawings to review clearly and use Adobe Acrobat for better results.
2) Some drawing scales are incorrect.
VA RESPONSE: See updated drawings, they’re all in black & white. Please zoom in on some drawings to review clearly and use Adobe Acrobat for better results.
3) Requesting to extend the RFI due date by as after clear drawings are posted/received we need more time to review the clear drawings and may have RFI. So, requesting to extend the RFI due date for a week after the issuance of clear drawings.
VA RESPONSE: Bid date will be extended for RFI responses and revised SOW. Please see SF30 for updated bid opening date.
4) Drawing GI001 general note no.2 states to have property damage insurance, is this insurance required? How much is the limit? Premium cost will depend on that.
VA RESPONSE: Other than the typical general liability insurance, no other additional insurance is required.
5) Spec section 01 45 00 para 3.4 lists various requirements for the CQC personnel. Please confirm contractor’s superintendent or project manager can simultaneously fulfill these duties and contractor doesn’t have to hire a full time CQC personnel.
VA RESPONSE: Confirmed.
Contractor shall assign a dedicated, capable, experienced, full-time site superintendent for the duration of the project in its entirety and will be required to be on site when ANY active construction work is being performed. Site supervisor is subject to VA approval.
6) Please confirm VA will hire an independent commissioning agent for all the required commissioning work.
VA RESPONSE: Confirmed.
7) There is a spec section for Applied Fireproofing as there is no new structural steel work, where is this fireproofing required?
VA RESPONSE: Any damage or penetration to the existing structural steel fireproof during construction is the contractor’s responsibility to be fixed and fireproofed. In addition, any structural steel beam uncovered during demolition of that is NOT fireproofed shall be the responsibility of the contractor to fireproof completely, whether troweled on, or sprayed as specified in the Applied Fireproofing spec provided.
NOTE: Contractors must estimate an approximate area of 17,000 SF will need to be fireproofed (the entire construction area), as an investigation has determined that the existing steel beams are NOT fireproofed.
8) Please confirm all the construction and noisy work can be performed in regular work hours.
VA RESPONSE: Confirmed.
9) There is a spec section for Subsurface Preparation for Floor Finishes. Please clarify if self-leveling is required if yes then what is the thickness. At the time of bid contractor cannot determine this, unless all existing flooring is removed.
VA RESPONSE: Yes, self-leveling is required as per the specifications.
10) There is a spec section only for Resinous Epoxy Base (RES 2). Please confirm there is no Resinous Epoxy Flooring work.
VA RESPONSE: See room finish schedule drawing # AF106.
11) As this area if for mental health patients is there any requirements for tamper proof or suicide proof fittings and hardware?
VA RESPONSE: Yes. All patient/ public accessible bathrooms must have tamper proof fittings and hardware as per Mental Health design guides/ manuals.
12) Drawing H106 indicates area of the 1’ x 1’ asbestos containing floor tile. During the prebid walkthrough we observed similar tiles in other project areas too which are not shown on the drawings. If this is right then VA may have to revised this drawing showing other locations.
VA RESPONSE: Contractor shall assume the entire construction site, estimated at 17,000 SF will require asbestos abatement. See amendment and revised SOW.
13) Drawing AD106 shows demolition of all existing partition walls. Please confirm that all of these walls are drywalls and not masonry.
VA Response: It’s the contractor's responsibility to field verify the site before construction. See drawings, specs, and contract documents for specifics on wall types.
14) Drawing AD106 demo key note # 1 is shown only in one location of corridor area. Doesn’t all the floor and drop ceiling system be demoed for all of the project area? If yes then please revise the drawing showing note # 1 at all the corridors and rooms.
VA RESPONSE: All corridor work will require new drop ceiling and flooring. Follow AD106 demo plan legend & keynotes. If there are any contradictions noted, contractors shall assume that all new corridor work will require new drop ceiling and new flooring and cove base. Contractors must bid accordingly based on this RFI response.
15) Drawing AD106 demo general note no.6 states where walls have been removed, fill any voids in floor with concrete fill. As this is a huge quantity of removed walls (is over 2,000 LF) please specify what could be the fill thickness and specify if pre-blended concrete mix like Sakrete brand can be used instead of the truck ready mix concrete.
VA Response: Contractors may use pre-blended concrete and assume an approximate area of 2,000 LF of concrete to be filled. Contractor to also follow specifications requirements where applicable.
16) Drawing AC105 states demolition plan 5B. Is this plan for the 5th floor which is below the project area?
VA RESPONSE: Confirmed. Yes, 5B, 5th floor area B, directly below.
17) Door schedule is calling for many STC 50 openings. Possibly 70+. Not only are all these wood doors which cannot reach STC 50 (typically they max out at STC 48 depending on the configuration) but STC 50 is also a VERY high rating. The bulk of these openings are offices; there’s no way they need an STC rating that high. Pricing them that way will be expensive and may be over budget. STC 50 is far too heavy a spec for these offices. If still STC 50 is required then please advise the basis of design.
VA RESPONSE: There is NO preference as long as it satisfies the drawings, specs, and contract documents for proper sound rating for patient privacy, which must meet the minimum requirements for sound rating.
18)Drawing A106.1 floor plan key note no.2 states Aluminum framed window. Refer to window schedule. But window schedule on drawing A602 calls for hollow metal frame. Please clarify which material is to be used for window frame aluminum or hollow metal?
VA RESPONSE: Aluminum is required.
19) Drawing A106.1 general floor plan note no.9 states subsurface preparation shall be performed in accordance with spec sec 09 05 16. Please confirm if contractor must use self-leveling underlayment product like Ardex K-15 as this is a very expensive application.
VA Response: Confirmed, contractor must use self-leveling underlayment to completely level and prepare the floor for an entirely smooth, level, finished floor. Self-leveling product that satisfies the drawings and project specs may be used.
20) Drawing A-301 Partition wall type P1 states to use 1/8” thick acoustical sound barrier at one side of wall. Please provide the product name or specification for this sound barrier. Is this a one integrated sheet or the 1/8” sound barrier can be a independent glued on sheet to gypsum board. Please clarify in detail as majority of the walls are type P1.
VA RESPONSE: ALL offices, treatment rooms, exam rooms as indicated on drawings require 1/8’ acoustical sound barrier for patient privacy requirements. It is up to the contractor’s means and methods to achieve this mandatory requirement for sound proofing each location to meet the requirements of this project specs. This is the contractor’s responsibility to do their due diligence.
21) Drawing AC105 plan legend states remove, store and reinstall ceiling tiles and grid after plumbing work. If we are already removing all the ceiling tiles in the project area as per the demolition drawing and installing new ceiling tiles as per reflected ceiling plan then why we are reinstalling ceiling tiles at some areas per AC105? Please clarify.
VA RESPONSE: In 5B area, the contractor is responsible for replacing any damaged ceiling tiles. Contractor must bid accordingly and match existing tiles.
22) Drawing A401 elevation nos. 1 and 2 indicates Acrylic Privacy Panels. Can agency provide specifications for these panels? Also, the sections 1 and 2 on drawing states these are sliding countertop doors. So, are these fix panels or sliding doors? Please clarify.
VA RESPONSE: This is the contractor’s responsibility to do their due diligence of thorough review of solicitation drawings and specifications.
A401 details #1 &10 calls for where sliding & stationary doors.
23) Drawing A602 shows various interior glazing types SF1 to SF6. Please provide specification section. Also, it indicates to provide STC 50 assembly for type SF3, SF4 and SF5, please confirm if this is required.
VA RESPONSE: Yes, an STC 50 assembly is required for patient privacy requirements. See specification glazing 08 80 00.
24) Drawing A501, detail no.2 states fire extinguisher cabinet by JL Industries, Ambassador series, model 2016. This model no. is not be found with the vendor, please provide the correct name and model no.
VA RESPONSE: The contractor can provide another model, but it must be wall recessed fully set back into the wall cavity and fit a 10lb ABC fire extinguisher.
It’s the contractor’s responsibility to provide the fire extinguishers.
25) Drawing A504 details 5 and 6 are for gypsum board soffits but these are not shown on the reflected ceiling plan/dwg AC106. Please identify these details on drawing AC106.
VA RESPONSE: Refer to AF601 finish schedule comments.
26) Spec sec 08 71 00 hardware set no. HW-3B states door hinges quantity and type as required. As this hardware set is for the majority sound rated doors, please specify the correct type and quantity of hinges required.
VA RESPONSE: See spec 08 71 00-24 (E. Hinges required per door) schedule.
27) Drawing AQ601 calls for Ligature resistant toilet accessories. Is there any specific manufacturer or basis of design?
VA RESPONSE: No preference as long as it satisfies the drawings, specs, and contract documents. Contractor to provide submittals for our review and approval.
28) LVT and Welded Sheet Vinyl: Are there any specific design or directional layouts for these materials?
VA RESPONSE: No. It can be submitted as an RFI during construction.
29) Flooring Pattern and Layout Patterns: Regarding the requirement to see all patterns, planks, accents, and herringbone displayed in the PDF, no layout was provided in the drawings.
VA RESPONSE: Contractor to submit the layout for our review and approval during construction.
30) Drawings and Scaling: Architectural finish floor plan AF106 cannot be used due to an incorrect scale and unclear wall extents caused by heavy markups. Please provide correct scaled drawing.
VA RESPONSE: See updated drawings provided with this amendment as they are all in black & white. Please zoom in on some drawings to review clearly and use Adobe Acrobat for better results.
31) Transitions: If the materials are the same height, should they be butt-jointed without a transition strip?
VA RESPONSE: Transition strips are preferred to the VA. Refer to room finish legend drawing #AF602.
32) Please confirm there is no phasing requirement for this project.
VA RESPONSE: Construction is considered to be a single phase, but may require sub-phases for work required in 5B and hallway/exterior corridor work outside of the locked 6B area. This corridor work will require off-hour and VA COR coordination and approval. Temporary construction barriers may be required for infection control/dust prevention. For these temp barriers, contractors will be required to use a hard barrier in hallway area, which will require sheetrock installation to decking above. Contractors must bid accordingly and assume a hard barrier with anti-room will be required for this work. If VA Engineering determines that this is not necessary during construction, this work will be a credit to the VA.
RFI Set 2 RFI’s continued and are not continuedly numbered:
1. Is there an asbestos survey available?
VA RESPONSE: See amendment and revised SOW, which now includes an area of 17,000 SF for asbestos abatememt.
1. The finish plans seem to not have the .ctb file attached when they plotted. The lineweights and colors make the take-off impossible to do at a precision we can stand-by on our take-off software. Can they kindly replot with the lineweights toggled on?
VA RESPONSE: See updated drawings, they’re all in black & white. Please zoom in on some drawings to review clearly and use Adobe Acrobat for better results.
1. Approximate project start and completion dates?
VA RESPONSE: See period of performance in the solicitation SOW.
1. 1 phase or multi-phase renovation?
VA RESPONSE: It’s 1 phase but 5B (or work outside 6B must be off hours and submitted to COR for approval). See response for RFI #32 above.
1. Temperature Control specification shown on the drawings states all new controls should be integrated to the existing JCI FX Utility Control System. Who is the base building vendor? Please provide contact information.
VA RESPONSE: SEE BELOW CONTACT INFO FOR ITC
CONTRACTOR: ITC.
Daniel DeStefano Project Manager ITC Services 117-19 14rd College Point NY 11356 917-567-9917 718-939-8801
6. Is it the responsibility of the mechanical contractor to perform all demolition as shown on drawings or is this scope under the responsibility of the general contractor?
VA RESPONSE: Awarded SDVOSB firm, will be the Prime GC, and will be responsible for ALL trade work required for this solicitation and all coordination of trades.
7. Is this project being phased per areas?
VA RESPONSE: See the VA response to question #4 and RFI 32 above.
8.Can you please confirm if all of the attached sign types are to be tamperproof?
VA RESPONSE: Confirmed, see drawing AW106.
9.As per AF602/Room Finish legend call out for EPB-1 epoxy wall base. How high is the epoxy wall base?
VA RESPONSE: The VA requires Stonhard Waterproofing Mortar System Also a 3-part system, this option substitutes the primer with Stonclad GS—a ¼" troweled mortar system—providing enhanced impact resistance and a smooth, uniform finish that eliminates surface imperfections. This system may take up to 8-10 days for completion. Epoxy wall base shall be a minimum of 4 inches.
10.Are there any phasing requirements?
VA RESPONSE: See the VA response to question#4 and RFI 32 above.
Work outside 6B must be planned and coordinated with the COR.
11.Stonhard products are proprietary, please confirm if we can price a Dex-O-Tex equal system in lieu of Stonhard system?
VA RESPONSE: NO, Stonhard is required.
RFI’S SET 3:
RFI’S are continued and are not continuously numbered:
1. Please confirm that the project has been filed in DOB. Please provide the filing #s.
VA RESPONSE. This is a federal facility and does not require filing in DOB.
2. Please advise whether the permitting will be handled by Owner or GC.
VA RESPONSE: See the VA response to question #1 in this set of RFI’s above.
3. Are there any existing violations on the property which would trigger the L2 process during permitting? If so, please advise whether this will compensated via change order.
VA RESPONSE: See the VA response to question #1 in this set of RFI’s above.
4. Where can the GC place its trailer / temporary office?
VA RESPONSE: If space is available on the grounds of the VA Medical Center, a GC trailer will be allowed. Contractor is responsible for utilities to the trailer. A temporary office can be used in the construction space. There is no other space withing the medical center to provide a temporary office. This will be discussed during the kick off meting and prior to construction.
5. What areas can be used for storage and staging?
VA RESPONSE: See the VA response to question #4 above in this set of RFI’s.
6. What is the route in and out for materials and debris?
VA RESPONSE: MATERIALS AND DEBRIS WILL BE ROUTED THROUGH THE LOADING DOCK, GROUND FLOOR. ALL CONSTRUCTON DEBRIS MUST BE HAULED IN SERVICE ELEVATORS DURING THE FOLLOIWNG HOURS: WEEKDAYS BEFORE 7AM OR WEEKDAYS AFTER 4PM. ALL DEMOLITION DEBRIS MUST BE PROPERLY COVERED TO PREVENT DUST AND DIRT FROM CONTAMINATING THE HALLWAYS AND PATIENT AREAS.
This will be discussed during the kick off meting before construction.
See facility plans, dumpster, and loading dock.
7. Is there an elevator available for use during construction? What is the weight capacity? What is the size (height, width, depth)?
VA RESPONSE: Yes, there are service elevators on each floor. Capacity is unknown, but standard, general construction material inlcuding sheetrock can be accommodated .
8. Please advise whether Contractor will be able to utilize the facility’s bathroom, water, and electrical facilities.
VA RESPONSE: Yes.
9. Is this an occupied facility during construction?
VA RESPONSE: The construction area of 6B is unoccupied. Hallway offices included in SOW will be unoccupied at the time of construction. However, there is an active patient clinic and inpatient Ward 6C that will be occupied.
10. Are temporary partitions/barriers required in any areas to separate the work area? If so, are there any fire rating requirements? Please provide temp wall layout plan.
VA RESPONSE: See ICRA plan. 5th floor work will need to be phased, planned, and plastic barriers. Also, see response to RFI 32 in the first set of RFI’s above for further clarification on barriers needed.
11. Are there any BIM requirements on this project?
VA RESPONSE: No.
12. Are there any allowances on this project?
VA RESPONSE: Yes. There is a $100,000 allowance on this project. Please see revised bid sheet and instruction in this amendment.
13. Are there any unit price requirements on this project?
VA RESPONSE: No.
14. Are there any alternates on this project?
VA RESPONSE: No.
15. Are there any LEED requirements on this project?
VA RESPONSE: No.
16. Who is the Agency CM (CMa) for this project?
VA RESPONSE: VA COR.
17. Please specify any delegated design work that the Contractor is responsible for.
VA RESPONSE: There is no design work. This project has been designed the an AE firm, Bancroft Engineers as per solicitation specs and drawings. See plans, specs, and contract documents.
18. Please clarify any and all items that the owner will be providing for contractor installation.
VA RESPONSE: See plans, specs, and contract documents.
19. Who is the building’s designated/proprietary Fire Alarm vendor/contractor? Please provide name, email, and phone number to the contact representative. This is important information for Electrical subcontractors since they will be carrying their price.
VA RESPONSE: Johnson controls.
20. Who is the building’s designated/proprietary BMS and Controls vendor/contractor? Please provide name, email, and phone number to the contact representative. This is important information for HVAC subcontractors since they will be carrying their price.
ITC.
Daniel DeStefano Project Manager ITC Services 117-19 14rd College Point NY 11356 917-567-9917 718-939-8801
21. Please specify whether there will be any required off-hour, after hours, night work, and/or weekend work required throughout the duration of this job.
VA RESPONSE: All corridor work outside of the 6B area and within the SOW of this project and 5th floor work will be off hours and weekends.
22. Please confirm that all noisy work and anything causing disturbance to the facility’s normal daily activities is to be performed after hours.
VA RESPONSE: Confirmed.
23. Please confirm that all abatement is to be performed after hours.
VA RESPONSE: No.
24. Please confirm that all demolition is to be performed after hours.
VA RESPONSE: No. 5B exterior corridor work only.
25. Please confirm that all shutdowns are to be performed after hours.
VA RESPONSE: All shutdowns to be coordinated with the COR, and most will not require off-hours unless it is directly affecting patient care areas and will exceed a 4-hour time frame.
26. Please confirm that all tie-in work is to be performed after hours.
VA RESPONSE: Confirmed.
27. Please confirm that all soldering is to be performed after hours.
VA RESPONSE: No, this is not necessary. Contractor will require hot work permits daily and coordination and approval of the VA Safety Office prior to soldering work.
28. Please confirm that all core drilling is to be performed after hours.
VA RESPONSE: Not required to be performed after hours.
29. Please specify whether is any phasing requirements on this project VA RESPONSE: See RFI responses above regarding phasing, including RFI #4 and 32 . It’s 1 phase but 5B (or work outside 6B must be off hours and submitted to COR for approval).
30. Please confirm that in the event of conflicting provisions within the bid documents, the more expensive option should be included within the bid price.
VA Response: Confirmed.
31. Is there any parking near the building for Contractor personnel?
VA RESPONSE: Yes, however, parking is extremely limited.
32. Please advise whether Owner will be vetting the GC’s and Asbestos Subcontractor’s full liability insurance policy (in addition to COI) for compliance with Owner general conditions as condition of award.
VA RESPONSE: No.
33. Please advise whether Hammer Clause in GC’s general liability policy is acceptable by Owner.
VA RESPONSE: No.
34. What is the deadline for RFI submissions?
Several key vendors and subcontractors have requested bid date extensions.
VA RESPONSE: The cut off for RFI’s has passed. No further RFI’s will be accepted for this solicitation. A bid extension is provided in this amendment. Please see details on SF30.
RFI SET 4:
1. Drawings are from 2022. All the nurse call items don’t seem to exist anywhere but eBay. I’m guessing this stuff has been discontinued for a while.
VA RESPONSE: See attached submittals provided in this amendment for the recent installed system in our facility.
2. Paging, they want everything to match the existing, but don’t tell you what the existing specs are.
VA RESPONSE: See attached submittals provided in this amendment for the recent installed system in our facility.
END OF RFI RESPONSES
NOTE: SEE ATTACHED REVISED SOW THAT INCREASES THE ASBESTOS ABATEMENT AREA TO ENTIRE CONSTRUCTION SITE, APPROX 17,000 SF, AND REVISED BID SHEET THAT INCLUDES AN ADDED ALLOWANCE OF $100,000.00 TO BE INCLUDED AS A SEPARATE LINE ITEM ON BID SHEET.
Contractors must bid accordingly based on solicitation drawings, specifications, revised drawings provided in the amendment specifically listed, revised SOW, and all RFI responses provided above.
Thank you.
CONTINUATION PAGE
AMENDMENT A0001-RFI RESPONSES AND SOW CLARIFICATIONS
IFB 36C24226B0002 RENOVATE 6B FOR OUTPATIENT MENTAL HEALTH
THIS IS AMENDMENT A0001 TO IFB 36C24226B0002 RENOVATE 6B FOR OUTPATIENT MENTAL HEALTH This amendment provides the following:
1. Mandatory Site Visit Sign In sheet conducted on 1.21.2026 (attached)
2. Revised SOW to include additional asbestos abatement of entire construction area, estimated at 17,000 SF (attached)
3. Revised Bid Sheet to include a line item 2 allowance for $100,000.00, to be included in the total amount of the bid as instructed on the revised bid sheet. Contractors must include this $100,000.00 as line item 2 with their submitted bid and utilize the revised bid sheet (attached).
4. Provide revised drawings for the following only: A106.1, A106.2, A106.3, A601, AF106, AF601, AF602, P106.1, P106.2, P601, MV406, M601, E601, E602, E701, E703, EL106, and ES106. Other than the drawings noted here, ALL other solicitation drawings are unchanged.
5. Provide revised and current Hill-Rom specs for this project. (attached)
A bid extension has been granted for this solicitation: The Bid Opening date is now 2.26/2026 at 2PM EST. No emailed bids will be accepted for this solicitation. Please follow the instructions on the solicitation SF 1442 accordingly.
Also, this amendment confirms that bids will only be accepted from firms who attended the mandatory site visit held on 1/21/2026 at 10AM. See attached site visit sign in sheet.
Thank you for your interest in this solicitation.
Pat
See attached document: REVISED BID SHEET_RENOVATE 6B FOR MH.
See attached document: SOW - Renovate 6B for Outpatient Mental Health Rev1-Pat.
See attached document: MANDATORY SITE VISIT SIGN IN SHEET_6B FOR MH_1.21.26.
See attached document: HILL ROM SPEC- RFI RESPONSE.
See attached document: 526-19-122 BID DWG_2026 UPDATED.