This document is a modification to an existing solicitation for a contract to provide elevator service and maintenance at the Northport VA Medical Center. The key changes are:
The contractor's technician is now required to be on-site 5 days per week, 40 hours per week, instead of once per week. The contract period has been changed from 4/19/2024 - 3/31/2029 to 6/1/2024 - 5/31/2029. The working hours have been updated from 8:00 AM - 4:30 PM to 7:00 AM - 3:30 PM, Monday through Friday, excluding holidays. The overall scope of the elevator service and maintenance remains unchanged, requiring the contractor to provide all necessary labor, materials, supervision, tools, and supplies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24224Q0245 0002.docx | DOCX document | |
| 1B ATTACHMENT B.pdf | ||
| 1C ATTACHMENT C.pdf | ||
| Service Contract Act WD 2015-4157.pdf | ||
| 1D ATTACHMENT D.pdf | ||
| Davis-Bacon Act WD NY20240012.pdf | ||
| P09 - QASP.docx | DOCX document | |
| 36C24224Q0245.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Changes to Performance Work Statement
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) Department of Veterans Affairs Samuel S . Stratton VA Medical Center 113 Holland Avenue (2-90NCA) Albany
NY
12208-3410 Department of Veterans Affairs Samuel S . Stratton VA Medical Center Network Contracting Activity 113 Holland Avenue (2-90NCA) Albany
NY
12208-3410 To all Offerors/Bidders
36C24224Q0245 05-03-2024
X X X
See CONTINUATION Page X The purpose of this modification is the make changes to the Performance Work Statement (PWS) inserted in solicitation 36C24224Q0245. Please see continuation page for changes made to the PWS.
Charles Collins Contract Specialist
CONTINUATION PAGE
1. Page 5 – B2 – PWS line #4, currently states: “technician shall be on site once per week.”
This shall change to: “The Contractor’s technician shall be on-site at the facility 5 days a week, 40 hours/week during the duration of this contract.”
2. Page 5 – PWS(A), Currently States: “This requirement is for elevator service and maintenance agreements for elevators located at the Northport VA Medical Center, 79 Middleville Rd., Northport NY 11768 from 04/19/2024 to 03/31/2029. The service and maintenance agreements shall include all material, labor, supervision, tools, supplies, and any other items necessary to perform.”
This shall change to: “This requirement is for elevator service and maintenance agreements for elevators located at the Northport VA Medical Center, 79 Middleville Rd., Northport NY 11768 from 06/01/2024 to 05/31/2029. The service and maintenance agreements shall include all material, labor, supervision, tools, supplies, and any other items necessary to perform:”
3. Page 6 - B2.1.3(A) Currently states: “Working Hour, the maintenance work outlined in this PWS shall be performed during normal working hours of 8:00 AM to 4:30 PM, Monday through Friday, holidays excepted.”
This shall change to: “The maintenance work outlined in this PWS shall be performed during normal working hours of 7:00 AM to 3:30 PM, Monday through Friday, holidays excepted.”