This document outlines a Quality Assurance Surveillance Plan (QASP) for janitorial services at the James J. Peters VA Medical Center in Bronx, New York. The QASP defines performance standards and acceptable quality levels for daily, weekly, monthly, and quarterly cleaning services. It identifies the roles of the Contracting Officer, Contracting Officer's Representative, and contractor representatives in monitoring performance. Standards are defined for cleaning tasks, restrooms, locker rooms, and inspection methods. Performance is rated on a scale from exceptional to unsatisfactory, with corrective action and documentation requirements for unacceptable work. The frequency of surveillance and performance reporting is also specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24223Q1166 0003.docx | DOCX document | |
| FILLABLE PRICE SCHEDULE REV.xlsx | XLSX spreadsheet | |
| 36C24223Q1166 0003.pdf | ||
| Questions Temporary Janitorial 2.docx | DOCX document | |
| 36C24223Q1166 0002.docx | DOCX document | |
| Questions Temporary Janitorial.docx | DOCX document | |
| Past Performance Evaluation Questionnaire.docx | DOCX document | |
| 36C24223Q1166 0002.pdf | ||
| FILLABLE PRICE SCHEDULE.xlsx | XLSX spreadsheet | |
| LIMITATIONS ON SUBCONTRACTING CERTIFICATION.docx | DOCX document | |
| Wage Determination Janitorial.pdf | ||
| 36C24223Q1166 Janitorial Services.pdf | ||
| Questions.docx | DOCX document | |
| 36C24223Q1166 0001_1.docx | DOCX document | |
| 36C24223Q1166 0001.pdf | ||
| Wage Determination 1977-0225.pdf | ||
| Site Visit Info BX - Janitorial.docx | DOCX document | |
| 36C24223Q1166_3.docx | DOCX document | |
| 36C24223Q1166_2.docx | DOCX document | |
| 36C24223Q1166.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
1. PURPOSE
This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
· What will be monitored?
· How monitoring will take place?
· Who will conduct the monitoring?
· How will monitoring efforts and results be documented?
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the QASP should recognize that unforeseen and uncontrollable situations may occur.
This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the contractor through task order modifications. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
2. GOVERNMENT ROLES AND RESPONSIBILITIES
The following personnel shall oversee and coordinate surveillance activities.
a. Contracting Officer (CO) - The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the task order terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also ensure that the contractor receives impartial, fair, and equitable treatment under the task order. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
Assigned Administrative Contracting Officer: Andres Cepeda Contract Specialist Network Contracting Activity 2 151 Knollcroft Road Lyons, NJ 07939 Phone: 908-900-8915 Email: andres.cepeda@va.gov
b. Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the task order and shall ensure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.
| Assigned COR: | Christopher Spence | |
| Assist. Housekeeping Officer | ||
| James J. Peters VA Medical Center | ||
| 130 West Kingsbridge Rd | ||
| Bronx, NY 10468 |
Phone: 718-584-9000 x1160 Email: Christopher.spence@va.gov
3. CONTRACTOR REPRESENTATIVES
The following employee(s) of the contractor serve as the contractor’s program manager for this contract.
Primary Contact:
Alternate Contact:
4. PERFORMANCE STANDARDS
The contractor is responsible for performance of ALL terms and conditions of the task order. CORs will provide task order progress reports quarterly to the CO reflecting performance on this plan and all other aspects of the resultant task order. The performance standards outlined in this QASP shall be used to determine the level of task order performance in the elements defined. Performance standards define desired services. The Government performs surveillance to determine the level of task order performance to these standards.
The Performance Requirements are listed below in Section 6. The Government shall use these standards to determine task order performance and shall compare the task order performance to the standard and assign a rating. At the end of the performance period, these ratings will be used, in part, to establish the past performance of the contractor on the task order.
5. METHODS OF QA SURVEILLANCE
Various methods exist to monitor performance. The COR shall use the surveillance method listed below in the administration of this QASP.
· DIRECT OBSERVATION. 100% surveillance: Clinic management staff will observe on an ongoing basis contractor performance in the clinic environment to ensure patient satisfaction and patient access standards are maintained. Deviations from performance requirements will be documented as they occur and reported to the Chief of Medicine and COR for validation.
· PERIODIC INSPECTION. Evaluates outcomes on a periodic basis or as needed. Inspections may be scheduled or unscheduled, as required. Patient treatment files to be reviewed will be randomly selected on a quarterly basis. All inspections and reports will be conducted in compliance with VA Privacy and Information security standards.
· VALIDATED USER/CUSTOMER COMPLAINTS. Relies on patient reporting to identify deficiencies. Complaints are then investigated and validated.
| Measures |
| PWS |
Reference Performance Requirement
| Standard |
| Acceptable Quality Level |
| Surveillance |
Method
| Incentive |
| Disincentive/Deduct |
Daily cleaning
| PWS Section 10; Tasks and Cleaning Standards |
| Perform all services listed as Daily cleaning in Section 10; Tasks and Cleaning Standards |
| Complete the full scope of daily cleaning service per the PWS. |
| 80% |
| Direct Observation of completed work and periodic inspection. Validation from clinical staff regarding cleanliness. |
| Favorable performance evaluation. |
| May reflect poor contract performance report. |
| Daily cleaning |
| PWS Section 10; Tasks and Cleaning Standards |
| Restrooms & |
Locker Room
Complete the full scope of daily cleaning service per the PWS.
| 95% |
| Direct Observation of completed work and periodic inspection. Validation from clinical staff regarding cleanliness |
| Favorable performance evaluation. |
| May reflect poor contract performance report. |
| Weekly Cleaning |
| PWS Section 10; Tasks and Cleaning Standards |
| Perform all services listed as Weekly cleaning in Section 10; Tasks and Cleaning Standards |
| Complete the full scope of the weekly cleaning services per the PWS. |
| 90% |
| Direct Observation of completed work and periodic inspection. Validation from clinical staff regarding cleanliness. |
| Favorable performance evaluation. |
| May reflect poor contract performance report. |
| Monthly Cleaning |
| PWS Section 10; Tasks and Cleaning Standards |
| Perform all services listed as Monthly cleaning in Section 10; Tasks and Cleaning Standards |
| Complete the full scope of the Monthly cleaning services per the PWS. |
| 90% |
| Direct Observation of completed work and periodic inspection. Validation from clinical staff regarding cleanliness. |
| Favorable performance evaluation. |
| May reflect poor contract performance report. |
| Quarterly Cleaning |
| PWS Section 10; Tasks and Cleaning Standards |
| Perform all services listed as Quarterly cleaning in Section 10; Tasks and Cleaning Standards |
| Complete the full scope of the Quarterly Cleaning Services per the PWS. |
| 95% |
| Direct Observation of completed work. |
| Favorable performance evaluation. |
| May reflect poor contract performance report. |
6. RATINGS
Metrics and methods are designed to determine if performance exceeds, meets, or does not meet a given standard and acceptable quality level. A rating scale shall be used to determine a positive, neutral, or negative outcome. The following ratings shall be used:
| EXCEPTIONAL |
| Performance meets task order requirements and exceeds many to the Government’s benefit. The task order performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective. |
Note: To justify an Exceptional rating, you should identify multiple significant events in each category and state how it was a benefit to the GOVERNMENT. However, a singular event could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
| VERY GOOD |
| Performance meets task order requirements and exceeds some to the Government’s benefit. The task order performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective. |
Note: To justify a Very Good rating, you should identify a significant event in each category and state how it was a benefit to the GOVERNMENT. Also, there should have been NO significant weaknesses identified.
| SATISFACTORY |
| Performance meets task order requirements. The task order performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory. |
Note: To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract. Also, there should have been NO significant weaknesses identified.
| MARGINAL |
| Performance does not meet some task order requirements. The task order performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented. |
Note: To justify Marginal performance, you should identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g. Management, Quality, Safety or Environmental Deficiency Report or letter).
| UNSATISFACTORY |
| Performance does not meet most task order requirements and recovery is not likely in a timely manner. The task order performance of the element or sub-element being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective. |
Note: To justify an Unsatisfactory rating, you should identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. However, a singular problem could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g. Management, Quality, Safety or Environmental Deficiency Reports, or letters).
7. DOCUMENTING PERFORMANCE
· ACCEPTABLE PERFORMANCE: The Government shall document positive performance. Any report may become a part of the supporting documentation for any task order action by preparing annual past performance using CONTRACTOR PERFORMANCE ASSESSMENT REPORT (CPAR).
· UNACCEPTABLE PERFORMANCE: When the task order does not meet the acceptable quality level, the CO shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case, the CO shall document the discussion and place it in the task order file.
· If the CO and COR determine formal written communication is required, the COR shall prepare a Contract Discrepancy Report (CDR), present it to the CO for review and who will in turn present it to the contractors program manager.
· The contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR will also state how long after the receipt the contractor has to present this corrective action plan to the CO. The Government shall review the contractor’s corrective action plan to determine acceptability. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance and the acceptability of the Contractor’s corrective action plan.
· Any CDRs may become part of the supporting documentation for any task order action deemed necessary by the CO. Sample CDR below.
CONTRACT DISCREPANCY REPORT
| 1. CONTRACT NUMBER |
| 2. REPORT NUMBER FOR THIS DISCREPANCY |
| 3. TO: (Contracting Officer) |
| 4. FROM: (Name of COR) |
5. DATES
a. CDR PREPARED
| b. RETURNED BY CONTRACTOR: |
| c. ACTION COMPLETE |
6. DISCREPANCY OR PROBLEM (Describe in detail. Include reference to PWS Directive; attach continuation sheet if necessary.)
| 7. SIGNATURE OF COR |
| Date: |
| 8. SIGNATURE OF CONTRACTING OFFICER |
| Date: |
| 9a. TO (Contracting Officer) |
| 9a. FROM (Contractor) |
10. CONTRACTOR RESPONSE AS TO CAUSE, CORRECTIVE ACTION AND ACTIONS TO PREVENT RECURRENCE. (Cite applicable quality control program procedures or new procedures. Attach continuation sheet(s) if necessary.)
| 11. SIGNATURE OF CONTRACTOR REPRESENTATIVE |
| Date: |
12. GOVERNMENT EVALUATION. (Acceptance, partial acceptance, reflection. Attach continuation sheet(s) if necessary.)
13. GOVERNMENT ACTIONS (Acceptance, partial acceptance, reflection. Attach continuation sheet(s) if necessary.)
14. CLOSE OUT
| NAME |
| TITLE |
| SIGNATURE |
| DATE |
CONTRACTOR NOTIFIED
COR
CONTRACTING OFFICER
8. FREQUENCY OF MEASUREMENT
· Frequency of Measurement. The frequency of measurement is defined in the task order or otherwise in this document. The government (COR or CO) will periodically analyze whether the frequency of surveillance is appropriate for the work being performed.
· Frequency of Performance Reporting. The COR shall communicate with the contractor and will provide written reports to the CO quarterly (or as outlined in the task order or COR delegation) to review task order performance.
9. COR AND CONTRACTOR ACKNOWLEDGEMENT OF QASP
SIGNED:
COR NAME/TITLE DATE
SIGNED:
CONTRACTOR NAME/TITLE DATE