528-21-122_Combined Drawing Set_Final.pdf
PDF 14 MB Posted
- Attached to
- Z1DA--528-21-122 PARKING LOT REPAIRS-BUFFALO
- Solicitation number
- 36C24222B0058
About this file
This document outlines the scope of work for a federal construction contract to perform parking lot repairs at the VA Western New York Healthcare System Buffalo VA Medical Center. The project involves cold milling and removal of existing asphalt, installation of a new underground duct bank and pull boxes, placement of asphalt binder and top courses, pouring new concrete curb and sidewalk, asphalt crack sealing, fog sealing, and installation of new thermoplastic and painted pavement markings across nine separate work areas. The contractor must submit plans, schedules, and safety documentation for approval and attend regular meetings to discuss progress. Work is to be completed within four months of award according to the phasing plan with most work occurring outside normal operating hours. The contractor will perform inspections, address any issues found, and coordinate warranty repairs with manufacturers as needed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24222B0058 0002.docx | DOCX document | |
| 528-21-122 Pre Bid Site Survey Sign in Sheet (002).pdf | ||
| 528-21-122 Table of Estimated Quantities.pdf | ||
| 36C24222B0058 0001.docx | DOCX document | |
| 528-21-122 FINAL COMBINED PROJECT SPECS (3).pdf | ||
| WAGE DETERMINATION - ny50.pdf | ||
| VHA Supplemental Contract Requirements for Combatting COVID-19 Updated 12-14-2021.docx | DOCX document | |
| VA Notice of Limitations on Subcontracting.docx | DOCX document | |
| 36C24222B0058_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
CS-100
COVER SHEET
A
FOR CONSTRUCTION
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING LOT REPAIRS
BUFFALO 528
21-122
N/A Project Director
APRIL 12, 2022 MTA RJCRevisions: Date:
528-21-122
PARKING LOT REPAIRS
BUFFALO VA MEDICAL CENTER
3495 Bailey Avenue Buffalo, NY 14215
DRAWING INDEX
PROJECT 528-21-122 DRAWING LIST
DRAWING NUMBER DRAWING NAME
CS-100 COVER SHEET
CN-100 GENERAL NOTES
CP-100 REPAIR AREAS 1, 2, 3, 4, 5 AND 6
CP-101 REPAIR AREAS 7, 8 AND 9; CONCRETE NOTES AND DETAILS
CP-102 AREA STRIPING PLANS AND DETAILS
CU-100 UNDERGROUND DUCT BANK
N/A BUFFALO VA MEDICAL CENTER
ROBERT CEBULSKI, P.E.
GENERAL ENGINEER
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
CN-100
GENERAL NOTES
A
FOR CONSTRUCTION
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING LOT REPAIRS
BUFFALO 528
21-122
N/A Project Director
APRIL 12, 2022 MTA RJCRevisions: Date:
N/A BUFFALO VA MEDICAL CENTER
ROBERT CEBULSKI, P.E.
GENERAL ENGINEER
GENERAL SITE CONSTRUCTION NOTES
1. THE EXACT OR EVEN APPROXIMATE LOCATION OF SUBSURFACE STRUCTURES AND/OR UTILITIES IN THE WORK AREAS ARE GENERALLY UNKNOWN. IT IS THE
RESPONSIBILITY OF THE CONTRACTOR TO PROCEED WITH GREAT CARE IN EXECUTING ANY WORK. CALL DIG SAFELY NEW YORK, TELEPHONE NUMBER. 811, 48 HOURS BEFORE YOU DIG, DRILL OR BLAST. UTILIZE INDUSTRY BEST PRACTICES WHEN EXCAVATING IN AREAS OF POTENTIALLY UNKNOWN UNDERGROUND FACILITIES. NOTE THAT ALL TRENCHING EXCAVATION MUST BE COMPLETED VIA HYDRO EXCAVATION.
2. THE CONTRACTOR SHALL LOCATE, MARK, SAFEGUARD, AND PRESERVE ALL SURVEY CONTROL MONUMENTS IN THE AREAS OF CONSTRUCTION.
3. THE CONTRACTOR SHALL MAINTAIN IN SERVICE ALL EXISTING SEWERS, CULVERTS, DITCHES, MANHOLES, UNDERGROUND UTILITIES AND CATCH BASINS
DURING CONSTRUCTION.
4. TRAFFIC SHALL BE MAINTAINED THROUGHOUT CONSTRUCTION. INGRESS AND EGRESS TO DRIVEWAYS, PARKING LOTS, AND SERVICE ROADS SHALL BE CONTINUOUSLY MAINTAINED THROUGHOUT THE PERIOD OF CONSTRUCTION. EXCAVATIONS SHALL BE BACKFILLED THE SAME WORK DAY WHERE POSSIBLE.
ROAD PLATES OR OTHER TEMPORARY METHODS OF SAFELY BRIDGING AND PROTECTING OPEN EXCAVATIONS MAY BE REQUIRED WHERE OPEN EXCAVATIONS
CANNOT BE BACKFILLED ON THE SAME WORK DAY.
5. THE CONTRACTOR SHALL TAKE CARE TO PREVENT DAMAGE TO EXISTING UTILITIES. DAMAGED UTILITIES SHALL BE IMMEDIATELY REPAIRED AND DOCUMENTED BY THE CONTRACTOR AT THE CONTRACTOR'S EXPENSE. THE COR SHALL BE NOTIFIED IMMEDIATELY OF ANY DAMAGES THAT OCCUR.
6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING AND INCURRING THE COST OF ALL REQUIRED PERMITS, INSPECTIONS, CERTIFICATES, ETC. AND SHALL COMPLY WITH ALL REQUIRED PERMITS. NOTE THAT THE VA MAY REQUEST THE CONTRACTOR TO UTILIZE A THIRD PARTY INDEPENDENT TESTING AGENCY TO PROVIDE MATERIAL TESTING AT THE VA'S DISCRETION. A CONCRETE TEST, SUBBASE DENSITY TEST, AND TOPSOIL TEST SHOULD BE
ANTICIPATED, WITH THE TOTAL NUMBER OF ON SITE TESTS NOT TO EXCEED FIVE (5).
7. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING ALL LABOR AND EQUIPMENT NEEDED FOR TRAFFIC AND PEDESTRIAN CONTROL AND SAFETY MEASURES.
8. ALL WORK SHALL BE DONE IN STRICT COMPLIANCE WITH ALL APPLICABLE NATIONAL AND STATE CODES, STANDARDS, ORDINANCES, RULES, AND
REGULATIONS.
9. MISCELLANEOUS WORK NOT SPECIFICALLY SHOWN ON THE CONTRACT DRAWINGS SUCH AS PATCHING, BLOCKING, TRIMMING, ETC. SHALL BE PERFORMED AS
REQUIRED TO MAKE THE WORK COMPLETELY FUNCTIONAL.
10. WHILE THE BEST EFFORT WAS MADE TO DETAIL ALL POSSIBLE PARTS AND MATERIALS FOR THIS PROJECT, IT IS THE CONTRACTORS RESPONSIBILITY TO PROVIDE ANY AND ALL PARTS/MATERIALS NOT DETAILED IN THE PROJECT PLAN THAT ARE REQUIRED TO COMPLETE THE PROJECT. PURCHASING NECESSARY MATERIALS THAT WERE NOT DETAILED IN THE PLANS DOES NOT CONSTITUTE BASIS FOR A CHANGE ORDER. ANY ADDITIONAL MATERIAL PURCHASES WITHIN
THE PROJECT SCOPE SHALL BE SUBMITTED TO THE VA PROJECT STAFF FOR APPROVAL.
11. IT IS THE CONTRACTOR'S RESPONSIBILITY TO EXAMINE ALL PLAN SHEETS AND COORDINATE WORK WITH ANY OTHER CONTRACTS FOR THE SITE.
12. THE CONTRACTING OFFICER AND CONTRACTING OFFICER'S REPRESENTATIVE SHALL BE NOTIFIED, IN WRITING, OF ANY CONDITIONS THAT VARY FROM THOSE SHOWN ON THE PLANS. THE CONTRACTOR'S WORK SHALL NOT VARY FROM THE PLANS WITHOUT PRIOR WRITTEN APPROVAL OF THE CONTRACTING 0FFICER.
13. ASPHALT MIXES SHALL BE: BINDER COURSE NYSDOT 19MM F2; TOP COURSE NYSDOT 9.5MM F2. BOTH POLYMER MODIFIED HMA, 80 SERIES COMPACTION IN
ACCORDANCE WITH NYSDOT SPECIFICATION SECTION 402-3.07.D.
14. CONTRACTOR SHALL BE RESPONSIBLE TO COMPLETE PAVEMENT PAINTING (DRIVEWAYS, PARKING LOT STRIPING, PEDESTRIAN CROSSWALKS, STOP BARS, TURN ARROWS, CURBS, AND OTHER AREAS DETAILED ON SHEET CP-102).
15. CONTRACTOR TO PURCHASE AND INSTALL APPROVED SIGNS AS DETAILED ON SHEET CP-102.
AREA 2
AREA 3 AREA 4
AREA 5
AREA 6
AREA 7
AREA 8
AREA 1
AREA 9
AREA LOCATION MAP
17. THE CONTRACTOR SHALL RESTORE LAWNS, DRIVEWAYS, CULVERTS, SIGNS, AND OTHER PUBLIC OR PRIVATE PROPERTY DAMAGED OR REMOVED DURING CONSTRUCTION TO AT LEAST AS GOOD A CONDITION AS BEFORE BEING DISTURBED AT NO ADDITIONAL COST TO THE VA. ANY DAMAGED TREES, SHRUBS, AND/OR HEDGES
SHALL BE REPLACED AT THE CONTRACTOR'S EXPENSE.
18. UNSUITABLE MATERIALS SHALL BE REMOVED FROM THE SITE AND PROPERLY DISPOSED.
19. ALL WORK THAT REQUIRES UTILITY SERVICE INTERRUPTION SHALL REQUIRE A SHUTDOWN SUBMITTAL REQUEST FROM THE CONTRACTOR TO THE VA. SUCH SUBMITTAL SHALL BE GIVEN WITH AT LEAST TWO WEEKS NOTICE OF PROPOSED DATE FOR WORK. UTILITY SERVICE INTERRUPTIONS OR SHUTDOWNS SHALL BE
COMPLETED ON WEEKENDS, IN COORDINATION WITH THE VA.
20. PROVIDING, INSTALLING, COMMISSIONING AND WARRANTY OF ALL PARTS/MATERIALS INSTALLED IN THIS PROJECT IS THE RESPONSIBILITY OF THE
CONTRACTOR.
21. THE CONTRACTOR SHALL AVOID LEAVING OPEN EXCAVATIONS OR UNCOMPLETED WORK THAT MAY POSE A HAZARD TO VEHICLE AND PEDESTRIAN TRAFFIC. IF NEEDED OR AS DIRECTED BY THE COR, THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING AND ERECTING ANY FENCING, BARRICADES OR OTHER TRAFFIC OR
PEDESTRIAN PROTECTION DEVICES AT NO ADDITIONAL COST TO THE VA.
22. ASPHALT SEALING (FOG SEAL) REQUIRES 2 COATS OF SEALANT. THE FIRST COAT SHALL BE SQEEGEE APPLIED, WHILE THE SECOND COAT MAY BE SPRAY APPLIED.
23. THE CONTRACTOR IS ADVISED TO REVIEW ALL PROJECT SPECIFICATIONS.
24. THE BOTTOM OF THE UNDERGROUND DUCT BANK TRENCH SHALL BE PITCHED BOTH WAYS TOWARDS PULLBOXES. SLOPE DUCTS TO DRAIN TOWARDS PULL BOXES
AT A RATE OF 4-INCHES OVER 100-FEET.
25. CONDUIT RUNS SHALL HAVE SPACERS, SEPARATING THE CONDUIT BY 3-INCHES AND BE UNIFORMLY SPACED A MAXIMUM OF 5-FEET APART. SECURE SPACERS TO CONDUIT AND EARTH TO PREVENT FLOATING DURING THE CONCRETE POUR. PROVIDE NONFERROUS TIE WIRES TO PREVENT DISPLACEMENT OF THE CONDUIT
DURING THE POUR.
26. THE WALLS OF THE TRENCH MAY BE USED TO FORM THE SIDE WALLS OF THE DUCT BANK, PROVIDED THAT THE SOIL IS SELF SUPPORTING AND THAT THE CONCRETE ENVELOPE CAN BE POURED WITHOUT SOIL INCLUSIONS. FORMS WILL BE REQUIRED WHERE THE SOIL IS NOT SELF SUPPORTING.
27. AFTER THE CONCRETE ENCASED DUCT HAS SUFFICIENTLY CURED, THE TRENCH SHALL BE BACKFILLED TO GRADE WITH MATERIALS SPECIFIED ON SHEET CU-100, INCLUDING PLACEMENT OF WARNING TAPE.
28. THE MEDICAL CAMPUS MUST REMAIN OPEN TO ACCOMMODATE PATIENTS, VISITORS AND EMPLOYEES DURING NORMAL OPERATING HOURS (7:00 AM - 4:30 PM, MONDAY THOUGH FRIDAY). THE VAST MAJORITY OF WORK ASSOCIATED WITH THIS PROJECT MUST OCCUR OUTSIDE OF NORMAL OPERATING HOURS. NIGHT AND
WEEKEND WORK IS REQUIRED.
29. THE CONTRACTOR MUST UTILIZE DUST CONTROL MEASURES FOR ANY ACTIVITY THAT MAY GENERATE DUST, INCLUDING BUT NOT LIMITED TO SAW CUTTING, PLACEMENT AND COMPACTION OF MATERIALS AND MILLING. WATER IS THE MOST COMMON DUST CONTROL MEASURE AND SHALL BE UTILIZED AS AND WHERE NEEDED.
WATER FROM THE VA MAY NOT BE AVAILABLE FOR ALL WORK AREAS. THE CONTRACTOR SHALL HAVE A PORTABLE SOURCE OF WATER AVAILABLE TO USE AS NEEDED.
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
CP-100
REPAIR AREAS 1, 2, 3, 4, 5 AND 6
A
FOR CONSTRUCTION
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING LOT REPAIRS
BUFFALO 528
21-122
N/A Project Director
APRIL 12, 2022 MTA RJCRevisions: Date:
N/A BUFFALO VA MEDICAL CENTER
ROBERT CEBULSKI, P.E.
GENERAL ENGINEER
AREA 1
AREA 1 WORK INCLUDES THE FOLLOWING ITEMS:
1. SAW CUT EXISTING ASPHALT TO ACCOMMODATE REMOVAL OF THE EXISTING CONCRETE ISLAND. REMOVE AND DISPOSE OF CONCRETE DOWN TO EXISTING
SUBBASE MATERIAL.
2. REMOVE AND DISPOSE OF EXISTING PORTABLE CONCRETE AND STEEL BOLLARDS. QUANTITY IS LESS THAN 10. REFER TO PHOTO 4 BELOW.
3. MILL EXISTING ASPHALT SURFACE DOWN TO EXISTING SUBBASE MATERIAL. LIMITS OF MILLING SHOWN ABOVE.
4. APPLY TACK COAT TO EXISTING ASPHALT EDGES, PLACE AND COMPACT BINDER AND TOP COURSE OF HOT MIX ASPHALT WHERE CONCRETE ISLAND WAS REMOVED AND WHERE ASPHALT WAS MILLED. DEPTH OF BINDER TO BE 3-INCHES MAXIMUM, DEPTH OF TOP COURSE TO BE 2-INCHES MAXIMUM; OR MATCH EXISTING IF LESS.
5. SEAL ALL NEW PAVEMENT SEAMS USING A HOT APPLIED POLYMERIC JOINT SEALANT (WR MEADOWS HI-SPEC OR APPROVED EQUAL).
6. AFTER NEW PAVEMENT INSTALLATION, CLEAN AND SEAL ALL EXISTING PAVEMENT CRACKS MEASURING 18" OR GREATER IN WIDTH USING A HOT APPLIED POLYMERIC
JOINT SEALANT (WR MEADOWS HI-SPEC OR APPROVED EQUAL).
7. RE-STRIPE THE PARKING LOT SPACES (APPROXIMATELY 5200 LF OF 4-INCH WIDE YELLOW PAINT STRIPING).
P1 V
P1
P2
P2
V
P3
P3V
CONCRETE ISLAND TO BE REMOVED
P1V
P1
AREA 2
AREA 2 WORK INCLUDES THE FOLLOWING ITEMS:
1. THE CONTRACTOR IS RESPONSIBLE FOR SECURING ANY RIGHT-OF-WAY (ROW) WORK PERMITS THAT MAY BE REQUIRED FOR IMPROVEMENTS PLANNED WITHIN
THE BAILEY AVENUE ROW.
2. CONTRACTOR MUST PROVIDE TRAFFIC CONTROL LABOR AND EQUIPMENT AS NEEDED TO PERFORM WORK.
3. SAW CUT EXISTING ASPHALT, SIDEWALK AND CONCRETE CURB TO ACCOMMODATE EXCAVATION FOR AND INSTALLATION OF UNDERGROUND DUCT BANK (REFER TO SHEET CU-100). SIDEWALK SHALL BE CUT AT EXISTING JOINTS. CURB WILL BE CUT THE SAME WIDTH AS THE TRENCH (APPROXIMATELY 24-INCHES) EXCEPT
WHERE NOTED FOR COMPLETE REMOVAL AND REPLACEMENT.
4. INSTALL CONDUIT AND PULL / JUNCTION BOXES AS DETAILED ON SHEET CU-100.
5. ENCASE CONDUIT IN CONCRETE. BACKFILL AREAS UNDER PAVEMENT OR CONCRETE WITH CRUSHED LIMESTONE, GRADE AND COMPACT MATERIAL TO PROVIDE
A SUITABLE SUBBASE. REFER TO DETAILS ON SHEET CU-100.
6. PROVIDE PULL STRING AND RUN IT THROUGH ALL NEW CONDUIT.
7. INSTALL WEATHER PROOF END CAPS ON ALL CONDUIT STUB-UPS.
8. POUR NEW CONCRETE SIDEWALK AND CURB WHERE REMOVED TO ACCOMMODATE TRENCHING AND WHERE CURB CALLED OUT FOR REMOVAL AND
REPLACEMENT. REFER TO SHEET CP-104 FOR APPLICABLE NOTES AND DETAILS.
9. MILL 2-INCHES OFF OF THE EXISTING ASPHALT SURFACE TO LIMITS SHOWN ON THE PLAN. DISPOSE OF MILLINGS OFFSITE AT A LOCATION SECURED BY THE
CONTRACTOR.
10. PLACE AND COMPACT 2-INCHES OF TOP COURSE HOT MIX ASPHALT.
11. POWERWASH AND PAINT CURB WITHIN THE WORK AREA SAFETY YELLOW.
12. CLEAN AND SEAL ALL NEW PAVEMENT SEAMS USING A HOT APPLIED POLYMERIC JOINT SEALANT (WR MEADOWS HI-SPEC OR APPROVED EQUAL).
13. PROVIDE AND INSTALL THERMOPLASIC PAVEMENT MARKINGS AS DETAILED ON SHEET CP-105.
14. CLEAN AND SEAL THE EXISTING JOINT BETWEEN CURB AND SIDEWALK WITH DOWSIL 902 RCS JOINT SEALANT OR APPROVED EQUAL PRODUCT. THE JOINT
MEASURES 150 LF OR LESS WITHIN THE WORK AREA. REFER TO PHOTO 5 ABOVE.
P2V
P2
P3V
P3
P4V
P4
LIMIT OF WORK / MILLING
(APPROXIMATELY 1350 SY)
LIMIT OF MILLING
(APPROXIMATELY 1750 SY)
REMOVE AND REPLACE CURB
(APPROXIMATELY 85 LF)
P4
P4V
LOCATION OF PORTABLE
BOLLARDS (TYP)
P1V
P1
AREA 3
P2V
P2
LIMIT OF WORK
(APPROXIMATELY 3000 SY)
AREA 3 WORK INCLUDES THE FOLLOWING ITEMS:
1. CLEAN AND SEAL ALL EXISTING PAVEMENT CRACKS MEASURING 18" OR GREATER IN WIDTH USING A HOT APPLIED
POLYMERIC JOINT SEALANT (WR MEADOWS HI-SPEC OR APPROVED EQUAL).
2. CLEAN AND SEAL (FOG SEAL) ALL ASPHALT SURFACES WITHIN THE LIMITS SHOWN ABOVE. SEALANT SHALL BE
COMMERCIAL GRADE (BLACK JACK CAS-73 OR APPROVED EQUAL).
3. RE-STRIPE THE PARKING LOT SPACES TO MATCH EXISTING LAYOUT (APPROXIMATELY 1500 LF OF 4-INCH WIDE YELLOW
PAINT STRIPING). ENSURE ALL AREAS TO RECEIVE PAINT ARE CLEAN.
AREA 4
P2V
P1
P2
P3V
P3
P1V
LIMIT OF WORK
(APPROXIMATELY 2900 SY)
AREA 4 WORK INCLUDES THE FOLLOWING ITEMS:
1. CLEAN AND SEAL ALL EXISTING PAVEMENT CRACKS MEASURING 18" OR GREATER IN WIDTH USING A HOT APPLIED POLYMERIC JOINT SEALANT (WR MEADOWS HI-SPEC
OR APPROVED EQUAL).
2. CLEAN AND SEAL (FOG SEAL) ALL ASPHALT SURFACES WITHIN THE LIMITS SHOWN ABOVE. SEALANT SHALL BE COMMERCIAL GRADE (BLACK JACK CAS-73 OR
APPROVED EQUAL).
3. RE-STRIPE THE PARKING LOT SPACES TO MATCH THE EXISTING LAYOUT (APPROXIMATELY 5450 LF OF 4-INCH WIDE YELLOW PAINT STRIPING). ENSURE ALL AREAS
TO RECEIVE PAINT ARE CLEAN.
AREA 5
P1V
P1
AREA 5 WORK INCLUDES THE FOLLOWING ITEMS:
1. SAW CUT EXISTING ASPHALT TO ACCOMMODATE REMOVAL OF DAMAGED ASPHALT.
2. REMOVE DAMAGED ASPHALT DOWN TO EXISTING SUBBASE MATERIAL.
3. PLACE AND COMPACT BINDER AND TOP ASPHALT COURSES AT DEPTHS THAT MATCH EXISTING (TO BE FIELD VERIFIED).
4. SEAL ALL NEW PAVEMENT SEAMS, AND APPROXIMATELY 30 LF OF EXISTING PAVEMENT SEAM WITH A HOT APPLIED POLYMERIC JOINT SEALANT (WR
MEADOWS HI-SPEC OR APPROVED EQUAL).
P2
P2 V
LIMIT OF ASPHALT REMOVAL
AND REPLACEMENT
(APPROXIMATELY 16 SY)
P3 V
P3
LIMIT OF HOT APPLIED POLYMERIC
JOINT SEALANT (APPROXIMATELY
30 LF)
AREA 6
P1 V
P1
P2V
P2
P3V
P3
LIMIT OF WORK (APPROXIMATELY 9050 SY)
AREA 6 WORK INCLUDES THE FOLLOWING ITEMS:
1. CLEAN AND SEAL ALL EXISTING PAVEMENT CRACKS MEASURING 18" OR GREATER IN WIDTH USING A HOT APPLIED POLYMERIC JOINT SEALANT (WR MEADOWS
HI-SPEC OR APPROVED EQUAL).
2. CLEAN AND SEAL (FOG SEAL) ALL ASPHALT SURFACES WITHIN THE LIMITS SHOWN ABOVE. SEALANT SHALL BE COMMERCIAL GRADE (BLACK JACK CAS-73 OR
APPROVED EQUAL).
3. RE-STRIPE THE PARKING LOT SPACES TO MATCH EXISTING (APPROXIMATELY 5450 LF OF 4-INCH WIDE YELLOW PAINT STRIPING). ENSURE ALL AREAS TO
RECEIVE PAINT ARE CLEAN.
P5
P5V
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
CP-101
REPAIR AREAS 7, 8 AND 9,
CONCRETE NOTES AND DETAILS
A
FOR CONSTRUCTION
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING LOT REPAIRS
BUFFALO 528
21-122
N/A Project Director
APRIL 12, 2022 MTA RJCRevisions: Date:
N/A BUFFALO VA MEDICAL CENTER
ROBERT CEBULSKI, P.E.
GENERAL ENGINEER
AREA 7
P1V
P1
P2 V
P2
P3V
P3
AREA 7 WORK INCLUDES THE FOLLOWING ITEMS:
1. MILL 2-INCHES OFF OF THE EXISTING ASPHALT SURFACE TO LIMITS SHOWN ON THE PLAN.
DISPOSE OF MILLINGS OFFSITE AT A LOCATION SECURED BY THE CONTRACTOR.
2. PLACE AND COMPACT 2-INCHES OF TOP COURSE HOT MIX ASPHALT.
3. ADD ASPHALT WEDGE TO EXISTING APRON TO SMOOTH TRANSITION.
4. RE-STRIPE THE PARKING LOT SPACES AS SHOWN AND OTHER MARKINGS (APPROXIMATELY
740 LF OF YELLOW PAINT STRIPING). TRAFFIC SYMBOLS SHALL BE THERMOPLASTIC. ENSURE
ALL AREAS TO RECEIVE PAINT OR THERMOPLASTIC ARE CLEAN.
5. PROVIDE AND INSTALL THERMOPLASTIC PAVEMENT MARKINGS AS DETAILED ON SHEET
CP-105.
6. PROVIDE AND INSTALL ONE-WAY SIGNAGE, POST AND POST BASE AS DETAILED ON SHEET
CP-105.
P4
P4
V
LIMIT OF WORK
(APPROXIMATELY 1000 SY)
10' 4"
ASPHALT WEDGE DETAIL
SIDE VIEW
3'
10'
TOP VIEW
EXISTING APRONA
B
A
SIDE VIEW
B
MATCH EXISTING SURFACES
AREA 8
P1
V
P1
P2
P2V
AREA 8 WORK INCLUDES THE FOLLOWING ITEMS:
1. MILL 2-INCHES OFF OF THE EXISTING ASPHALT SURFACE TO LIMITS SHOWN ON THE PLAN.
DISPOSE OF MILLINGS OFFSITE AT A LOCATION SECURED BY THE CONTRACTOR.
2. PLACE AND COMPACT 2-INCHES OF TOP COURSE HOT MIX ASPHALT.
3. RE-STRIPE THE PARKING LOT SPACES TO MATCH THE EXISTING LAYOUT (APPROXIMATELY
110 LF OF YELLOW PAINT STRIPING). ENSURE ALL AREAS TO RECEIVE PAINT ARE CLEAN.
LIMIT OF WORK
(APPROXIMATELY 1000
SY)
AREA 9
AREA 9 WORK INCLUDES THE FOLLOWING ITEMS:
1. SAW CUT EXISTING ASPHALT TO ACCOMMODATE REMOVAL OF DAMAGED ASPHALT.
2. REMOVE DAMAGED ASPHALT DOWN TO EXISTING SUBBASE MATERIAL.
3. PLACE AND COMPACT BINDER AND TOP COURSE ASPHALT COURSES AT DEPTHS THAT MATCH EXISTING (TO BE FIELD VERIFIED).
4. SEAL ALL NEW PAVEMENT SEAMS, AND APPROXIMATELY 30 LF OF EXISTING PAVEMENT SEAM WITH A HOT APPLIED POLYMERIC JOINT SEALANT.
LIMIT OF WORK (APPROXIMATELY 22 SY)
P1 V
P1
P2V
P2
P3
V
P3
CONCRETE NOTES AND DETAILS
1" SCORED OR SAWCUT
CONTRACTION JOINT.
1/4" DEEP
SCORED JOINTS
1/4" R. (TYP.)
FORMED
JOINTS ONLY
EXPANSION JOINT WITH 1/4"
BITUMINOUS JOINT FILLER
EXPANSION AND SCORED JOINT
DETAIL
6" (T
YP
1'- 6"
1'- 0"
6" TOP OF PAVING
5,000 PSI CONCRETE
JOINT TO MATCH EXISTING
6" 5"1"
1" RADIUS
N.T.S.
CURB ADJACENT TO SIDEWALK DETAIL
SIDEWALK
12" COMPACTED STONE SUBBASE
NYSDOT ITEM 304.12
1'- 6"
1'- 0"
6"
4" LAYER TOPSOIL
TACK COAT PRIOR
TO PAVING
5,000 PSI CONCRETE
SOD
FINISH GRADE 1" BELOW TOP
OF CURB IN ALL LAWN AREAS.
TOP OF SOD TO BE FLUSH WITH
TOP OF CURB AS SHOWN
6" 5"1"
1" RADIUS
N.T.S.
CURB ADJACENT TO TURF DETAIL
TOP OF PAVING
TACK COAT PRIOR
TO PAVING
FILL WITH DOWSIL 902 RCS JOINT SEALER OR APPROVED EQUAL
12" COMPACTED STONE SUBBASE
NYSDOT ITEM 304.12
CONCRETE SIDEWALK
PAVEMENT
SIDEWALK - 6" THICK OR MATCH EXISTING.
MATCH EXISTING SLOPE
EXPANSION JOINT
2" RECESS
CROSS SECTION
GRASS AREA
NEW CONCRETE (5000 PSI) - NYSDOT TYPE HP
SUBGRADE SUBBASE - MIN. 6" THK (SIDEWALK)
(NYSDOT NO. 304.12)
CURB
X X XX
W.W.F.6X6/10X10
N.T.S.
X XX
N.T.S.
DOWEL
DOWEL
DOWEL
AutoCAD SHX Text NOTES: 1. CONCRETE SIDEWALK CONSTRUCTION METHODS SHALL CONFORM TO NYSDOT SPECIFICATION SECTION CONCRETE SIDEWALK CONSTRUCTION METHODS SHALL CONFORM TO NYSDOT SPECIFICATION SECTION 608-3.01 PORTLAND CEMENT CONCRETE SIDEWALKS AND DRIVEWAYS. 2. CONCRETE CURB CONSTRUCTION METHODS SHALL CONFORM TO NYSDOT SPECIFICATION SECTION 609-3.04 CONCRETE CURB CONSTRUCTION METHODS SHALL CONFORM TO NYSDOT SPECIFICATION SECTION 609-3.04 CAST-IN-PLACE CONCRETE CURB. 3. CONCRETE MATERIAL SHALL CONFORM TO NYSDOT SPECIFICATION SECTION 501 - PORTLAND CEMENT CONCRETE MATERIAL SHALL CONFORM TO NYSDOT SPECIFICATION SECTION 501 - PORTLAND CEMENT CONCRETE - GENERAL. NYSDOT TYPE HP CONCRETE SHALL BE USED FOR CURB AND SIDEWALK AND HAVE A 28-DAY DESIGN STRENGTH OF 5000 PSI. 4. NEW SIDEWALK AND CURB SHALL BE DOWELED INTO EXISTING. SIDEWALK DOWELS SHALL BE INSTALLED NEW SIDEWALK AND CURB SHALL BE DOWELED INTO EXISTING. SIDEWALK DOWELS SHALL BE INSTALLED EVERY THREE FEET, WITH A MINIMUM OF 2 DOWELS PER JOINT. CURB DOWELS SHALL BE A MINIMUM OF 1 PER JOINT. DOWELS SHALL EXTEND INTO EXISTING AND PROPOSED CONCRETE A MINIMUM OF 6-INCHES AND BE PLACED VERTICALLY AT THE CENTER OF CONCRETE. DRILL AND EPOXY DOWELS INTO EXISTING CONCRETE. DOWELS SHALL BE #3 EPOXY COATED REBAR. 5. INSTALL PREMOLDED RESILIENT JOINT FILLER AT ALL JOINTS BETWEEN SIDEWALK AND CURB AND AT ALL INSTALL PREMOLDED RESILIENT JOINT FILLER AT ALL JOINTS BETWEEN SIDEWALK AND CURB AND AT ALL TRANSVERSE CONSTRUCTION JOINTS. FILLER SHALL BE DOW CORNING 902 OR APPROVED EQUAL PRODUCT. 6. SIDEWALK SCORED JOINTS SHALL BE 1/4" WIDE, TO A DEPTH OF ONE-THIRD OF THE SLAB THICKNESS SIDEWALK SCORED JOINTS SHALL BE 1/4" WIDE, TO A DEPTH OF ONE-THIRD OF THE SLAB THICKNESS AND PLACED AT INTERVALS TO MATCH EXISTING. 7. CURB CRACK CONTROL JOINTS SHALL BE AT INTERVALS TO MATCH EXISTING AND FORMED OR SAW CUT CURB CRACK CONTROL JOINTS SHALL BE AT INTERVALS TO MATCH EXISTING AND FORMED OR SAW CUT TO A WIDTH BETWEEN AND INCH WITH A MAXIMUM DEPTH OF 1-1/2 INCHES. 18 AND INCH WITH A MAXIMUM DEPTH OF 1-1/2 INCHES. 14 INCH WITH A MAXIMUM DEPTH OF 1-1/2 INCHES. 8. CONCRETE SHALL BE POURED / USED WITHIN 90 MINUTES OF BATCH TIME. CONCRETE SHALL BE POURED / USED WITHIN 90 MINUTES OF BATCH TIME. 9. ADDITIONAL WATER MAY BE ADDED TO BATCHED CONCRETE ONLY WITH THE APPROVAL OF THE VA. ADDITIONAL WATER MAY BE ADDED TO BATCHED CONCRETE ONLY WITH THE APPROVAL OF THE VA. ADDITIONAL WATER ADDED TO CONCRETE SURFACES FOR FINISHING MAY ONLY BE DONE WITH THE APPROVAL OF THE VA. 10. FORMS SHALL BE FREE FROM WARP, EXTEND TO THE FULL DEPTH OF CURB OR SIDEWALK AND BE FORMS SHALL BE FREE FROM WARP, EXTEND TO THE FULL DEPTH OF CURB OR SIDEWALK AND BE SECURED TO PREVENT MOVEMENT OR DISPLACEMENT. 11. CONCRETE SHALL BE COMPACTED DURING PLACEMENT USING AN IMMERSION TYPE MECHANICAL VIBRATOR. CONCRETE SHALL BE COMPACTED DURING PLACEMENT USING AN IMMERSION TYPE MECHANICAL VIBRATOR. 12. USE ONLY MAGNESIUM FLOATS AND FINISHING TOOLS, DO NOT USE STEEL OR ALUMINUM. FINISH THE USE ONLY MAGNESIUM FLOATS AND FINISHING TOOLS, DO NOT USE STEEL OR ALUMINUM. FINISH THE CONCRETE TO PRODUCE A SMOOTH SURFACE AND THEN BROOM SURFACES TO A UNIFORM SLIP-RESISTANT TEXTURE. TOOL THE EDGES AND SCORED JOINTS OF ALL SIDEWALK SLABS WITH AN EDGING TOOL HAVING A 1/4-INCH RADIUS. 13. IMMEDIATELY AFTER FINISHING AND NOT MORE THAN 30 MINUTES AFTER CONCRETE PLACEMENT, APPLY A IMMEDIATELY AFTER FINISHING AND NOT MORE THAN 30 MINUTES AFTER CONCRETE PLACEMENT, APPLY A CLEAR MEMBRANE CURING COMPOUND THAT INCLUDES A FUGITIVE DYE AT A RATE OF 1 GALLON PER 150 SQUARE FEET. CONTINUOUSLY WETTED BURLAP OR OTHER ALTERNATE METHOD OF CURE SHOULD BE CONSIDERED FOR USE ON CONCRETE SCHEDULED TO BE PAINTED (CURBS) AS CURING COMPOUND MAY INTERFERE WITH PROPER PAINT ADHESION. 14. CONCRETE SHALL BE PROTECTED FROM PEDESTRIAN TRAFFIC A MINIMUM OF 3-DAYS AFTER POURING, CONCRETE SHALL BE PROTECTED FROM PEDESTRIAN TRAFFIC A MINIMUM OF 3-DAYS AFTER POURING, AND A MINIMUM OF 7-DAYS FROM VEHICLE TRAFFIC. 15. FORMS SHALL BE LEFT IN PLACE UNTIL CONCRETE HAS HARDENED SUFFICIENTLY TO PERMIT REMOVAL FORMS SHALL BE LEFT IN PLACE UNTIL CONCRETE HAS HARDENED SUFFICIENTLY TO PERMIT REMOVAL WITHOUT DAMAGING CURB OR SIDEWALK. THE CURB FACE / FRONT FORM MAY BE REMOVED BEFORE THE OTHERS TO FACILITATE FINISHING THE CURB. NO PLASTERING WILL BE PERMITTED. 16. IF THE AMBIENT AIR TEMPERATURE IS EXPECTED TO FALL BELOW 40 DEGREES F DURING THE 3 DAY IF THE AMBIENT AIR TEMPERATURE IS EXPECTED TO FALL BELOW 40 DEGREES F DURING THE 3 DAY MINIMUM CURE TIME, THE CONTRACTOR MUST SUPPLY INSULATING MATERIALS CAPABLE OF MAINTAINING A TEMPERATURE OF 55 DEGREES F WITHIN THE INSULATED AREA. AN EXTERNAL SOURCE OF HEAT MAY BE REQUIRED. HI-LOW THERMOMETERS SHALL BE PLACED WITHIN THE INSULATED AREA TO RECORD TEMPERATURES. 17. THE VA DOES NOT HAVE A DEDICATED CONCRETE WASHOUT AREA ON SITE. THE CONTRACTOR AND / THE VA DOES NOT HAVE A DEDICATED CONCRETE WASHOUT AREA ON SITE. THE CONTRACTOR AND / OR CONCRETE SUPPLIER WILL NEED TO DETERMINE HOW AND WHERE CONCRETE WASHOUT WILL BE PERFORMED. CONSTRUCTION OF ANY ON-SITE TEMPORARY WASHOUT COLLECTION BASINS WILL REQUIRE VA APPROVAL.
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
CP-102
AREA STRIPING PLANS AND DETAILS
A
FOR CONSTRUCTION
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING LOT REPAIRS
BUFFALO 528
21-122
N/A Project Director
APRIL 12, 2022 MTA RJCRevisions: Date:
N/A BUFFALO VA MEDICAL CENTER
ROBERT CEBULSKI, P.E.
GENERAL ENGINEER
AREA 7 PAVEMENT MARKINGS AND SIGNAGE PLAN
TYP. ALL
ARROWS
PAVEMENT MARKING
DETAILS
5'
3' 1'
6'
CROSS WALK
1.5'
12'
STOP BAR LANE STRIPING
0.5'
4'
8' SPACING
PAVEMENT MARKINGS NOTES:
1. AT LEAST 5 DAYS PRIOR TO START OF PAVEMENT STRIPING, THE CONTRACTOR SHALL SUBMIT A SCHEDULE OF OPERATIONS TO THE VA FOR
REVIEW AND APPROVAL.
2. THE CONTRACTOR SHALL PROVIDE THE VA WITH THE PREFORMED THERMOPLASTIC MANUFACTURERS WRITTEN INSTRUCTIONS FOR USE.
3. ALL MAIN ENTRANCE MARKINGS, AND AREA 7 TRAFFIC ARROWS TO BE 120 MIL THERMOPLASTIC, EITHER PREFORMED OR THROUGH MOLTEN THERMOPLASTIC APPLICATION. ALL PARKING STALL STRIPING SHALL BE YELLOW TRAFFIC PAINT.
4. PAVEMENT MARKINGS SHALL BE INSTALLED AS INDICATED ON THE PLAN AND FIELD COORDINATED AND VERIFIED WITH THE VA PRIOR TO
FINAL INSTALLATION.
5. THE CROSS WALK, LANE STRIPING, AND STOP BAR SHALL BE WHITE.
6. ARROWS AND DROP OFF LANE STRIPE SHALL BE YELLOW.
7. APPLY REFLECTIVE GLASS BEADS AT THE TIME OF THERMOPLASTIC APPLICATION AT A RATE OF 6 POUNDS PER 100 SQUARE FEET.
8. DIMENSIONS OF MARKINGS ARE BASED OFF OF TYPICAL STANDARDS AND AVAILABLE MATERIALS AND PREFORMED SYMBOLS. SLIGHT MODIFICATIONS TO DIMENSIONS MAY BE ACCEPTABLE IF SUBMITTED TO THE VA FOR REVIEW AND APPROVAL.
9. PAVEMENT MARKINGS SHALL ONLY BE APPLIED DURING CONDITIONS OF DRY WEATHER WITH SUBSTANTIALLY DRY PAVEMENT SURFACES.
10. THE CONTRACTOR SHALL CLEAN THE PAVEMENT TO REMOVE OIL, DIRT, DUST, GREASE AND OTHER SIMILAR FOREIGN MATERIALS. AFTER CLEANING, SEAL OIL SOAKED AREAS WITH CUT SHELLAC TO PREVENT BLEEDING THROUGH NEW PAINT.
11. STORE ALL MATERIALS IN CLEAN AND DRY AREAS.
12. POWERWASH AND PAINT ALL CURBS WITHIN THE WORK AREA YELLOW (APPROXIMATELY 810 LF).
13. APPLY UNIFORMLY PAINTED AND REFLECTED PAVEMENT MARKING OF REQUIRED COLORS, LENGHT AND WIDTH WITH TRUE SHARP EDGES
AND ENDSON PROPERLY CURED, PREPARED AND DRIED SURFACES.
14. APPLY PAINT AT WET FILM THICKNESS OF 0.4 MM (0.015 INCH). DISPERSE REFLECTIVE GLASS BEADS EVENLY ON WET PAINT AT A RATE OF 6 LBS PER GALLON OF PAINT. APPLY PAINT IN ONE COAT. WHEN DIRECTED BY THE VA, APPLY ADDITIONAL COATS AT MARKINGS SHOWING LIGHT SPOTS. COMPLY WITH PAINT MANUFACTURER'S MAXIMUM DRYING TIME REQUIREMENTS TO PREVENT UNDUE SOFTENING OF ASPHALT, AND PICK-UP, DISPLACEMENT, OR DISCOLORATION BY TIRES OF TRAFFIC.
15. WHEN DEFICIENCY IN MARKING DRYING OCCURS, DISCONTINUE PAINT OPERATIONS UNTIL CAUSE OF SLOW DRYING IS DETERMINED AND
CORRECTED.
16. REMOVE AND REPLACE MARKING APPLIED LESS THAN MINIMUM MATERIAL RATES, DEVIATES FROM TRUE ALIGNMENT, EXCEEDS STIPULATED LENGHT AND WIDTH TOLERANCES, OR SHOWS LIGHT SPOTS, FAULTY DISTRIBUTION OF BEADS, SMEARS, OR OTHER DEFICIENCIES OR
IRREGULARITIES.
17. REMOVE MARKING BY CAREFULLY CONTROLLED SANDBLASTING, OR OTHER APPROVED METHOD TO PREVENT DAMAGE ON APPLIED
SURFACE.
4'
3'
6'
2'
4'
3'
1'
1 2 3
MAIN ENTRANCE STRIPING PLAN
24"
18"
3 3
3 3
SOLID 6" WIDE YELLOW STRIPE
*SIGNS, POSTS, POST BASES AND MOUNTING HARDWARE SHALL BE
FABRICATED AND INSTALLED IN ACCORDANCE WITH NYSDOT STANDARD
SPECIFICATION SECTION 645 AND THE MANUAL OF UNIFORM TRAFFIC
CONTROL DEVICES 229 EDITION. SIGN MATERIAL SHALL BE ALUMINUM,
SIGN SHEETING SHALL BE RETRO REFLECTIVE NYSDOT CLASS A .
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
CU-100
UNDERGROUND DUCT BANK
A
FOR CONSTRUCTION
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
PARKING LOT REPAIRS
BUFFALO 528
21-122
N/A Project Director
XXXXXXXXXXXXX MTA RJCRevisions: Date:
N/A BUFFALO VA MEDICAL CENTER
ROBERT CEBULSKI, P.E.
GENERAL ENGINEER
SIX (6)
2-INCH SCHEDULE 80
THREE (3)
2-INCH SCHEDULE 80
THREE (3)
2-INCH SCHEDULE 80
SIX (6)
2-INCH SCHEDULE 80
THREE (3)
2-INCH SCHEDULE 80
THREE (3)
2-INCH SCHEDULE 80
PB-1
PB-3
PB-4
PB-1
PB-3
PB-4
PB-2
P1
P1
V
P2V
P2
P3V
P3
P4 V
P4
PB-2
30" X 48" x 36" DEEP
QUANZITE BOX
24" X 36" X 26" DEEP
QUANZITE BOX
30" X 48" x 36" DEEP
QUANZITE BOX
24" X 36" X 26" DEEP
QUANZITE BOX
(4) CONCRETE BRICKS
51mm x 203mm x 406mm
(2"x8"x16")
CONDUIT(S) WITH BELL
ENDS (TYP). SIZE AS
INDICATED ON PLANS
CLEAN 19mm (3/4")
CRUSHED ROCK
GRADE. FEATHER & TAMP
BACKFILL TO CREATE FLUSH
INSTALLATION AND POSITIVE
DRAINAGE AWAY FROM BOX
PULLBOX
LINE SIDES OF
EXCAVATION WITH 13.6
KG (30 LBS.) FELT
PAPER
GALVANIZED RIGID STEEL
CONDUIT REQUIRED FOR
BENDS AND STUB-UPS.
GRADE
CL
FINISH GRADE
FINISH GRADE
HIGH
VOLTAGE
LOW
VOLTAGE
DATA
" M
IN
3" MIN
3"
3" MIN
12" MIN
12" MIN
" M
IN
" M
IN
3" MIN
3"
3" MIN
3" MIN
3" TYP
3" MIN
3" TYP
" M
IN
" M
IN
3" MIN
3"
3" MIN
3" MIN
3" TYP
THIS ROW FROM PB-1
THIS ROW TO PB-3
THIS ROW TO PB-4
2" STUB-UP WITH END CAP (TYP)
*PLEASE REFER TO SPECIFICATION SECTION
26 05 41 - UNDERGROUND ELECTRICAL
CONSTRUCTION FOR ADDITIONAL PULLBOX /
CONDUIT INSTALLATION AND TRENCHING
REQUIREMENTS.
10" - 12" MIN HEIGHT *NOTE THAT PULL BOXES SHOWN ON THIS SHEET PROVIDE A
CONCEPTUAL IDEA OF TYPE AND SIZE REQUIRED FOR THE
PROJECT. THE CONTRACTOR MAY SUBMIT EQUAL BOXES TO
THE VA FOR REVIEW AND APPROVAL.
AutoCAD SHX Text
NTS
AutoCAD SHX Text
ONE LINE DIAGRAM
AutoCAD SHX Text
UNDERGROUND DUCTBANK PLAN
AutoCAD SHX Text
UNDERGROUND POLYMER CONCRETE PULLBOX - TURF AREA DETAIL
AutoCAD SHX Text
NTS
AutoCAD SHX Text
SELECT GRANULAR FILL - NYSDOT ITEM # 203.07 BACKFILL AND COMPACT IN 6" LIFTS
AutoCAD SHX Text
WARNING TAPE
AutoCAD SHX Text
RESTORE SURFACE TO MATCH EXISTING
AutoCAD SHX Text 2" SCH 80 PVC CONDUIT - ALL BENDS AND STUB-UPS MUST BE GALVANIZED RIGID STEEL. 6 TOTAL
AutoCAD SHX Text
NATIVE SOIL
AutoCAD SHX Text
2,000 LB CONCRETE USE PLASTIC SPACERS EVERY 5FT
AutoCAD SHX Text
AutoCAD SHX Text
NTS
AutoCAD SHX Text
DUCTBANK DETAIL IN TURF
AutoCAD SHX Text
ALL TRENCHING TO BE COMPLETED BY MEANS OF HYDRO-EXCAVATION
AutoCAD SHX Text
AutoCAD SHX Text
NTS
AutoCAD SHX Text
DUCTBANK DETAIL UNDER PAVEMENT
AutoCAD SHX Text
AutoCAD SHX Text
NTS
AutoCAD SHX Text
DUCTBANK DETAIL UNDER CONCRETE
AutoCAD SHX Text
SELECT STRUCTURAL FILL - NYSDOT ITEM # 203.21 BACKFILL AND COMPACT IN 6" LIFTS
AutoCAD SHX Text
WARNING TAPE
AutoCAD SHX Text
RESTORE SURFACE TO MATCH EXISTING
AutoCAD SHX Text 2" SCH 80 PVC CONDUIT - ALL BENDS AND STUB-UPS MUST BE GALVANIZED RIGID STEEL. 6 TOTAL
AutoCAD SHX Text
NATIVE SOIL
AutoCAD SHX Text
2,000 LB CONCRETE USE PLASTIC SPACERS EVERY 5FT
AutoCAD SHX Text
ALL TRENCHING TO BE COMPLETED BY MEANS OF HYDRO-EXCAVATION
AutoCAD SHX Text 12" NYSDOT TYPE 2 SUBBASE STONE - NYSDOT ITEM # 304.12 BACKFILL AND COMPACT IN 6" LIFTS
AutoCAD SHX Text 2" 9.5mm TOP 80 SERIES NYSDOT ITEM # 402.098203
AutoCAD SHX Text 3 " 19mm BINDER 80 SERIES 12" 19mm BINDER 80 SERIES NYSDOT ITEM # 402.198903
AutoCAD SHX Text
ASPHALT STEP JOINT. CLEAN AND TACK COAT PRIOR TO PAVING
AutoCAD SHX Text
SELECT STRUCTURAL FILL - NYSDOT ITEM # 203.21 BACKFILL AND COMPACT IN 6" LIFTS
AutoCAD SHX Text
WARNING TAPE
AutoCAD SHX Text
RESTORE SURFACE TO MATCH EXISTING
AutoCAD SHX Text 2" SCH 80 PVC CONDUIT - ALL BENDS AND STUB-UPS MUST BE GALVANIZED RIGID STEEL. 6 TOTAL
AutoCAD SHX Text
NATIVE SOIL
AutoCAD SHX Text
2,000 LB CONCRETE USE PLASTIC SPACERS EVERY 5FT
AutoCAD SHX Text
ALL TRENCHING TO BE COMPLETED BY MEANS OF HYDRO-EXCAVATION
AutoCAD SHX Text
6" NYSDOT TYPE 2 SUBBASE STONE - NYSDOT ITEM # 304.12 BACKFILL AND COMPACT.
AutoCAD SHX Text
6" NYSDOT CLASS HP CONCRETE
AutoCAD SHX Text
AutoCAD SHX Text
HIGH VOLTAGE
AutoCAD SHX Text
LOW VOLTAGE
AutoCAD SHX Text
DATA
AutoCAD SHX Text
TYPICAL PULL BOX COVER 3-SECTION LABELED AS SHOWN
AutoCAD SHX Text
DIVIDERS IN BOX TO CREATE 3 EQUAL SPACES
AutoCAD SHX Text
BOX AND COVER COLOR SHALL BE MUNSELL GREEN OR LIGHT GREEN
AutoCAD SHX Text
AutoCAD SHX Text
NTS
AutoCAD SHX Text
PULLBOX TOP VIEW (TYP)
AutoCAD SHX Text
SOD INSTALLED OVER 2-INCHES OF TOPSOIL
AutoCAD SHX Text
HIGH VOLTAGE
AutoCAD SHX Text
LOW VOLTAGE
AutoCAD SHX Text
DATA
AutoCAD SHX Text
AutoCAD SHX Text
NTS
AutoCAD SHX Text
PULLBOX PB-2 CONDUIT TERMINATION DETAIL
AutoCAD SHX Text
ELECTRIC
AutoCAD SHX Text
ELECTRIC
AutoCAD SHX Text
TELE
AutoCAD SHX Text
ELECTRIC
AutoCAD SHX Text
ELECTRIC
AutoCAD SHX Text
TELE
| CS_100 |
| Sheets and Views |
| 528-21-122 Parking Lot Repair Drawing-Cover Sheet |
| CN_100 |
| Sheets and Views |
| 528-21-122 Parking Lot Repair Drawing- Revised-CN-100 |
| CP_100 |
| Sheets and Views |
| 528-21-122 Parking Lot Repair Drawing-CP-100 |
| CP_101 |
| Sheets and Views |
| 528-21-122 Parking Lot Repair Drawing-CP-101 |
| cp_102 |
| Sheets and Views |
| 528-21-122 Parking Lot Repair Drawing- Revised-CP-102 |
| CU_100 |
| Sheets and Views |
| 528-21-122 Parking Lot Repair Drawing- Revised-CU-100 |
File details come from the government source that posted it. Updated .