20210825_PreBid_Clarifications_PreBid_Site_Visit_FeedwaterPump.docx
DOCX document 514 KB Posted
- Solicitation number
- 36C24221Q1292
About this file
This notice is for a federal construction contract solicitation to replace the steam-turbine driven boiler feed water pump and associated components located in the Boiler Plant at the James J. Peters Veterans Affairs Medical Center in Bronx, New York. The solicitation is set aside for Service-Disabled Veteran Owned Small Businesses, with a cost estimate between $100,000 to $200,000. The scope of work includes removing the existing pump, installing a new steam turbine pump and associated components, verifying connections and torque, commissioning with the pump manufacturer, and submitting project schedules and materials lists. The replacement pump must meet the specified performance criteria and be compatible with existing systems. The project completion date is 60 calendar days from notice to proceed. Responses are due as detailed in the solicitation to be posted on August 13, 2021 on SAM.gov. The contracting agency is the Department of Veterans Affairs Veterans Health Administration VISN 2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24221Q1292 0001.docx | DOCX document | |
| wage determination.txt | TXT text file | |
| 36C24221Q1292.docx | DOCX document | |
| ATT A - Performance Specifications - Feedwater Pump.docx | DOCX document | |
| ATT B Pictures - Feedwater Pump.docx | DOCX document | |
| ATT C - CPM Plan - Feedwater Pump.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| US Department of Veterans Affairs | Steam Feedwater Pump Replacement | |
| James J. Peters Bronx VA Medical Center | Project # N/A | |
| Reference # 526-21-4-644-0997 |
Pre-Bid Clarifications Pre-Bid Site Visit
August 25th, 2021
Clarifications:
1) Contractor MS Project schedule to include a proposed NTP date of October 4, 2021 and shall include a line item for steam turbine pump procurement.
2) Include manufacturer and model of proposed steam turbine pump replacement in the “Construction Means and Methods” statement.
3) Pump alignment to be performed by the pump manufacturer or approved 3rd party and shall be included in the proposal price. Provide documentation of pump alignment data as compared to the pump manufacturer’s tolerances for final acceptance.
4) There are a total of 3 attachments (A – Pump Performance Specifications, B – Pictures, C – Construction Project Management Plan).