The file's text, extracted by GovTribe without its formatting.
B. 3 PRICE WORKSHEET
* NOTE THE QUANTITIES AND SIZES LISTED ARE ESTIMATES TO BE USED FOR PRICE
EVALUATION PURPOSES ONLY.
Base Year Period of Performance: 10/01/2020-09/30/2021
| CLIN |
| Item Description |
| Estimated Quantities |
| UNIT |
| Unit Price |
| Total Estimated Price |
New York Campus
| 0001 |
| VA Owned 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 0002 |
| Rental of 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
(As needed)
| 0003 |
| Rental of 30 Cubic Yard Open Top (Solid Waste) |
| 0004 |
| Rental of (4) 2 Cubic Yard rear load (Single Stream Recycling) |
| 0005 |
| Pick up (4) 2 Cubic Yard rear load. (Single Stream Recycling) 2X per a week. |
| 12 |
| MO |
| 0006 |
| Pick up the single Baler VA owned (Cardboard) 2X per week. |
| 0007 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) contractor owned |
| 0008 |
| Per Ton Disposal of 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 0009 |
| Per Ton Disposal for 30 Cubic Yard Open Top (Solid Waste) |
contractor owned
| 0010 |
| Pick up 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) 3x per week VA owned |
| 0011 |
| 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
As Needed Pick up
| 0012 |
| Pick up 30 Cubic Yard Open Top (Solid Waste) 2X per a week. contractor owned |
| 0013 |
| Monthly sanitizing of VA owned compactor |
Brooklyn Campus
| 0014 |
| Rental of a 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 0015 |
| Rental of (4) 2 Cubic Yard rear load. |
| 0016 |
| Rental 20 Cubic Yard rear load (solid waste) |
| 0017 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 0018 |
| Per Ton Disposal for 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
| 1 |
| TN |
| 0019 |
| Pick up (4) 2 Cubic Yard rear load. (Single Stream Recycling) 2X per a week. contractor owned. |
| 1 |
| TN |
| 0020 |
| Pick up Baler VA owned (Cardboard) 2X per a week |
| 0021 |
| Pick up 20 Cubic Yard rear load (solid waste) 1X per a week. contractor owned |
| 0022 |
| Pick up 35 Cubic Yard Self Contained Compactor VA owned (Solid Waste). 2x per week |
| 0023 |
| As needed Pick up contractor owned 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 0024 |
| Monthly sanitizing of VA owned compactor |
St. Albans Campus
| 0025 |
| VA Owned (2) 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 0026 |
| Rental of a 30 Cubic Yard Cubic Yard Open Tops Container Trash Compactor (Solid Waste) |
| 12 |
| MO |
| 0027 |
| Rental of 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
| 0028 |
| Rental of 6 Cubic Yard rear load (Single Stream Recycling). |
| 0029 |
| Pick up of (2) 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) 2X per a week VA owned |
| 0030 |
| Pick up contractor owned 30 Cubic Yard Cubic Yard Open Tops Container (Solid Waste) 2X per a week |
| 0031 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 1 |
| TN |
| 0032 |
| Pick up 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned. As needed |
| 0033 |
| Pick up 6 Cubic Yard rear load (Single Stream Recycling) 1X per a week. contractor owned |
| 0034 |
| Pick up the single Baler VA owned (Cardboard) 2X per a week. |
| 0035 |
| Monthly sanitizing of VA owned compactor |
Total Estimated Base $ _______________
Option Year one Period of Performance: 10/01/2021-09/30/2022
| CLIN |
| Item Description |
| Estimated Quantities |
| UNIT |
| Unit Price |
| Total Estimated Price |
New York Campus
| 1001 |
| VA Owned 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 1002 |
| Rental of 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
(As needed)
| 1003 |
| Rental of 30 Cubic Yard Open Top (Solid Waste) |
| 1004 |
| Rental of (4) 2 Cubic Yard rear load (Single Stream Recycling) |
| 1005 |
| Pick up (4) 2 Cubic Yard rear load. (Single Stream Recycling) 2X per a week. |
| 1006 |
| Pick up the single Baler VA owned (Cardboard) 2X per week. |
| 1007 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) contractor owned |
| 1008 |
| Per Ton Disposal of 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 1009 |
| Per Ton Disposal for 30 Cubic Yard Open Top (Solid Waste) |
contractor owned.
| 1010 |
| Pick up 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) 3x per week VA owned |
| 1011 |
| 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
As Needed Pick up
| 1012 |
| Pick up 30 Cubic Yard Open Top (Solid Waste) 2X per a week. contractor owned |
| 1013 |
| Monthly sanitizing of VA owned compactor |
Brooklyn Campus
| 1014 |
| Rental of a 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 1015 |
| Rental of (4) 2 Cubic Yard rear load. |
| 1016 |
| Rental 20 Cubic Yard rear load (solid waste) |
| 1017 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 1018 |
| Per Ton Disposal for 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
| 1 |
| TN |
| 1019 |
| Pick up (4) 2 Cubic Yard rear load. (Single Stream Recycling) 2X per a week. contractor owned |
| 1020 |
| Pick up Baler VA owned (Cardboard) 2X per a week |
| 1021 |
| Pick up 20 Cubic Yard rear load (solid waste) 1X per a week. contractor owned |
| 1022 |
| Pick up 35 Cubic Yard Self Contained Compactor VA owned (Solid Waste). 2x per week |
| 1023 |
| As needed Pick up contractor owned 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 1024 |
| Monthly sanitizing of VA owned compactor |
St. Albans Campus
| 1025 |
| VA Owned (2) 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 1026 |
| Rental of a 30 Cubic Yard Cubic Yard Open Tops Container Trash Compactor (Solid Waste) |
| 1027 |
| Rental of 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
| 1028 |
| Rental of 6 Cubic Yard rear load (Single Stream Recycling). |
| 1029 |
| Pick up of (2) 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) 2X per a week VA owned |
| 1030 |
| Pick up contractor owned 30 Cubic Yard Cubic Yard Open Tops Container (Solid Waste) 2X per a week. |
| 12 |
| MO |
| 1031 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 1 |
| TN |
| 1032 |
| Pick up 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned. As needed |
| 1033 |
| Pick up 6 Cubic Yard rear load (Single Stream Recycling) 1X per a week. contractor owned |
| 1034 |
| Pick up the single Baler VA owned (Cardboard) 2X per a week. |
| 1035 |
| Monthly sanitizing of VA owned compactor |
Total Estimated Base $ _______________
Option Year two Period of Performance: 10/01/2022-09/30/2023
| CLIN |
| Item Description |
| Estimated Quantities |
| UNIT |
| Unit Price |
| Total Estimated Price |
New York Campus
| 2001 |
| VA Owned 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 2002 |
| Rental of 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
(As needed)
| 2003 |
| Rental of 30 Cubic Yard Open Top (Solid Waste) |
| 2004 |
| Rental of (4) 2 Cubic Yard rear load (Single Stream Recycling) |
| 2005 |
| Pick up (4) 2 Cubic Yard rear load. (Single Stream Recycling) 2X per a week. |
| 12 |
| MO |
| 2006 |
| Pick up the single Baler VA owned (Cardboard) 2X per week. |
| 2007 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) contractor owned |
| 2008 |
| Per Ton Disposal of 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 2009 |
| Per Ton Disposal for 30 Cubic Yard Open Top (Solid Waste) |
contractor owned
| 2010 |
| Pick up 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) 3x per week VA owned |
| 2011 |
| 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
As Needed Pick up
| 2012 |
| Pick up 30 Cubic Yard Open Top (Solid Waste) 2X per a week. contractor owned |
| 2013 |
| Monthly sanitizing of VA owned compactor |
Brooklyn Campus
| 2014 |
| Rental of a 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 2015 |
| Rental of (4) 2 Cubic Yard rear load. |
| 2016 |
| Rental 20 Cubic Yard rear load (solid waste) |
| 2017 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 2018 |
| Per Ton Disposal for 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
| 2019 |
| Pick up (4) 2 Cubic Yard rear load. (Single Stream Recycling) 2X per a week. contractor owned. |
| 1 |
| TN |
| 2020 |
| Pick up Baler VA owned (Cardboard) 2X per a week |
| 2021 |
| Pick up 20 Cubic Yard rear load (solid waste) 1X per a week. contractor owned. |
| 12 |
| MO |
| 2022 |
| Pick up 35 Cubic Yard Self Contained Compactor VA owned (Solid Waste). 2x per week |
| 2023 |
| As needed Pick up contractor owned 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned |
| 2024 |
| Monthly sanitizing of VA owned compactor |
St. Albans Campus
| 2025 |
| VA Owned (2) 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 2026 |
| Rental of a 30 Cubic Yard Cubic Yard Open Tops Container Trash Compactor (Solid Waste) |
| 12 |
| MO |
| 2027 |
| Rental of 30 Cubic Yard Open Tops (Construction & Demolition Debris) |
| 2028 |
| Rental of 6 Cubic Yard rear load (Single Stream Recycling). |
| 2029 |
| Pick up of (2) 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) 2X per a week VA owned |
| 2030 |
| Pick up contractor owned 30 Cubic Yard Cubic Yard Open Tops Container (Solid Waste) 2X per a week |
| 2031 |
| Per Ton Disposal for 35 Cubic Yard Self Contained Trash Compactor (Solid Waste) |
| 1 |
| TN |
| 2032 |
| Pick up 30 Cubic Yard Open Tops (Construction & Demolition Debris) contractor owned. As needed |
| 2033 |
| Pick up 6 Cubic Yard rear load (Single Stream Recycling) 1X per a week. contractor owned |
| 2034 |
| Pick up the single Baler VA owned (Cardboard) 2X per a week. |
| 2035 |
| Monthly sanitizing of VA owned compactor |
Total Estimated Base $ _______________
Recycling Rebate Worksheet:
| CLIN |
| Item Description for all three sites |
| Estimated |
Rebate per Ton
| Estimated yearly Recycling (tonnage) |
| Total Estimated Rebate |
Base Year
| R0001 |
| Cardboard recycling/comingled paper and plastic |
205.5
84.5
Option Year 1
| R1001 |
| Cardboard recycling/comingled paper and plastic |
205.5
84.5
Option Year 2
| R2001 |
| Cardboard recycling/comingled paper and plastic |
205.5
84.5