This solicitation is for upgrade work at the Sewage Treatment Plant at the Northport VA Medical Center in Northport, New York. The scope of work includes general construction, alterations, phasing, maintenance of plant operations, mechanical and electrical work, installation of new and replacement equipment, and removal of existing structures. The project will be awarded as a single contract with a completion time of 367 calendar days from notice to proceed. Bids are requested for three items: upgrade of the sewage treatment plant as a lump sum; unit pricing for hauling and disposal of grit and rags from tank cleaning; and an allowance for concrete repair work. The solicitation response date and other details will be provided in the full solicitation to be posted on SAM.gov on or around January 16, 2020. This opportunity is set aside for veteran-owned small businesses and has a size standard of $36.5 million.
36C24220B0011 0001 Statement of Bid Items - Addendum 1.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24220B0011-0002000.docx | DOCX document | |
| 36C24220B0011-0001002.pdf | ||
| 36C24220B0011-0001003.pdf | ||
| 36C24220B0011-0001000.docx | DOCX document | |
| 36C24220B0011-005.pdf | ||
| 36C24220B0011-004.pdf | ||
| 36C24220B0011-006.pdf | ||
| 36C24220B0011-003.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NO. 632-17-103
UPGRADE SEWAGE TREATMENT PLANT, PHASE 1
STATEMENT OF BID ITEM(S)
| 1 | BID INSTRUCTIONS |
| A. | A single award will be made on Item No. I based on available funding. Offerors should quote a price on each item listed. |
| 2 | BID SCHEDULE |
| ITEM NO. | |
| DESCRIPTION | |
| EST. QUANTITY | |
| UNIT | |
| UNIT PRICE $ | |
| TOTAL BID $ |
| I |
| Upgrade Sewage Treatment Plant, Phase 1 |
| Complete Project |
| LS |
| NA |
| $ |
| II |
| Unit Cost for Hauling and Disposal of Grit from Tanks |
| 600 |
| CY |
| $ |
| $ |
| III |
| Allowance for Concrete Repair |
| As authorized |
| NA |
| NA |
| $10,000 |
Total Project Bid Price
| 3 | STATEMENT OF BID ITEM(S) |
| A. | ITEM I, UPGRADE SEWAGE TREATMENT PLANT, PHASE 1: Contractor shall supply all labor, tools, materials, equipment, supplies and supervision necessary to perform all work to renovate and upgrade the Sewage Treatment Plant at the U.S. Department of Veterans Affairs Medical Center, 79 Middleville Road, Northport, NY 11768. Work shall include, but not be limited to general construction, alterations, phasing, maintenance of plant operations, mechanical and electrical work, installation of new and replacement equipment, necessary removal of existing structures, coordination with governing municipalities inspections/approvals, and certain other items. Materials and equipment to be installed in permanent manner and be approved by the government prior to installation. Construction methods and workmanship shall comply with manufacturer's specifications and generally accepted trade practices. All work shall be in full accordance with architect and engineer drawings and specifications by Hayduk Engineering, LLC; please see drawings and specifications. All work shall be in full accordance with drawings and specifications. The contract completion time is 367 calendar days from receipt of Notice to Proceed. |
B. ITEM # II, Unit Cost for Hauling and Disposal of Grit and Rags from Cleaning of Tanks: Contractor shall remove and dispose of off-site any existing grit and rags remaining in the tank after pumping out liquids. Pumping of liquids from the tank being emptied and cleaned to the tank remaining in service is included in Bid Item # I and is not included in this Bid Item # II.
C. ITEM # III, Allowance for Concrete Repair: Contractor shall perform exterior wall patching and concrete repairs as requested by the VA and in accordance with methods approved by the VA. This item only applies to conditions existing prior to the start of the project. It does not include damage caused by the Contractor during his execution of the project which is included under Item # I.