36C24219Q0200-002.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
VISN 2 Downstate Asbestos/Lead/Mold Abatement On-Call and Emergency Services
Solicitation number
36C24219Q0200
Issued by

About this file

36C24219Q0200 Pricing Schedule Table - VISN 2 Abatement Services.xlsx

View the file

Other files

File Type Posted
36C24219Q0200-0002000.docx DOCX document
36C24219Q0200-0001000.docx DOCX document
36C24219Q0200-001.docx DOCX document
36C24219Q0200-003.docx DOCX document
36C24219Q0200-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ASBESTOS

ITEM UNIT OF MEASURE UNIT PRICE

PRE-WORK REQUIREMENTS
Submittals
Attend on-site pre-start meeting, prepare and submit brief asbestos abatement work plan, project schedule, decontamination unit sketches and worker qualificationsEA
Mobilize All Personnel and Equipment To Site (Within 24 Hour Notice)EA
Mobilize All Personnel and Equipment To Site (Within 72 Hour Notice)EA
Mobilize All Personnel and Equipment To Site (> 72 Hour Notice)EA
CONTAINMENT & PREPARATION IN ASBESTOS ABATEMENT WORK AREA
Remove and relocate within facility all movable furniture, etc.HR
Hard Separation barrier, 2" x 4" wood studs @ 16", 1/2" plywood ea. side to 8' heightSF
Hard Separation barrier, 2" x 4" wood studs @ 16", 1/2" plywood ea. side to 12' heightSF
for heights above 12' add
Remove Non-Asbestos Material (to access ACM for abatement). Establish HEPA-filtered negative pressure containment as stipulated in the project documents.
Non-ACM CarpetSF
Non-ACM Vinyl Cove Base MoldingSF
Non-ACM Vinyl Floor Tile with Non-ACM MasticSF
Non-ACM Concrete Masonry Unit Wall ChaseSF
Non-ACM Wall PlasterSF
Non-ACM Ceiling PlasterSF
Non-ACM Sheetrock WallSF
Non-ACM Sheetrock CeilingSF
Remove and store on-site existing Non-ACM suspended acoustical tile, metal T-grid to remain in placeSF
Remove, clean and store on-site existing suspended acoustical ceiling tile system complete with metal T-grid and tileSF
Remove and Clean 2 x 4 Fluorescent Light fixtures, Store on SiteEA
Remove Asbestos-Contaminated Material (In accordance with all applicable regulations and contract requirements, including but not limited to preparation of work areas, installation of critical barriers, polyethylene sheeting containment barriers, installation/setup of HEPA Microtrap machines, decontamination enclosures, material removal and required cleaning to meet air clearance standard, dismantling and removal of containment and equipment at conclusion of project).
Demolition in asbestos contaminated area, Plaster and Lath ceiling, including suspension systemSF
Demolition in asbestos contaminated area, ceiling, suspended acoustical tileSF
Demolition in asbestos contaminated area, concealed spline ceiling systemSF
Demolition in asbestos contaminated area, ceiling, gypsum boardSF
Demolition in asbestos contaminated area, ceiling, Fiberglass Batt InsulationSF
Demolition in asbestos contaminated area, ceiling, Fiberglass Pipe InsulationLF
Remove Asbestos-Containing Material (In accordance with all applicable regulations and contract requirements, including but not limited to preparation of work areas, installation of critical barriers, polyethylene sheeting containment barriers, installation/setup of HEPA Microtrap machines, decontamination enclosures, material removal and required cleaning to meet air clearance standard, dismantling and removal of containment and equipment at conclusion of project).
Transite Board
Cement-asbestos Transite Board (i.e, in Laboratory Fume Hood or Benchtop)SF
Surfacing (Plaster /Sheetrock)
ACM Plaster Ceiling (including suspension system and lath)SF
ACM Plaster Wall (including lath)
ACM Sheetrock Ceiling (clean studs and leave in place)
ACM Sheetrock Wall (clean studs and leave in place)SF
ACM Sheetrock Ceiling including suspension system
ACM Sheetrock Wall including studsSF
Ceiling Tiles
Ceiling Tiles with ACM Mastic (glue daubs)SF
Vinyl Asbestos Floor Tile/Mastic
Single Layer of Vinyl Asbestos Tile and ACM MasticSF
for each additional Layer of VAT and ACM Mastic addSF
Single Layer of Vinyl Composition Tile (non-ACM) & ACM MasticSF
for each additional Layers of non-ACM VCT and ACM Mastic addSF
Remove ACM Mastic (only) from Concrete floorsSF
Carpet
Remove Asbestos-Contaminated Carpet from FloorSF
Duct Insulation
Remove Boiler Breeching, Duct or AHU Insulation (to 1" thick)SF
Remove Boiler Breeching, Duct or AHU Insulation (to 2" thick)SF
Pipe Insulation (Full Containment)
to 4" Insulation Size (Outside Dia.)LF
to 8" Insulation Size (Outside Dia.)LF
to 12" Insulation Size (Outside Dia.)LF
Pipe Insulation (GloveBag Method)
to 4" Insulation Size (Outside Dia.)LF
to 8" Insulation Size (Outside Dia.)LF
to 12" Insulation Size (Outside Dia.)LF
Spray-on Fireproofing
Remove asbestos insulation or fire proofing from decking, beams, columns, joists or other flat structural surfaces plus any overspraySF
Remove asbestos insulation or fire proofing from irregular surfaces plus any overspraySF
REINSTALL ITEMS (INCLUDES CLEANING)
Reinstallation
Re-install existing 2 x 4 fluorescent light fixtureEA
Re-install existing suspended acoustical ceiling tiles in existing gridSF
Reinstall all movable furniture, equipment, etc. after work is complete (excluding office partition units)Day
WASTE DISPOSAL
Disposal
Asbestos waste disposal charges, including haulC.Y.
Disposal of Non-ACM Construction and Demolition MaterialC.Y.

&"-,Bold"&14HAZARDOUS MATERIALS ABATEMENT

UNIT PRICING TABLE

LEAD

ITEM UNIT OF MEASURE UNIT PRICE

REMOVAL OF LEAD BASED PAINT (LBP)
Pre-Work
Attend on-site pre-start meeting, prepare and submit brief lead abatement work plan, project schedule, decontamination unit sketches and worker qualificationsEA
Mobilize All Personnel and Equipment To Site (Within 72 Hour Notice)
Mobilize All Personnel and Equipment To Site (> 72 Hour Notice)EA
Containment
Preparation of lead containment area in accordance with all applicable regulations and contract requirements and post-abatement cleaning (including but not limited to pre-cleaning, HEPA vacuum and wet wipe floor and wall surfaces, cover non-work surfaces with polyethylene sheeting)SF of Floor Area
Encapsulation
Encapsulation of lead-based paint, interior, brushwork, trim, under 6"LF
Encapsulation of lead-based paint, interior, brushwork, trim, 6" to 12" wideLF
Encapsulation of lead-based paint, interior, brushwork, balustradesLF
Encapsulation of lead-based paint, interior, brushwork, pipe, to 4" diameterLF
Encapsulation of lead-based paint, interior, brushwork, pipe, to 8" diameterLF
Encapsulation of lead-based paint, miscellaneous, steel, flat surfacesSF
Encapsulation of lead-based paint, miscellaneous, steel, beams, brushworkSF
Encapsulation of lead-based paint, miscellaneous, steel, trussesSF
Removal
Removal of lead-based paint, baseboard, to 8" wideLF
Removal of lead-based paint, balustrades, one sideSF
Removal of lead-based paint from doorsSF
Removal of lead-based paint, from door frames, trim to 6"LF
Removal of lead-based paint, handrailsLF
Removal of lead-based paint, frame and trimLF
WASTE PACKAGING, HANDLING AND DISPOSAL
Disposal of Lead-containing Hazardous Waste (> 5 parts per million of leachable lead by Toxicity Characteriustic Leaching Procedure)55-gallon Drum
Disposal of Lead-containing Non-Hazardous Waste (< 5 parts per million of leachable lead by Toxicity Characteriustic Leaching Procedure)55-gallon Drum

MOLD

ITEM UNIT OF MEASURE UNIT PRICE

PRE-WORK REQUIREMENTS
Submittals
Attend on-site pre-start meeting, prepare and submit brief mold abatement work plan, project schedule and worker qualificationsEA
Mobilize All Personnel and Equipment To Site (Within 72 Hour Notice)EA
Mobilize All Personnel and Equipment To Site (> 72 Hour Notice)EA
CONTAINMENT & PREPARATION IN MOLD-IMPACTED AREA
Remove and relocate within facility all movable furniture, etc.HR
Hard Separation barrier, 2" x 4" wood studs @ 16", 1/2" plywood ea. side to 8' heightSF
Hard Separation barrier, 2" x 4" wood studs @ 16", 1/2" plywood ea. side to 12' heightSF
for heights above 12' add
Remove Mold-Impacted Material. Establish HEPA-filtered negative pressure containment as stipulated in the project documents.
Carpet (remove and dispose)SF
Vinyl Cove Base Molding (remove and dispose)SF
Vinyl Floor Tile and Mastic (remove and dispose)SF
Wall Plaster and Lath (remove and dispose)SF
Ceiling Plaster and Lath (remove and dispose)SF
Sheetrock Wall (remove and dispose, leave studs in place)SF
Sheetrock Wall (remove and dispose of entire wall system including studs)SF
Sheetrock Ceiling (remove and dispose, leave studs in place)SF
Sheetrock Ceiling (remove and dispose of entire wall system including studs)SF
Suspended Acoustical Tile Ceiling (clean grid and leave in place)SF
Suspended Acoustical Tile Ceiling (remove and dispose of entire ceiling syetm including grid and ceiling tile)SF
Concealed spline ceiling system (remove and dispose)SF
Fiberglass Pipe Insulation (remove and dispose)LF
Remove, clean and store on-site non-impacted suspended acoustical ceiling tile system complete with metal T-grid and tileSF
Remove and clean 2 x 4 fluorescent light fixtures, store on siteEA
Apply Mold-Inhibitor to Surface Following Abatement (e.g. wall cavity, chase)SF

File details come from the government source that posted it.