About this file

36C24219Q0179 QUALITY ASSURANCE SURVEILLANCE PLAN.docx

View the file

Other files

File Type Posted
36C24219Q0179-0001000.docx DOCX document
36C24219Q0179-002.pdf PDF
36C24219Q0179-001.docx DOCX document
36C24219Q0179-004.docx DOCX document
36C24219Q0179-005.pdf PDF
36C24219Q0179-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN:

Purpose:

The purpose of this Quality Assurance Surveillance Plan (QASP) is to provide guidance on how the quality of services provided under this contract will be monitored.

This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance.

This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the contractor. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.

Scope:

The areas to be addressed under the QASP are as followed:

1. PRELIMINARY ASBESTOS ASSESSMENT

2. ASBESTOS SAMPLING AND ANALYSIS

3. ASBESTOS/LEAD/MOLD SURVEY REPORT

4. ASBESTOS PERIODIC SURVEILLANCE

5. ASBESTOS ABATEMENT DESIGN

6. ASBESTOS PROJECT AIR MONITORING

7. ASBESTOS FINAL AIR CLEARANCE MONITORING

8. ASBESTOS ABATEMENT COMPLIANCE REPORT

Quality Assurance Check Points:

The table below describes the areas to be reviewed in the QASP process. Quality assurance will be conducted by the Contracting Officer’s Representative (COR), of the Facility Management Service (FMS). The results of the QASP will be approved by the COR.

Required Service
Standard
Acceptable Quality Level
Method of Surveillance
Incentive
Visually inspect project areas designated by VA and Submit a description of preliminary asbestos assessment and anticipated abatement issues.
The information obtained in performance of this task shall be sufficient to develop a proposal for sampling, analysis and survey report when requested by VA.
95%
COR complaints that standard is not being met.
Positive past performance and exercise upcoming option period
Conduct Lead-Based Paint Sampling and Analysis and Mold Sampling and Analysis
Samples will be collected and analyzed in accordance with EPA and New Jersey State protocols, OSHA 29 CFR and other applicable standards.
100%
COR complaints that standard is not being met.
Positive past performance and exercise upcoming option period
Submit Asbestos/Lead/Mold Survey Report
Submit all the information requested under Task 3 a-g in the Statement of Work.
95%
COR complaints that standard is not being met.
Positive past performance and exercise upcoming option period
Perform Asbestos Periodic Surveillance
VHA Directive 714, “Asbestos Management Program” and other applicable regulations
100%
COR complaints that standard is not being met.
Positive past performance and exercise upcoming option period
Perform Asbestos Abatement Design
Design shall conform to all applicable regulations and relevant professional standards.
100%
COR complaints that standard is not being met.
Positive past performance and exercise upcoming option period
Conduct Asbestos Project Air Monitoring
Air monitoring shall be conducted by an experience and certified Industrial Hygienist.
100%
COR complaints that standard is not being met.
Positive past performance and exercise upcoming option period
Conduct Asbestos Final Air Clearance Monitoring
VHA Directive 714, “Asbestos Management Program” and other applicable regulations
100%
COR complaints that standard is not being met.
Positive past performance and exercise upcoming option period
Provide with Asbestos Abatement Compliance Report
Contractor shall provide accurate analysis report.
100%
COR complaints that contractor fail to report
Positive past performance and exercise upcoming option period
Response Time
Within 24 hours for Emergency and within 72 hours for Non-Emergency.
95%
COR complaints that contractor fail to respond within the specified timeframe.
Positive past performance and exercise upcoming option period.

Government roles and responsibilities:

The following personnel shall oversee and coordinate surveillance activities.

a. Contracting Officer (CO) - The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.

Assigned CO: Delfo Saco-mizhquiri

b. Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.

Assigned COR: Leighton Smith

Corrective Action:

The Contractor will be notified any time a performance standard is missed or of any complaints related to services provided or personnel performance issues. The Contractor will be given an opportunity to correct any deficiency noted. The timeframe for correcting deficiencies will be determined on a case by case basis by the Contracting Officer or COR depending of the circumstances.

File details come from the government source that posted it.