36C24126Q0602_1.docx
DOCX document 19 KB Posted
- Solicitation number
- 36C24126Q0602
About this file
This is Amendment No. 1 to a combined synopsis/solicitation for commercial HVAC replacement services at the VA Connecticut Healthcare System West Haven Medical Center. The amendment incorporates Questions and Answers submitted by prospective offerors by July 3, 2026, which clarify and modify the original solicitation requirements. Key clarifications include: the "steam coil timeline" reference in the SOW is a typographical error and should be disregarded; all refrigerant piping from the branch box to each of the seven evaporators must be replaced in addition to the 275 feet of line sets from branch box to condenser; standard insulation is acceptable for refrigerant lines; only brazed refrigerant piping connections are permitted; the branch box must be replaced; the new VRF system shall not connect to building management systems and will operate with standalone controls; the VA will supply power only to the main disconnect, with the contractor responsible for all other power wiring; new thermostats and low-voltage interlock wiring are required with no reuse of existing controls; work may proceed during summer as the unit is currently non-operational; all applicable taxes must be included in pricing; work shall comply with applicable infection control requirements for each work location; work hours are 7:00 a.m. to 4:00 p.m. Monday-Friday for standard tasks, with crane operations and tasks impacting medical center operations coordinated outside regular business hours or weekends; and modifications to the commercial services contract are governed by FAR 52.212-4(c) with equitable adjustments available only through bilateral modification. The original solicitation deadline was July 13, 2026, at 4:00 p.m. Eastern Time, with responses directed to Contracting Specialist Juliette Buchanan at the VA Network Contracting Office in Providence, Rhode Island. The acquisition is 100% set aside for verified Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) with a NAICS code of 238220 and FSC/PSC of Z1DZ.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24126Q0602.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment to a Previous Combined Solicitation
Amendment to a Previous Combined Solicitation
| SUBJECT* |
| Replace DNA Laboratory HVAC at West Haven, CT VAMC |
GENERAL INFORMATION
| CONTRACTING OFFICE’S ZIP CODE* |
| 02908 |
| SOLICITATION NUMBER* |
| 36C24126Q0602 |
| RESPONSE DATE/TIME/ZONE |
| 07-13-2026 16:00 EASTERN TIME, NEW YORK, USA |
| ARCHIVE |
| 30 DAYS AFTER THE RESPONSE DATE |
| RECOVERY ACT FUNDS |
| N |
| SET-ASIDE |
| SDVOSBC |
| PRODUCT SERVICE CODE* |
| Z1DZ |
| NAICS CODE* |
| 238220 |
| CONTRACTING OFFICE ADDRESS |
| Network Contracting Office 1 |
VAMC Providence
830 Chalkstone Avenue Providence RI 02908
POINT OF CONTACT*
Contract Specialist Juliette Buchanan juliette.buchanan@va.gov
PLACE OF PERFORMANCE
| ADDRESS |
| US Department of Veterans Affairs |
VA Medical Center West Haven
950 Campbell Avenue
West Haven CT
| POSTAL CODE |
| 06516 |
| COUNTRY |
| USA |
ADDITIONAL INFORMATION
AGENCY’S URL
URL DESCRIPTION
| AGENCY CONTACT’S EMAIL ADDRESS |
| juliette.buchanan@va.gov |
EMAIL DESCRIPTION
DESCRIPTION
AMENDMENT NO. 1
SOLICITATION NO. 36C24126Q0602
DATE: 7/7/2026
1. THE SOLICITATION IS HEREBY AMENDED AS FOLLOWS:
a. The following Questions and Answers, submitted by prospective offerors by July 3, 2026, are incorporated into this solicitation.
b. The Government’s responses modify and/or clarify the solicitation.
c. All other terms and conditions of the solicitation remain unchanged. Vendors are reminded to review all other aspects of the solicitation and consider this amendment when preparing their responses.
2. RFI QUESTIONS AND ANSWERS
· SOW refers to “steam coil timeline” under qualifications which appears to be a typo error as the scope does not appear to include steam coil. Please confirm.
The reference to “steam coil timeline” in the Qualifications section of the SOW is a typographical error. The project scope does not include any steam coil components or steam system work. Offerors should disregard this phrase.
· SOW item 5 and 8 refer to replacement of approximately 275 feet of line sets from the branch box to the condenser, however it does not seem to mention replacement of the piping from the branch box to each evaporator (of which there are 7 listed in the scope. Please confirm if the refrigerant piping from the branch box to each evaporator will also need to be replaced.
All piping associated with refrigerant must be replaced.
· Please confirm if standard ½” insulation is acceptable for refrigerant lines or if VA specification 230711 will need to be followed requiring 1” insulation.
Standard for this project is acceptable.
· Please confirm “zoom lock” refrigerant piping is not acceptable as per typical VA standards.
Braze only.
· SOW mentions connecting to the branch box but not replacing it. If the branch box is a different refrigerant type, it is assumed that it would need to be replaced. Please confirm.
Must replace.
· Please confirm the VRF system is not to be connected to JCI or Siemens building management DDC system.
Not Connected.
· SOW item 9 states the VA will connect electrical service to the unit. Please confirm this includes all power wiring required to each evaporator and branch box and condenser.
The VA will only supply power to the main disconnect. The VA will NOT be connecting to any other power source.
· Please advise if new thermostats and low voltage interlock wiring is required, or if it is anticipated that the existing controllers and wiring are to be reused.
New is required, no use of existing.
· Please advise if the replacement will need to take place during fall after cooling is not needed, or if the system is not functional and replacement is able to be performed during summer.
Can and should be done prior to end of cooling season. Unit is not operational.
· Will the sign-in sheet from site visit be available in addendum?
No.
· Please confirm if tax should be included in our proposal? Will an exempt certificate be provided?
Contractors are required to include all applicable taxes in their proposed prices unless the solicitation states otherwise. A tax-exempt certificate will be provided for purchasing materials for use in a tax‑exempt government project if state law requires it.
· What are the ICRA level requirements in the work areas with piping and evaporators?
All work shall comply with the requirements applicable to each individual work location. The required equal level shall be determined based on the specific scope of work, the patient risk, classification and the occupancy of the area in which the work is being performed. The contractor is responsible for complying with all infection control measurements.
· Is the use of temporary plastic wall panels (such as STARC panels) acceptable to meet ICRA requirements?
All work shall comply with the requirements applicable to each individual work location. The required equal level shall be determined based on the specific scope of work, the patient risk, classification and the occupancy of the area in which the work is being performed. The contractor is responsible for complying with all infection control measurements.
· Will work need to be conducted during off hours?
Per the Statement of Work: Work shall occur during regular business hours from 7:00 a.m. – 4:00 p.m. Monday – Friday and tasks with impact to Medical Center operations shall be coordinated outside of regular business hours and/or on the weekend 7:00 a.m. – 4:00 p.m. Saturday – Sunday. No work shall be performed on Government Holidays unless an emergency status has been indicated by the Contracting Officer.
Crane pick shall be coordinated outside of regular business hours and/or on the weekend 7:00 a.m. – 4:00 p.m. Saturday – Sunday.
· Will shutdowns be required to be done during off hours or weekends?
The system is currently not operational, so no shutdown is required.
· Will area be occupied during HVAC replacements?
Coordination with service is required to separate staff from workspace.
· Please confirm or advise how existing controls are connected to the existing system? Mitsubishi systems have their own control system. Is the intent to have BACnet included for direct BMS connection?
Standalone controls for each head, no BMS.
· Please provide electronic copies of the floor plans handed out during the site visit.
Unsure of what floor plans are being referred to.
· Are as-builts available showing the existing piping routing?
Not available.
· Will unforeseen conditions be addressed via the changed clause per VAAR 852.243-70 or FAR 52.243-4? #5 on page 4 indicates “approximately” No. Because this requirement is being solicited as a commercial services contract under FAR Part 12, neither VAAR 852.243‑70 (Construction Contract Changes) nor FAR 52.243‑4 (Changes—Construction) applies.
FAR 52.212‑4(c) (Changes) governs permissible changes to commercial contracts.
Any modification must be within scope and mutually agreed to by both parties.
Equitable adjustments related to unforeseen conditions may be addressed only through a bilateral modification, since unilateral change authority does not apply to commercial services unless explicitly stated.