Statement of Work SOW.pdf
PDF 76 KB Posted
- Attached to
- J091--Fuel Oil Tank Inspection Service Contract
- Solicitation number
- 36C24126Q0076
About this file
This Statement of Work (SOW) details tank inspection services for the VA Maine Healthcare System in Augusta, ME. The project involves conducting 5-year external and 10-year internal inspections on two aboveground storage tanks (Tank A and Tank B), each with a 74,000-gallon capacity. The inspections must be performed by API 653 certified inspectors using unmanned (robotic) techniques, with no personnel allowed to enter the tanks. The contractor is required to submit an Activity Hazard Analysis and Safety Plan at least 20 business days prior to work, and must comprehensively inspect tank components including foundation, shell, roof, appurtenances, and interior surfaces following the API 653 Appendix C Checklist. The period of performance is 30 days from contract award, with the facility's daily fuel usage ranging from 1,000 gallons in summer to 5,000 gallons in winter, necessitating careful coordination of tank inspections to minimize operational disruption.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW Attachment 1 - API 653 Appendix C Checklist.pdf | ||
| Attachment 852.219-75 Limitation on Subcontracting.pdf | ||
| 36C24126Q0076.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Project Title: Inspection of Oil Tanks - 5-Year and 10-Year Inspections Project Number: 402-25-207SC Location: VA Maine Healthcare System, 1 VA Center, Augusta, ME Period of Performance: 30 Days from Contract Award
1. General Scope
The Contractor shall provide tank inspection services at the VA Maine Healthcare System located at 1 VA Center in Augusta, ME. The facility has two aboveground storage tanks (Tank A and Tank B), each with a capacity of 74,000 gallons. The Contractor is required to perform both 5-year (external) and 10-year (internal) inspections on both tanks in accordance with sections 6.3 and 6.4 of the American Petroleum Institute (API) Standard 653.
Both tanks are currently in service. For internal inspections, unmanned (robotic) inspections are mandated. No personnel shall enter the tanks, and the facility will not drain the tanks for any purpose.
If necessary, only one tank may be removed from service at a time. The Contractor must coordinate with the Government regarding the timing of out-of-service inspections. The facility's daily fuel usage ranges up to approximately 1,000 gallons in summer and up to 5,000 gallons in winter.
2. Pre-Work Submissions
The following documents must be submitted by the Contractor and approved by the Government at least 20 business days prior to the start of work:
• Activity Hazard Analysis (AHA): The AHA should cover all aspects of the work, including but not limited to:
1. Tank Inspection
2. Fall Protection
3. Lockout/Tagout
4. Hoisting/Lifting
The Government reserves the right to request additional AHAs not listed above without additional cost. Each AHA must reference safety precautions, personal protective equipment (PPE), and other precautions as specified in the Safety Data Sheet (SDS) for #2 fuel oil and related hazards. The AHA must document job steps with the corresponding:
1. Hazards
2. Controls
3. Risk Assessment Code (RAC)
4. Equipment to be Used
5. Training Requirements
6. Inspection Requirements
Note: VA Maine requires the Contractor to place locks/tags on equipment locked out by the VA Facilities.
• Safety Plan: Corporate safety and health policies and procedures.
3. Inspection Requirements
The Contractor must employ API 653 certified inspectors. The inspections shall be conducted as outlined below and in strict compliance with the attached API 653 Appendix C Checklist (Attachment 1). Inspections must incorporate any updates or revisions made to the checklist by the API that are not reflected in Attachment 1.
A. In-Service Inspections
• Perform inspections using the attached checklist, including but not limited to:
1. Tank Foundation (C1.1)
2. Tank Shell (C1.2)
3. Shell Appurtenances (C1.3)
4. Tank Roof (C1.4)
5. Roof Appurtenances (C1.5)
6. Access Structures (C1.6)
B. Out-of-Service (Internal) Inspections
• Perform internal inspections including but not limited to:
1. Safety Checks (C2.1)
2. Inspection of Tank Exterior (C2.2)
3. Inspection of Bottom Interior Surface (C2.3)
4. Inspection of Shell Seams and Plate (C2.4)
5. Inspection of Shell Mounted Overflows (C2.6)
6. Inspection of Fixed Roof Appurtenances (C2.7)
7. Inspection of Floating Roof (C2.8)
8. Inspection of Floating Roof Seal Assemblies (C2.9)
9. Inspection of Floating Roof Appurtenances (C2.10)
10. Inspection of Common Tank Appurtenances (C2.11)
4. Reporting
The Contractor shall provide a detailed inspection report that includes the results of all inspections and recommendations for repair.
Attachments
• Attachment 1: API 653 Appendix C Checklist
Please let me know if there are any additional details or specific adjustments you would like to include.