Correct Deficiencies Generator Buildings 1WA 1EA Full Specifications Final.pdf
PDF 2 MB Posted
- Solicitation number
- 36C24125R0038
About this file
This is a comprehensive technical specification document for a construction project to correct deficiencies in Generator Buildings 1WA and 1EA at the VA Medical Center in Leeds, Massachusetts. The project involves demolition, site preparation, and installation of new systems including electrical upgrades, generator modifications, fire suppression systems, and building improvements. The total project value is estimated between $1,000,000 and $5,000,000, with a solicitation expected to be issued on or about March 29, 2025.
Key technical requirements include replacing six automatic transfer switches, adding egress doors, modifying generator exhaust systems, installing generator docking stations, updating coordination studies, installing new surge protection devices, and implementing comprehensive labeling across multiple building systems. The project also requires specialized work such as clean agent fire suppression system installation, advanced utility metering, and integration with existing campus control systems. Contractors must comply with strict VA specifications, including detailed safety requirements, environmental controls, and complex technical integration standards for building automation and control networks.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C01_36C24125C0071_SAM Award Notice.pdf | ||
| 28 31 00.pdf | ||
| 36C24125R0038_Amendment 0002.pdf | ||
| 26 36 23.01.pdf | ||
| 36C24125R0038_amendment 1.pdf | ||
| 631-18-003 sign-in.pdf | ||
| Past Performance Questionnaire (2).pdf | ||
| Drawings Generator Building 1EA 1WA Final.pdf | ||
| 36C24125R0038_Solicitation.docx | DOCX document | |
| 36C24125R0038_Pre-Solicitation Notice.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. 631-18-003
Correct Deficiency Generator Buildings 1WA, 1EA
VA Medical Center, Northampton, MA
Construction Documents
Specifications
September 30, 2024
DEPARTMENT OF VETERANS AFFAIRS
Medical Center
421 North Main Street Leeds, MA 01053
Correct Deficiency Generator Buildings 1WA, 1EA
631-18-003 09-30-24
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 05-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 06-21 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-21 01 74 19 Construction Waste Management 01-21 01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 Flashing and Sheet Metal 01-21 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17
DIVISION 08 - DOORS AND WINDOWS
08 11 13 Hollow Metal Doors and Frames 01-21 08 71 00 Door Hardware 01-21
DIVISION 09 - FINISHES
09 91 00 Painting 01-21
DIVISION 21- FIRE SUPPRESSION
00 01 10 - 2
SECTION NO. DIVISION AND SECTION TITLES DATE
21 22 00 Clean Agent Fire Suppression Systems 05-15
DIVISION 23 – MECHANICAL
23 09 23 Direct Digital Control System for HVAC 03-23 23 10 01 Facility Fuel Oil Day Tanks and Piping Systems 04-20 23 51 00 Breechings, Chimneys And Stacks 04-20
DIVISION 25 – INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 02-10
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 23 Electrical Identification 09-21 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protection Device Coordination Study 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 36 23 Automatic Transfer Switches 01-17 26 36 23.01 Generator Docking Station 01-17 26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 01-18 26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19 27 05 33 Raceways and Boxes for Communications Systems 10-18
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 11 Earthwork 07-16 31 23 19 Dewatering 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 17 23 Pavement Markings 08-16 32 90 00 Planting 08-16
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
NO. SHEET TITLE
1 GI001 COVER SHEET
2 GI002 DRAWING INDEX
3 GI003 GENERAL NOTES
4 GI004 LIMITS OF CONSTRUCTION
5 GI006 EROSION CONTROL DETAILS
6 AE-001 GENERAL CONDITIONS
7 MH001 MECHANICAL LEGEND AND NOTES
8 EP001 ELECTRICAL LEGEND AND NOTES
9 ESS502 LOW VOLTAGE ELECTRICAL DETAILS
10 ESS602 AUTOMATIC TRANSFER SWITCH CONTROL DIAGRAM
11 ESS603 METERING SYSTEM RISER DIAGRAM
12 01EA-GS-101 BUILDING NO. 1EA - EXISTING CONDITIONS-REMOVAL PLAN
13 01EA-GS-102 BUILDING NO. 1EA - SITE PLAN
14 01EA-GS-501 BUILDING NO. 1EA - CIVIL DETAILS
15 1EA-AE-101 BUILDING NO. 1EA - DEMOLITION AND RENOVATION PLANS
16 01EA-MH101 BUILDING NO. 1EA - MECHANICAL DEMOLITION PLAN
17 01EA-MH201 BUILDING NO. 1EA - MECHANICAL PLAN
18 01EA-EP101 BUILDING NO. 1EA FIRST LEVEL ELECTRICAL PLAN
19 01EA-EP601 BUILDING NO. 1EA - PANEL SCHEDULES
20 01WA-GS-101 BUILDING NO. 1WA - EXISTING CONDITIONS-REMOVAL PLAN
21 01WA-GS-102 BUILDING NO. 1WA - SITE PLAN
22 01WA-GS-501 BUILDING NO. 1WA - CIVIL DETAILS
23 1WA-AE-101 BUILDING NO. 1WA - DEMOLITION AND RENOVATION PLANS
24 01WA-MH101 BUILDING NO. 1WA - MECHANICAL DEMOLITION PLAN
25 01WA-MH201 BUILDING NO. 1WA - MECHANICAL PLAN
26 01WA-EP101 BUILDING NO. 1WA - ELECTRICAL PLAN
27 01WA-EP601 BUILDING NO. 01WA - PANEL SCHEDULES
- - - E N D - - -
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing electrical equipment, and furnish labor and materials and perform work for correcting deficiencies in generator building 1WA and 1EA as required by drawings and specifications. Work will include but is not limited to the following:
1) Base bid
a) Replacing 6 existing automatic transfer switches on the LV electrical system with new automatic transfer switches with bypass feature and upgrades to the respective feeders and controls.
b) Adding egress doors for existing generator buildings 1EA and 1WA and modify the existing generator exhaust systems at buildings
1EA and 1WA.
c) Provide generator docking station for portable generator connections at building 1EA and 1WA, add new surge protection devices.
d) Exterior Systems – exterior building lighting as indicated on the Contract Documents.
e) Update the coordination study in Generator building 1WA and 1EA, fault current study and arc-flash labeling. Provide new labels for all equipment, panels or disconnects where the study requires changes to the boundary levels or available energy levels from the previous study.
f) Labeling and relabeling existing and new panelboards, switchboards, mechanical equipment, elevator equipment, transfer switches, disconnect switches, HVAC equipment, pumps, chillers, AC equipment, IT circuits, J-boxes, receptacles, lighting switches, includes all previously labeled equipment that will have their designations changed to match the new campus standard, this is required throughout Buildings 1WA, and 1EA, and others
01 00 00 - 2 areas as noted on the contract documents. The new tagging and labels shall match the facility standards.
2) Bid Options priced by line item
a) Remove and replace current generator day tanks in building 1WA and
1EA. Integrated into the existing generator controls.
b) Dry chemical fire suppression in 1WA and 1EA. The existing fire alarm will be utilized to integrate the new suppression system.
c) Communication Systems wiring infrastructure updates for status, alarm, and metering. The proposed alarm and metering system shall be seamless integrated into the existing Building Management
System (BMS) Direct Digital Controls. The existing Campus system is a Johnson Control System (SNE Buildings System). The existing
BMS network will be utilized to integrate the Advanced Metering
System and Transfer Switch Monitoring System into the existing
Johnson Control System.
d) Building metering at each service for 1WA and 1EA as indicated on the Contract documents. Metering shall be networked over the existing Building Management System (BMS) Direct Digital Control system.
B. Offices of DuBois & King, Inc., 85 Main Street, Springfield, VT 05156, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting
Officer or his duly authorized representative.
C. Before placement and installation of work subject to tests by testing laboratory retained by the Contractor, the Contractor shall notify the
COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 - 3
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, grading, site restoration, necessary removal and replacement and upgrading of electrical equipment and construction and certain other items.
B. The period of performance for this project is 470 calendar days; the first 45 days shall be utilized for administration time to complete preconstruction submissions and other preparation prior to the start of construction. Construction cannot commence until preconstruction submittals have been approved. The construction shall be completed within the remaining period of 425 days.
C. Any deviation from the specification will require a formal memo from the subject matter expert (manufacturer, subcontractor) that proposed product/assembly meets the intent of the specification and why the specificity of the specification cannot be met.
1.4 PROJECT MANAGEMENT TEAM
A. All of the people listed below need to attend all construction meetings.
B. Provide preconstruction submittal with delegation and identification letter for each of the persons below including any resumes or certifications demonstrating to the below requirements.
C. Project Manager
a. Minimum 10 years construction experience with at least 5 years management experience with projects similar in size and scope.
b. The Project Manager shall be a separate qualified individual from the Prime Contractor’s Superintendent and Safety Manager having duties only as the Project Manager.
D. Superintendent
1. Provide project superintendent with a minimum of [10] years of experience in construction with at least [5] of those years as a superintendent on projects similar in size and complexity.
The individual must be familiar with the requirements of OSHA and have experience in the areas of hazard identification and safety compliance in addition to safety training requirements
01 00 00 - 4 indicated elsewhere in the project documents. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The project superintendent shall be dedicated to this project only and not assigned on other contracts.
2. The Superintendent shall be a separate qualified individual from the Prime Contractor’s Project Manager and Safety
Manager.
3. The General Contractor must provide adequate supervision for all locations (buildings) of work whenever work is being performed. This supervision must come from the General
Contractor and must be a competent person. This project will potentially have work in multiple locations concurrently and the General Contractor is expected to provide required additional supervision.
E. Safety Manager
1. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and must meet requirements in 01 35 26 specification and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State and local requirements are met for the project.
2. The SSHO shall be a separate qualified individual from the
Prime Contractor’s Project Manager and Superintendent.
1.6 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. Every contractor (subcontractors included) must have a physical access PIV Badge. The badge must be a current VA issued badge but does not need to be issued at this facility. This requires a minimum of two (2) visits to a VA – to get fingerprints taken (approx. 1
01 00 00 - 5 hour), to get sponsored (approx. 30 min), and to get the badge
(approx. 1 hour). The second two (2) are possible to get both done in one day. The only exception is contractors who do not need access to VA Buildings and who is also just working for the day.
3. All badges must be worn by every contractor (subcontractor) and visible at all times on the jobsite.
B. Security Procedures:
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate. These doors are for the new egress doors in buildings 1EA, 1WA.
3. The Contractor shall be responsible for any Government-owned keys that have been issued to them for access to facilities or areas pertinent to this contract.
4. Upon completion of the work in an area, or upon request of the
Contracting Officer, the key or keys relevant to the area shall be returned immediately. Keys shall be returned prior to final task order payments.
5. Should the Contractor Lose a Key: The Contractor shall notify the
Contracting Officer, immediately and in writing, but not later than one (1) working day after he is aware of the loss. Should the key not be found before final acceptance, the General Contractor will be responsible for replacing ALL cores associated with the lost key at
$45.00 per core. The $45 will be charged to the contract.
01 00 00 - 6
6. The General Contractor will be responsible for the costs associated with the replacement of the cores and any damages suffered by the
Government.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours
01 00 00 - 7 before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. Motor vehicles belonging to any contractor must be registered at the
Police HQ in Building 25 and attain a parking pass for employee lots. This includes personally owned and company vehicles. These passes must be visibly displayed at all times while parked on VAMC campus.
3. Contractor parking will be limited to Lots N and P and by written permission of the COR at any other employee lot. There will be absolutely no parking in patient parking spaces or ADA spaces
(unless the contractor has an applicable decal/tag). Failure to comply with motor vehicle restrictions, will result in ticket fines and/or vehicle towing.
4. Parking is rigidly controlled throughout the Medical Center.
Contractor parking is only allowed in designated areas (subject to change). Parking in designated patient parking areas is strictly prohibited. Parking on grass is also prohibited. Parking in roadways is prohibited. Parking for equipment necessary to perform the work will be authorized in advance of starting the project.
1.7 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer AND AS DIRECTED BY THE COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government.
C. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
D. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways
01 00 00 - 8 constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-4)
E. Working space and space available for storing materials shall be as directed by the COR.
F. Provide a Logistics Plan that includes a laydown area, delivery routes, container/equipment staging, temporary toilets, dumpsters, expected ingress and egress (if applicable), location of fencing for work area and laydown area, parking, etc. The COR must approve the Logistics Plan prior to the General Contractor executing.
G. All containers/pallets must be marked with the contractor/task order number 8-digit project number. Dumpster locations (not the individual dumpster) will also be marked if used over five (5) business days.
H. Workers are subject to rules of Medical Center applicable to their conduct.
I. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
J. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
01 00 00 - 9
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. The contractor should schedule delivery of material to limit the amount of storage space and time. VA Warehouse will not and cannot accept any contractor deliveries and will turn away any such deliveries.
4. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
K. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved.
L. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor. A compressed schedule is not allowed.
01 00 00 - 10
3. Utility disruptions will take place off hours. Any temporary power required shall be provided.
4. Operational Hours: 7:00am-6pm Monday through Friday.
5. Off-Hours: 6pm-7am Monday- Friday and anytime Saturday and Sunday.
Activities impacting normal operations or scheduling conflicts, or noisy work shall be scheduled off-hours.
M. Construction Fence: Submit proposed construction fence on the Logistic
Plan. All work and laydown areas are required to be fenced, and gates to be lockable. Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on coordinated with the
COR. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR. Provide the entire construction fence with an approved fabric privacy screening full height with wind cutouts. Opacity/shade percentage 85% lock-stitch strength 50 lbs. per ft consisting of a knitted high density polyethylene filament. Color and design to be approved by COR. All work areas and laydown spaces are required to be fenced.
N. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
O. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air
01 00 00 - 11 pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
2. Contractor shall submit a request to interrupt any such minor utility disruption of services to COR, in writing, 6 working days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption. Minor disruption is one that does not impact patients or employees.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR. The COR shall be notified of approximate dates of expected upcoming major interruptions 10 work days in advance so that the Medical Center can begin making plans for maintaining operations during the utility interruption.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
01 00 00 - 12
7. Review Fire Alarm System and Panels to be determined existing state and sign off that any troubles or other errors that occur are not and existing condition.
P. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes, vents, and the like, and their hangers or supports, shall be completely removed back to their source.
1. Those which are indicated to be abandoned but cannot be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from in an approved method and as accepted by the
COR.
2. Abandoned raceways that cannot be fully removed shall have the cables removed in all of those abandoned raceways and duct banks. Where removal of conduit and duct banks is not feasible and if approved by
COR, cut abandoned raceway at horizontal level (before turn up) and cap
(do not use tape-use an approved existing style conduit type cap) and paint cap red. Indicate location on the record documents.
3. The intent is that those systems listed above that are so embedded in existing concrete walls or floors that they cannot fully be removed without compromising the structure can be capped. These shall be fully investigated by the contractor and reviewed and accepted by the COR.
4. The lines shall not be capped in any finished or unfinished areas, but shall be removed and sealed, capped, or plugged in only in masonry, CMU, concrete walls, concrete ceilings or concrete floors where they penetrate those materials or if accepted by the COR within walls or partitions; so that they are completely behind the finished surfaces.
Q. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
R. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
01 00 00 - 13
1.8 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA, of buildings and areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of the building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
01 00 00 - 14
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably
01 00 00 - 15 interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-4)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. Contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified.
Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
01 00 00 - 16
- Designating areas for equipment maintenance and repair;
- Providing waste receptacles at convenient locations and provide regular collection of wastes;
- Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
- Providing adequately maintained sanitary facilities.
1.11 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for
01 00 00 - 17 any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the
Architect and engineer and is being provided for information only.
The Contractor shall field verify all existing conditions.
(FAR 52.236-4)
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration (historical data) are available from the COR.
C. A copy of the existing soil report(s) will be made available for inspection by bidders upon request to the Engineering Officer at the VA
Medical Center, which are records from the previous project designs and shall be considered part of the contract documents.
D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations.
1.13 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.14 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer
01 00 00 - 18 may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, and particularly as work progresses from area to area, Contractor shall have line grades and slopes of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of duct banks and concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each duct rout and building modification and/or addition.
2. Elevations of bottoms of trenches, manholes and vaults.
3. Lines and elevations of all outside distribution systems.
4. Lines of elevations of all swales and interment areas.
5.Lines and elevations of roads, streets and parking lots.
01 00 00 - 19
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.15 COORDINATION
A. Coordinate work and products meeting the requirements associated with all applicable specification sections and plans to produce a system complete, functional, and ready for the purpose intended.
B. Pre-worksite Re-visit Requirements: Before starting work in a particular area, visit the worksite and carefully examine the areas to verify complexity, existing conditions and difficulties that will affect work including all work done under various specification sections and the VA. Commencement of work shall be construed as acceptance of the existing conditions and difficulties. No change to the contract price or schedule shall be allowed for work caused by unfamiliarity with the site conditions that are visible or readily construed by an experienced observer.
C. Coordinate the location of all work, equipment and components with all trades and equipment installers to prevent interferences and maintain proper use and access to all items and spaces. Refer to the
“Coordination Drawing Checklist” for further details. General
Contractor is responsible for coordinating all equipment and components being installed with the placement location and dimension requirements.
Prior to job execution each trade shall submit “complete” coordinated shop drawings indicating all equipment and material layouts with locations from walls/columns, bottom/top elevations, vibration isolators, supports, dimensions, utility requirements and equipment submittal numbers. Each trade shall maintain a set of working drawings
01 00 00 - 20 to document as-built information as the work progresses and submit to the COR monthly for review.
D. New work shall be installed and connected to existing work neatly and carefully. All work shall be coordinated with other trades to avoid conflicts and to obtain a neat competent installation that will afford maximum accessibility for easy and proper operation, maintenance, service and headroom. All work shall be installed in a manner that permits easy accessibility and proper removal of system components requiring periodic service. Disturbed or damaged work shall be replaced or repaired to new conditions. Any items determined to be in non-compliance shall be corrected by the Contractor at no additional expense to the Government.
E. The drawings show or describe the general arrangement of equipment, articles, assemblies, appurtenances but do not show all required fittings, drains, air vents, supports and may not identify all required accessories, components, fittings, and offsets that are necessary to properly complete the installation for the purpose intended. The contract drawings are diagrammatic only intended to show general layout of conduit, ductwork, piping, equipment, terminals, specialties and not intended to show all required offsets, details, accessories and equipment to be connected. Provide all necessary fittings, offsets and pipe runs based on field measurements and reviewed coordination drawings. Coordinate with other trades for space available and relative location of equipment and accessories to be connected at all locations.
The Contractor shall alter locations of items where necessary to avoid interference and clearance difficulties. Locations of components and equipment shall be adjusted to accommodate the work with interferences anticipated and encountered. The Contractor shall determine the exact routing and location of systems prior to fabrication and installation.
Accurate field measurements and coordination drawings shall be prepared to establish the locations and characteristics of the various systems
(new and existing to remain). It is the intent of the drawings/specifications that the Contractor provides all materials, labor and coordination necessary to complete the work described or implied by the contract documents at no additional cost/time to the
Government. The Contractor shall propose with submitted coordination drawings other dimensions with similar characteristics where necessary
01 00 00 - 21 to avoid interferences and clearance difficulties. Should the contract documents not agree with themselves the greater quantity of superior work and materials shall be performed.
F. Coordinate all mechanical (eg, HVAC), electrical, plumbing (MEP) utility service, fire protection sprinkler system shutdowns and space access three (3) weeks in advance with the COR. Due to facility scheduling and access difficulties, some shutdowns and the performance of certain work will need to be performed during off-hours by the Contractor. Arrange phases and perform work to ensure utility services for other buildings and areas at all times as required.
1.16 AS-BUILT DRAWINGS
A. The contractor shall maintain a full size set of Red-line drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications. A copy of this set must be provided monthly with application for payment.
B. The installing contractor shall maintain as-built drawings of each completed phase for verification; and, shall provide the complete set at the time of pre-final punchlist. Provide record drawings as follows:
1. Red-lined, hand-marked drawings are to be provided, with one paper copy and a scanned PDF version of the hand-marked drawings provided on CD or DVD 15 work days prior to Pre-final punchlist.
The pre-final punchlist will not be held until complete red-lines are received.
2. Revit/Autocad as-built drawings are to be submitted in the most current version of the program.
C. The as-built drawings shall indicate the location and type of all lockout/tagout points for all energy sources for all equipment and pumps to include breaker location and numbers, valve tag numbers, etc. Coordinate lockout/tagout procedures and practices with local VA requirements.
D. Record Specifications: The Contractor shall maintain a copy of the Project Specifications, including addenda and modifications issued, for Project Record Documents. The Contractor shall mark
01 00 00 - 22 the Specifications to indicate the actual installation where the…