This document contains questions and answers regarding a project to replace locks at a Community Based Outpatient Clinic. The facility confirmed that the existing 26 doors are already prepared for the installation of ML2065 mortise locks and the existing door strikes can accommodate the locks. They prefer the ML190 sectional trim kit for the locks and confirmed the doors are 1-inch thick wood. Indicators and engraving are not required. The existing locks have independent deadbolts that will need filler plates. Pricing should be consolidated into the line items provided in Attachment 2 and include standard burden and overhead in the hourly rate. Acceptable work hours may vary from typical hours.

View the file

Other files for this federal contract opportunity

Other files attached to J063--CBOC Lock Replacement, newest first.
File Type Posted
36C24124Q0130_3.docx DOCX document
36C24124Q0130_2.docx DOCX document
Attachment 3 Past Performance Worksheet.xlsx XLSX spreadsheet
Attachment 1 SOW.pdf PDF
Attachment 4 852.219-75 VA Notice of Limitations on Subcontracting.docx DOCX document
Attachment 2 Price Schedule.xlsx XLSX spreadsheet
Combined Synopsis - Solicitation.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1. Do all of the existing 26 doors to be retrofitted with ML2065 mortise locks, currently all have ML2065 or similar dimension mortise locks installed in them allowing for the installation of the new locks without modification to the existing door? Simply, can the facility confirm all doors are already properly prepped for the installation of a ML2065 mortise lockset.

Answer: Confirmed.

2. Can the facility confirm all of the existing strikes on existing frames can properly accommodate the function and alignment of an ML2065 Mortise with deadbolt without any modification to the frame?

Answer: Confirmed.

3. Can the facility confirm which trim kit is desired - Escutcheon Trim (M31 in the attached brochure) or Sectional Trim (ML190 in the attached brochure)?

Answer: ML190 preferred.

4. Can the facility please confirm all doors are 1 ¾” thickness.

Answer: Confirmed.

5. Can the facility please confirm if doors are metal or wood.

Answer: Wood.

6. Can the facility confirm which style of indicator it would like in the attached brochure – V11 assumed.

Answer: V11 is acceptable.

7. Can the facility confirm whether the engraving “LOCK” arrow indicator option is wanted in the attached brochure – EMC assumed.

Answer: No, indicators itself are acceptable.

8. Are there currently separately installed deadbolts independent of the mortise in every door as task

(D) suggests? By stating the abandoned holes will need filler plates, this suggests there are deadbolts currently installed on the doors that act independently of the existing mortise.

Answer: Correct. They are currently separate.

9. There is no space within attachment 2 to include a separate cost for Project Management should the Attachment 2 Price Schedule be modified and an additional line item be added to accommodate this?

Answer: No, please consolidate pricing into the line items provided.

10. There is no space within attachment 2 to include Freight for the material, should the Attachment 2 Price Schedule be modified and an additional line item be added to accommodate this?

Answer: No, please consolidate pricing into the line items provided.

11. There is no space within attachment 2 to include Profit and Overhead should the Attachment 2 Price Schedule be modified and an additional line item be added to accommodate this?

Answer: No, please consolidate pricing into the line items provided.

12. We are assuming that the hourly rate in item number 0001 includes a standard burden in addition to the prevailing wage. Please confirm.

Answer: Yes.

13. Please advise if it is acceptable to submit pricing simply as one lump sum?

Answer: Yes

14. Please confirm acceptable work hours if they differ from typical work hours.

Answer: Yes