This document is a contract amendment that provides additional information and answers to requests for information (RFIs) related to Solicitation 36C24124B0054 for the Abate Asbestos Renovation 2024 project. The key details are:
The purpose of this amendment is to answer RFIs related to the abatement project. The agency is the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 1. The renovation work involves asbestos abatement in various rooms, with Room 2109 requiring complete abatement during off-hours over a weekend. All abatement work must be performed off-hours, while refinishing can occur during business hours. The contractor must provide 35 calendar days' notice prior to starting specific room abatement. The contractor is required to coordinate sequencing of the room abatement and refinishing with the Contracting Officer's Representative to minimize disruption to VA operations. No specific timeline or pricing details are provided in this amendment.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 631-23-016 36C241 Department of Veterans Affairs Network Contracting Office 1 VA Central Western Massachusetts HCS 421 North Main Street Leeds
MA
01053-9764 36C241 Department of Veterans Affairs Network Contracting Office 1 VA Central Western Massachusetts HCS 421 North Main Street Leeds
MA
01053-9764 To all Offerors/Bidders
36C24124B0054 10-07-2024
X X X
The purpose of this amendment is to answer RFIs. Please see below.
Chelsea Rodrigue Contract Opportunities
VA-VHA-RPOE-2024-0035
631-23-016 Abate Asbestos Renovation 2024 Site Visit Questions and Answers
Q1: Does the VA have a certain sequence for the rooms or are we able to schedule rooms in an order which is most efficient?
A1: There is no ordered sequence, however, the VA to have 35 calendar days notice prior to start detailing specific room start dates and finishes. Coordinate with COR.
Room 2109 MUST be completely abated during off hours, and over a weekend. Starting FRIDAY 1630 – MONDAY 0630. All areas are to be abated off hours. Re-finishing can occur during business hours. Sequencing of room abatement and refinish to be kept to absolute minimum in order for VA to return these spaces to use.
Q2: Will the VAIH be able to get TEM results within <12 hours to allow an area to be abated one night and the containment removed the next?
A2: Typical wait time for TEM results is 24hrs. This will depend on time of day delivered to lab and day of week. VA not planning on expediting TEMs.
Q3: Is the CPIH required to be onsite during the VAIHs clearance collection and during containment removal activities?
A3: Yes, CPIH is required to be onsite during all abatement activities – see Specification Section 2.2 for the scope of the CPIH. The CPIH is also expected to accompany the VPIH on all visual clearance inspections.
Q4: Can B044 and B046 be done together at one time?
A4: B044 and B046 can both be completed at the same time. However, the VA planned this to be done as separate containments and would need to be abated that way but can be done at same time. However, VA to have 35 calendar days notice prior to start detailing specific room start dates and finishes. Coordinate with COR.
Q5: At B12 Room 7, the door will need to remain open while awaiting the TEM results. Do you require plywood to be secured within the opening for security purposes?
A5: The SOW was incorrect in Room Number – see attachment “B12 Room 004” but correct is Room 4 the landing and room connected to the stairwell. There are three doors so it is expected that the outer door will be able to remain closed during abatement. Decon can go in Room B2 and window opens in B3 and can be used for negative air. Window unit will need to be removed (or moved) potentially so GC to include.
Q6: There is no vent location in 2109. Since this room requires TEM sampling, the containment will have to remain up for at least one daytime shift while the hospital is under operation. Can we vent through 2108? Keep in mind this will require HEPA exhaust tubing to be suspended from the ceiling until the containment is removed.
A6: Reference attachment “Ventilation in Room 2109”. Depending on when construction starts there are 3x windows that can be used for ventilation, rooms 2129, 2150, and 2152. VA to have 35 calendar days notice prior to start detailing specific room starts and finishes. Room 2109 MUST be completely abated during off hours, over a weekend. Starting FRIDAY 1630 – MONDAY 0630. Coordinate with COR.
GC will have to remove the whole window unit if they want to use window in room 2108.
Q7: Can you please provide the sign in sheet from the site walk?
A7: Yes, the sign in sheet is attached.
Q8: Is the base to be installed vinyl or carpet? And it all appeared to be 6", is that correct?
A8: Johnsonite 6” height Color: Snow White or equivalent. Supersedes 4” that is in the spec.
Q9: Waiting Room 2109 - Where is the closest exhaust/ventilation opening to route negative air?
A9: See answer to Q6.
Q10: Rooms 1072,1299,1293,2109 - Please confirm that there is tile and mastic under the carpet in these rooms.
A10: Based on previous adjacent abatement and homogeneous finish, the above rooms are presumed to have mastic and leveler that need to be abated.
Q11: Is the VA carrying a VPM for this off-hour project?
A11: The VA is providing a VPIH, the Contractor is responsible for a CPIH. VA will be using Mabbett and Associates Inc for VPIH services.
Q12: Who is responsible for paying for the TEM?
A12: VA is paying for the first TEM, contractor is responsible for subsequent TEMs if the first test fails.
Q13: Will every room be available during the entire project, or will they be completed in phases?
A13: There is no ordered sequence, however, the VA to have 35 calendar days notice prior to start - detailing specific room start dates and finishes. The ability to do multiple spaces will depend on the contractor # of crews, means and methods, and ability to immediately start refinishing after abatement activity. Coordinate with COR.
Room 2109 MUST be completely abated during off hours, and over a weekend. Starting FRIDAY 1630 – MONDAY 0630. All areas are to be abated off hours. Off Hours considered 1630-0630. Re-finishing can occur during business hours. Sequencing of room abatement and refinish to be kept to absolute minimum in order for VA to return these spaces to use.
Q14: Thermoset Rubber base is listed on the Specifications but no brand, color, or Height. Just straight base for carpet and cove for LVT. Most of the rooms have 6-inch base, should we figure for 6-inch base or 4-inch base?
A14: See Q8.
Q15: Is self-leveling required?
A15: Yes see Spec 09 05 16.
Q16: B044 Carpet Tile is Shaw Veil Match Existing Color. What color is the Existing color?
A16: Product has been discontinued, replace with Structure 5T297 24” x 24”
Q17: Who is responsible for moving furniture?
A17: VA will move furniture.
Q18: Is there a Wage Determination?
A18: The appropriate wage determination is MA20240003 10/11/2024. See Attached.
Q19: There is an Above Ceiling Work Permit attached in the solicitation, Does the VA anticipate work to be done above the ceiling?
A19: It is not anticipated but if there is any reason for above ceiling work due to means and methods it is there for awareness on procedure.
Q20: There is an electrical panel schedule attached to solicitation, does the VA anticipate Electrical work to be done?
A20: No there is no anticipated electrical scope for this project.
Q21: There is a Mechanical and plumbing system valve charts attached to the solicitation, Does the VA anticipate Mechanical and Plumbing work to be done?
A21: No there is no anticipated mechanical or plumbing scope for this project.
Q22: There is a hot work permit attached, does the VA anticipate hot work to be done?
A22: It is not anticipated but if there is any reason for above ceiling work due to means and methods it is there for awareness on procedure.
Q23: “Shaw, Veil Carpet Tile, TME” is this Shaw, Patcraft, S319V-Veiled?
A23: Product has been discontinued, replace with Structure 5T297 24” x 24”
Q24: Are transitions required for the new to existing finishes? Please specify.
A24: Use Schluter Systems edge protector and profile trim. Select appropriate transition product between flooring. Use “Satin Nickle Anodized Aluminum”, provide samples with shop drawings.
See attached document: Wage Determination.
See attached document: Site visit sign in sheet abate asbestos 2024.
See attached document: Ventilation in Room 2109.
See attached document: B12 Room 004.