About this file

This document contains questions and answers regarding a Multiple Award Task Order Contract (MATOC) solicitation. The solicitation is for construction services within Veterans Integrated Service Network 1 on behalf of the Department of Veterans Affairs Veterans Health Administration. Offerors must submit project experience information using the Project Information Sheet for Contractors and have references complete the Past Performance Questionnaire, with both updated to a new proposal due date of September 13, 2023. The document provides the requested updated exhibits and clarifies that the project sheets should only be included under the experience subfactor.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--VISN 1 Construction MATOC, newest first.
File Type Posted
WD MA20230001 Effective 12082023.pdf PDF
523-19-602 Rev 1 AD100 AS101 AS102.pdf PDF
Amendment 0017 RFIs.pdf PDF
523 19 602 Project Manual Part 1 A0016.pdf PDF
523 19 602 Drawings Pages 19 to 23 A0016.pdf PDF
Seed Project Original Site Visit Sign In Sheet August 9 2023 A0016.pdf PDF
523-19-602 Seed ICRA JP Police Office A0016.pdf PDF
SPECIAL MATOC REQUIREMENTS A0016.pdf PDF
Exhibit F Price Schedule Sheet A0016.pdf PDF
Exhibit E Base Offer Cost Breakdown A0016.xlsx XLSX spreadsheet
523 19 602 Drawings Pages 10 to 18 A0016.pdf PDF
523 19 602 Drawings Pages 1 to 9 A0016.pdf PDF
523 19 602 Project Manual Part 2 A0016.pdf PDF
36C24123R0073 0016.pdf PDF
Exhibit G VA PAY FORM w Monthly checklist A0016.pdf PDF
523-19-602 Seed Project Notice of Task Order Request for Proposal A0016.pdf PDF
Seed Project Parking Map A0016.PNG PNG image
Amendment 0016 RFIs.pdf PDF
36C24123R0073 0015.pdf PDF
36C24123R0073 0014.pdf PDF
MATOC RFIs Amendment 10.pdf PDF
523-19-602 Revised Specs.pdf PDF
SSJ Lock Systems.pdf PDF
SSJ DDC BMS.pdf PDF
Seed RFIs Amendment 10.pdf PDF
36C24123R0073 0008.pdf PDF
S06 36C24123R0073 0006.pdf PDF
36C24123R0073 0005.docx DOCX document
Amendment 5 Seed RFIs.pdf PDF
Updated Exhibit B Past Performance Questionnaire.pdf PDF
GENERAL CONTRACT REQUIREMENT SECTIONS 01000 01001 01300 01451 01700.pdf PDF
Seed Project RFIs.pdf PDF
36C24123R0073 0004.pdf PDF
WD MA20230001 Effective 08112023.pdf PDF
36C24123R0073 0004.docx DOCX document
36C24123R0073 0001.pdf PDF
36C24123R0073 Solicitation.pdf PDF
523 19 602 Drawings Pages 31 to 68.pdf PDF
523 19 602 Specifications.pdf PDF
Exhibit E Base Offer Cost Breakdown.xlsx XLSX spreadsheet
Exhibit D Proposal Inquiry Form.pdf PDF
523 19 602 Project Manual Part 2.pdf PDF
Exhibit G VA PAY FORM w Monthly checklist.pdf PDF
Exhibit C Safety Questionnaire.pdf PDF
Exhibit B Past Performance Questionnaire.pdf PDF
WD MA20230001 Effective 07212023.pdf PDF
523 19 602 Project Manual Part 1.pdf PDF
523 19 602 Drawings Pages 24 to 30.pdf PDF
523 19 602 Drawings Pages 19 to 23.pdf PDF
Exhibit A Project Information Sheet for Contractors.pdf PDF
Show all 50

Z2DA--VISN 1 Construction MATOC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATOC RFIs

1. I am working on compiling the Project Questionnaire Forms (Exhibit B) to be sent out to our references. On the form, it mentions a transmittal letter to be sent in with the questionnaire and that a sample is provided, however I don't see one included. Can you please confirm what this cover letter should entail for the questionnaires? Or is the first page of the questionnaire with the project information the actual "cover letter"?

Response: The first page of the questionnaire with the project information is the cover letter.

2. The instructions for both Subfactor 1 and Factor 2 refer to Exhibit 1, Project Information Sheet for Contractors. Should we include this exhibit in both factors? The specific instructions are shown below: Subfactor 1 Capability and Experience: "Prepare a Project Information Sheet for Contractors (Exhibit A) for a minimum of three (3) and a maximum of five (5) completed projects." Factor 2 Past Performance Information:

Offerors shall discuss, using the Project Information Sheet for Contractors (Exhibit A), their performance for a minimum of three (3) and a maximum of five (5) completed projects.

Response: Include in Subfactor 1 only since they will be in the same binder. The project information sheets will be used as part of the experience subfactor and past performance.

3. Please provide the new Exhibit B form for Past Performance Questionnaire that should have been issued with Amendment 4.

Response: There was a system error when posting Amendment 4. Exhibit B will be uploaded with this amendment under attachment name Updated Exhibit B Past Performance Questionnaire. The only change to the Exhibit B was the date was updated to the new proposal due date of 9/13/2023. The updated General Contract Requirements were also not posted right away with Amendment 4 and is now uploaded as GENERAL CONTRACT REQUIREMENT SECTIONS 01000 01001 01300 01451 01700 and the changes are highlighted in yellow.

4. Amendment 0004 posted on 08/15/23 lists an updated "Exhibit B Past Performance Questionnaire" as one of the provided document attachments. However, the file is not available from SAM.gov for download. The original Exhibit B is the only one available.

Please provide the updated PPQ form that offerors are to use for references.

Response: There was a system error when posting Amendment 4. Exhibit B will be uploaded with this amendment under attachment name Updated Exhibit B Past Performance Questionnaire. The only change to the Exhibit B was the date was updated to the new proposal due date of 9/13/2023. The updated General Contract Requirements were also not posted right away with Amendment 4 and is now uploaded as GENERAL CONTRACT REQUIREMENT SECTIONS 01000 01001 01300 01451 01700 and the changes are highlighted in yellow.