P09_PWS Update.docx
DOCX document 29 KB Posted
- Solicitation number
- 36C24123Q0511
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24123Q0511_1.docx | DOCX document | |
| S02_Attachment 1_PWS.pdf | ||
| S02_Attachment 3_Past Performance Worksheet.xlsx | XLSX spreadsheet | |
| S02_Attachment 2_Price Schedule.xlsx | XLSX spreadsheet | |
| 36C24123Q0511.docx | DOCX document | |
| Combined Synopsis-Solicitation_Medical Gas.pdf | ||
| S02_Attachment 4_VARR 852.219-75_Certificate of Compliance.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement Department of Veterans Affairs (VA) VA Connecticut Healthcare System Medical Gas System – Equipment Replacement
The West Haven VAMC is seeking a qualified vendor to remove and replace faulty and outdated equipment essential to the safe operation of the medical gas system, specifically a medical vacuum pump package and a medical air system. All work shall be completed within 6 Months of contract award unless other time frames are agreed upon prior to contract award.
Facility Information:
West Haven VAMC 950 Campbell Avenue West Haven, CT 06516-2770
Building 1, Room SG 182 – Medical Air System Building 2, G137 – Medical Vacuum System
Scope of Work:
This requirement is to perform the following services and necessary labor and materials for the removal, disposal and installation of all components of the medical air system with compressors and desiccant dryers and a medical vacuum pump package in West Haven, CT.
Submit a report of service detailing work performed and American Society of Sanitary Engineering (ASSE) all required certifications to ensure compliance with NFPA 99 2021 edition. All contracted work must be performed by a qualified vendor.
All work must be performed and completed on a schedule that will be approved in advance. Dates and times of repairs must be coordinated between the contractor and Government to minimize impact to facility operations. All work is expected to take place after facility normal operating hours, nights and or weekends.
Building 1, Room SG 182 – Medical Air System Requested parts or equivalent.
EMSE Triple Stack Mounted Medical Air Plant (Expandable) with scroll compressors and desiccant Dryers.
· Horsepower (each Compressor): 10 HP
· Capacity (system, one compressor in reserve);
· 69.6 SCFM @ psig
· Stack Mounted
· 200-gallon receiver
· 230, 460V/3Ph/60Hz or 380V/3Ph/50Hz
· Duplex deciccant dryer including:
· (2) twin dryer towers
· (2) pressure regulators
· Combination Dew point sensor & CO monitor
· Level 2 Control Panel, NFPA 99 compliant, with 5” touchscreen HMI
Building 2, G137 – Medical Vacuum System Requested parts or equivalent.
Duplex Medical Vacuum System, Dry Claw Vacuum Pump, stack mounted
· Horsepower 7.5 (each pump)
· Vacuum pump capacity: 65.0 SCFM @ 19’ Hg
· System capacity: 65.0 SCFM @ 19’Hg
· Receiver (ASME): 120 gallon / vertical tank
· High discharge temperature switches
· Intake vacuum filters
· Level 2 Control Panel: NFPA 99 compliant, 5” touchscreen HMI, including system status, service alert and alarm history Silences: 2” MPT
· AMICO Isolation Valve – Dual Gauge Ports – Locking – 3”
Interference to Normal Functions:
When the contractor’s work interferes with hospital functions, such as when work produces excessive noise, odors, dust, utility service interruptions, or other interferences with normal hospital operations that cannot be contained within the area of work, the contractor must schedule said work at other than normal hours and as directed by the VA designee at no additional charge to the Government.
Debris Removal:
The Contractor/Installer must be required to remove waste materials and debris daily from the campus. All waste material and debris must be removed off the site by the contractor and must be disposed of in accordance with applicable Local, State and VA and Federal regulations.
Property Damage:
The Contractor must take all necessary precautions to prevent damage to any government property. The Contractor must report any damages immediately and must assessed current replacement costs for property damaged by the contractor unless corrective action is taken. Any damaged material will be replaced in a timely manner or corrected by the Contractor with like materials at no extra cost to the government upon approval of the Contracting officer.
Additional Information:
The Department of Veterans Affairs is a smoke free environment and smoking is not permitted at the facility.
COVID-19 Precautions:
Face coverings are required to be worn while on station. See internal VA POC for precaution updates prior to arrival on station.
COVID-19 precautions can potentially change at any time; contractors must be required to follow all current COVID-19 regulations.
Contactor policies and procedures shall comply with all VA Privacy & Security, the Privacy Act and Health Insurance Portability and Accountability Act (HIPAA).
Records Management:
The following standard items relate to records generated in executing the contract and should be included in a typical procurement contract:
1. Citations to pertinent laws, codes and regulations such as 44 U.S.C chapters 21, 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.
2. Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
3. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.
4. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.
5. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.
6. The Government Agency owns the rights to all data/records produced as part of this contract.
7. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
8. Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].
9. No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.
10. Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.