36C24123Q0211 0001_2.docx

DOCX document 16 KB Posted

Attached to
H130--36C24123Q0211 Boiler Plant Predictive Maintenance
Solicitation number
36C24123Q0211
Issued by

View the file

Other files

File Type Posted
36C24123Q0211 0001_3.docx DOCX document
36C24123Q0211 0001.docx DOCX document
VA directive 1810(1)_D_2017-02-06.pdf PDF
WD 2015-4019 Revision 12-27-2022.pdf PDF
36C24123Q0211_1.docx DOCX document
Past Performance Worksheet.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBJECT*

36C24123Q0211 Boiler Plant Predictive Maintenance

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
01053-9764
SOLICITATION NUMBER*
36C24123Q0211
RESPONSE DATE/TIME/ZONE
01-23-2023 12:00PM EASTERN TIME, NEW YORK, USA
ARCHIVE
60 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N
SET-ASIDE
VSA
PRODUCT SERVICE CODE*
H130
NAICS CODE*
541330
CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs

VA CENTRAL WESTERN MASSACHUSETTS HCS

Acquisitions-90 421 North Main Street Leeds MA 01053-9764

POINT OF CONTACT*

Contracting Officer Craig Harris Craig.Harris@va.gov 603-314-1664

PLACE OF PERFORMANCE

ADDRESS
Manchester VA Medical Center

718 Smyth Rd

Manchester NH

POSTAL CODE
03104
COUNTRY
USA

ADDITIONAL INFORMATION

AGENCY’S URL

URL DESCRIPTION

AGENCY CONTACT’S EMAIL ADDRESS

EMAIL DESCRIPTION

Amendment to a Previous Combined Solicitation

Amendment to a Previous Combined Solicitation

DESCRIPTION

*= Required Field
Amendment to a Previous Combined Solicitation

Page 1 of

Amendment to a Previous Combined Solicitation

***AMENDMENT 00002 –36C24123Q0211 Boiler Plant Predictive Maintenance UPDATE*** Please confirm receipt of this update in your solicitation response

The purpose of this amendment is to provide answers to questions submitted at the site visit, as referenced below:

Question 1:

Can you provide a List of all equipment to be covered under the predictive maintenance contract?

Answer:

1. Duplex Fuel Skid (2 pumps/2 motors) Motor and pump split shaft with rubber coupler.

2. Oil Filtration System (1 pump/1 motor) Motor and pump split shaft with rubber coupler and has a mechanical seal.

3. Feedwater Pumps (3 pumps/3 motors) 7 stage cartridge and has mechanical seal.

4. Condensate Pumps (2 pumps/2 motors) 2 stage cartridge.

5. Sump Pumps (2 pumps/2 motors) Motor and pump split shaft with rubber coupler.

6. Condensate Return Pumps (2 pumps/2 motors) have mechanical seals

7. Boiler Burner Combustion Fans (3 motors/3 fans)

Question 2:

Is there a baseline reading for the current settings or would this contract create a new program to create a new baseline?

Answer 2:

We need to create a new program and new baseline.