36C10D25R0009 0002.docx
DOCX document 27 KB Posted
- Solicitation number
- 36C10D25R0009
- Issued by
-
Department of Veterans Affairs
About this file
This document is an amendment to a federal solicitation for replacing Air Handling Units 1 & 2 at the Montgomery VA Regional Office. The solicitation (36C10D25R0009) involves removing and replacing existing air handling units with new units, with critical details including an extended proposal due date of June 26, 2025 at 4:00 PM Central Time. Key modifications include publishing Request for Information (RFI) questions through June 10, 2025, and releasing the sign-in sheet from a June 4, 2025 site walk-through.
The amendment addresses several technical considerations through a Q&A format, including confirmation that no coated coils are required, new louvers will be installed, and no contingency dollars will be provided for potential repair or temporary cooling. The contracting officer from the Department of Veterans Affairs Veterans Benefits Administration Acquisition Directorate has confirmed that temporary cooling requirements emerged due to a return-to-office mandate, which was not initially factored into the original design when maximum telework was anticipated. The project will be completed while maintaining 100% administrative operational status at the Montgomery Regional Office.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| June 4 2025 Air Handler Replacement Site Visit Sign In Sheets.pdf | ||
| 36C10D25R0009 0001.docx | DOCX document | |
| 36C10D25R0009_2.docx | DOCX document | |
| AE VB3145_100 Construction_Specifications.pdf | ||
| P07 Al20250093 03.14.2025 SAM.pdf | ||
| PPQ VBA.doc | DOC document | |
| from AE 00 Combined 100 percent.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
VA
VB3145
00101 Department of Veterans Affairs Veterans Benefits Administration Acquisition Directorate 1800 G Street NW Washington DC 20006 00101 Department of Veterans Affairs Veterans Benefits Administration Acquisition Directorate 1800 G Street NW Washington DC 20006
36C10D25R0009
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 06-26-2025 4:00pm CDT See CONTINUATION Page X The intention of this amendment is to:
1-Publish RFI questions through 6.10.2025 2-Publish sign in sheet from June 4, 2025 walk-through.
3-EXTEND proposal due date/time:
PROPOSALS are now due June 26, 2025 at 4:00pm Central Time.
NO further RFI questions will be accepted.
All other terms and conditions remain the same
Jacalyn Hainey Contracting Officer
CONTINUATION PAGE
Request for Information -Solicitation #36C10D25R0009 VB3145 - Replace Air Handling Units 1 & 2 at the Montgomery RO
Question (1)-
· Who is the contact for the basis of design AHU?
Answer: SPUR
Question (2)-
· How is the building going to be conditioned during the removal and replacement of the AHUs? (With the specified requirement to only use the east side louver as the access point, the east side unit has to be removed and has to stay out until the west side unit is remove and then replaced. This removes all cooling for the building).
Answer: See answer to question 3.
Question (3)-
· There is no provision for temporary cooling in the specification.
Answer: The temporary cooling aspect is being forced to be added after design was finalized due to the governments return to office mandate was implemented. With max telework an option during the design phase, there was not a need for temporary cooling. This all changed when the new administration took office and caused us the customer to go back and look at how this project could be completed while remaining 100% administratively operational.
Question (4)-
· Are coated coils required in this environment?
Answer: No, that is not part of the design request from the VA. However, if it is something that the manufacturer provides as part of the manufacturing process and is already included in unit pricing, the VA will evaluate during the submittal process.
Question (5)-
· Can we reuse the louver?
Answer: No there is a provision in the design to go back with new louver/s.
Question (6)-
· For the Contracting Officer. Would it be a better solution for the Government if there was a contingency dollar amount in the contract, for some amount, to cover any cost that might occur in either the repair of the 2 return fans and\or the possible need for temporary cooling in the building?
Answer: No contingency.
Question (7)-
· Is there a chance to get a 2-week extension from the time we get all RFI’s answered?
Answer: Yes, proposal due date will be extended.
Proposal due date will now be 6/26/2025 by 4pm CST.
See attached document: June 4 2025 Air Handler Replacement Site Visit Sign In Sheets.
A.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| GRAND TOTAL |
| __________________ |
A.2 DELIVERY SCHEDULE
| ITEM NUMBER |
| SHIPPING INFORMATION |
| QUANTITY |
| DELIVERY DATE |
Montgomery, AL VBA Regional Office Air Handler Replacement