Applicable Doc. 12 - Monthly Status Report Template.pdf
PDF 106 KB Posted
- Attached to
- DF01--IAM Recompete Task Order (VA-24-00001896)
- Solicitation number
- 36C10B24Q0109
About this file
This monthly status report template outlines progress on a Department of Veterans Affairs project to improve veteran relationship management systems. Key accomplishments this period included tasks to enhance specified capabilities. The report schedules deliverables and milestones, and tracks budget and spending across tasks. Upcoming work focuses on additional milestones and task completion. Financial data provides budget and invoicing information by task.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Monthly Status Report
Department of Veterans Affairs
Major Initiative 6/Veterans Relationship Management
IAM Access Services (AcS) Project
Order ID:
Reporting Period:
Submitted to:
Department of Veterans Affairs Attn: Mr. Jerry Wharton - VA PM
Submitted by:
Date Page 2 Status Report
1. Agenda
Monthly status reports are organized according to the following agenda:
• Summary
• Project Status
• Schedule (deliverables/milestones)
• Scope
• Financial Status
• Upcoming Work and Milestones
2. Project Purpose
The goal of this project is to XXXX
3. Summary
During this performance period, the Vendor Team key accomplishments include the following:
• Task 1 – xxxx
• Key Accomplishment
• Key Accomplishment
• Task 2 – xxxx
• Key Accomplishment
• Key Accomplishment
• Task 3 – xxxx
• Key Accomplishment
• Key Accomplishment
4. Project Status
4.1. Schedule (deliverables/milestones)
Table 1 shows the planned start and end dates, the estimated percent complete, and the change in percent complete from the previous report for each task.
Table 1 – Status of Major Tasks
Description Scheduled
Start
Scheduled
Finish
Estimated
Complete
Previous
Complete
Comment
Major Task 1
Date Page 3 Status Report
Description Scheduled
Start
Scheduled
Finish
Estimated
Complete
Previous
Complete
Comment
Major Task 2
Major Task 3
4.2. Scope
In accordance with the Statement of Work, the LS3 Team will produce deliverables according to the schedule. Table 2 provides information regarding the delivery status for each deliverable.
Table 2 – Status of Deliverables
Item
No.
Deliverables Estimated
Initial
Delivery
Estimated Final
Approval
Status
1 Deliverable 1
2 Deliverable 2
3 Deliverable 3
5. Financial Status
Table 3 provides a summary of the project costs by task consumed this month, total consumed, total planned, percent spent, and remaining funds available.
Table 3 – Cost By Task Summary
Task Amount
Invoiced in
Month
Total Amount
Invoiced
Planned
Invoice
Percent
Spent
Remaining
Task 1 $0.00 $0.00 $0.00 0% $0.00
Task 2 $0.00 $0.00 $0.00 0% $0.00
Task 3 $0.00 $0.00 $0.00 0% $0.00
Travel $0.00 $0.00 $0.00 0% $0.00
Total $0.00 $0.00 $0.00 0% $0.00
Date Page 4 Status Report
6. Upcoming Work and Milestones
The following section summarizes the essential work and specific milestones projected for the next reporting period which include:
• Upcoming Major Task
• Upcoming Milestone
Date Page 5 Status Report
If there are any questions concerning this status report, please do not hesitate to call me at (xxx) xxx-xxx or e-mail e-mail address.
Submitted by: xxx
Name, Program Manager
Date
File details come from the government source that posted it. Updated .