About this file

This document contains a schedule of line items and related information for a federal contract opportunity to acquire medical imaging equipment and install turnkey services at various Veteran's Affairs (VA) healthcare facilities across multiple VISN networks.

The key details are:

  • This opportunity is for the purchase and turnkey installation of various imaging modalities including radiographic, fluoroscopic, SPECT/CT, and PET/CT systems at 11 different VA facilities across 7 VISN networks.
  • The solicitation number is 36A79724Q0012 and it is being issued by the Department of Veterans Affairs National Acquisition Center.
  • Vendors must provide detailed technical specifications, installation plans, and pricing for the requested equipment and services.
  • Site visits are scheduled at each facility in July and August 2024 to allow vendors to assess existing conditions.
  • Responses are due by a specific deadline, with an award anticipated in May 2024.
  • The contract will include both the equipment purchase and complete turnkey installation services.

View the file

Other files

File Type Posted
36A79724Q0012 0001.docx DOCX document
648B43000 Drawings.zip ZIP file
515B40021 - 678B42018.zip ZIP file
Amendment 0001 - Continuation Page.pdf PDF
636B43019 Drawings.zip ZIP file
692B43001 Drawings.zip ZIP file
678B42017.zip ZIP file
515B40021 - 636B43019.zip ZIP file
VA Directive 6550 - New Appendix A - published Jun. 2023.docx DOCX document
MAY 2024 Extended Install and Turnkey Consolidation Schedule.pdf PDF
636B43019 - 678B42017.zip ZIP file
MAY 2024 TKY Consolidation - Schedule of Line Items - Updated 7-10-24.xlsx XLSX spreadsheet
678B42017 - 692B43001.zip ZIP file
Memorandum for Training.pdf PDF
636B43019.zip ZIP file
Vendor Workup Spreadsheet - 36A79724Q00012.xlsx XLSX spreadsheet
NAC Turnkey Rubric - 4Oct2023.pdf PDF
36A79724Q0012_1.docx DOCX document
Vendor Folders.zip ZIP file
MAY 2024 Extended Install and Turnkey Consolidation - RFO.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Line Items

HTME VISNStationEquip POTKY POEquipment TypeQTYSite Visit POCSite Visit DateSite Visit Time
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021515B40023XR RAD1timothy.meneguzzo@va.gov8/1/2410am EST
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026515B40025XR RF1timothy.meneguzzo@va.gov8/2/2410am EST
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40009580B40011XR RF1Yaseen.Golzarian@va.gov8/5/2410am CST
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007600B40009XR RAD1Marina.McGruder@va.gov Calvin.Evans@va.gov7/29/2024 & 8/1/202411am - 12pm PST
VISN 23: VA Midwest Health Care Network636 DES MOINES, IA636B43019636B43025NM PET CT1Ronald.TrumpJr@va.gov7/31/249am - 11am CST
VISN 20: VA Northwest Network648 PORTLAND, OR648B43000648B43001XR RF1Kelly.wachholz@va.gov8/7/242pm - 4pm PST
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40003655B40006NM SPECT CT1james.sabin@va.gov8/6/2410am EST
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40007655B40008XR CT1james.sabin@va.gov8/7/2410am EST
VISN 20: VA Northwest Network663 SEATTLE, WA663B43005663B43006XR CT1johnny.huang@va.gov justin.collins2@va.gov8/8/248:30am - 10am PST
VISN 20: VA Northwest Network668 SPOKANE, WA668B43002668B43003XR RAD1richard.poor@va.gov justin.collins2@va.gov7/29/249am - 10am PST
VISN 8: VA Sunshine Healthcare Network673 TAMPA, FL673B40031673B40035XR CT1Angelina.Chiaracane@va.gov8/1/241pm - 3pm EST
VISN 8: VA Sunshine Healthcare Network673 TAMPA, FL673B40032673B40036RT LINAC1Vinh.bui@va.gov8/1/249am EST
VISN 22: VA Desert Pacific Healthcare Network678 TUCSON, AZ678B42017678B42023XR RAD1Jennifer.Lewis8@va.gov7/29/248:30am - 12pm PST
VISN 22: VA Desert Pacific Healthcare Network678 TUCSON, AZ678B42018678B42021XR RAD1Jennifer.Lewis8@va.gov7/29/248:30am - 12pm PST
VISN 20: VA Northwest Network692 WHITE CITY, OR692B43001692B43002XR CT1christopher.banco@va.gov Christopher.Ortiz2@va.gov justin.collins2@va.gov7/30/2410am - 12pm PST

Q&A

VISNStationEquipment Requisition NumberTurnkey Requisition NumberEquipment QuestionsTurnkey QuestionsGOVT Equipment ResponseGOVT Turnkey Response
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Are there as-builts available - Structural, Architectural, Electrical, Mechanical? Are there any finishes proposed for change/upgrade outside of what is required to install new equipment? Any counters/Cabinets proposed for change/upgrade? Is there a UPS planned for this room?As-Bult drawings are available (contractor shall be responcible for field verifying existing conditions); the station does have standard finishes; there was discussion during the site walk of changing the tech area; UPS for acquistion and processing workstations only
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021515B40023Are architect drawings available for our use?Yes, there are architect drawings available.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Line 30 a. - Quantity of additional wireless detectors. - Are you asking for 4 wireless detectors total? Meaning, two beyond the table and wall stand? If yes, please confirm the sizes for the two additional detectors.
Line 32 c. - Maximum first wireless detector weight. - Please confirm this is for the wall stand detector in line 22. If yes, please change the specification from 8 lbs. to 8.4 lbs.Flooring:
1.Existing flooring to be replaced in the Exam and Control rooms?
2.If so, do you want heat welded seamless sheet vinyl flooring , VCT, or LVT?
3.4” or 6” rubber or vinyl base or flash cove

Walls:

1. Paint all existing walls or only where walls were patched?

Ceilings:

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork:

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting:

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power:

1.If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?
2.If full system UPS is requested where will this system be located and where will the source feeder for the UPS system fed from?

HVAC:

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?

Other:

1.If a patient lift exists will the VA remove existing patient lift, store, and reinstall the lift?Line 30a- Total of 3. Two 14x17 & 17x17. So one beyond table and wallstand
Line 32c- change to 8.4 lbs.Flooring:

1. Yes

2.Heat welded Seam Sheet
3.4” vinyl base

Walls:

1. Paint all existing walls Ceilings:

1. No Millwork:

1. New counter and cabinets required for radiology tech area Lighting:

1.No
2.No

Power:

1.PP-P 480 volt, 400A; basement (B137)
2.N/A

HVAC:

1.Not needed
2.No

Other:

1.Contractor will have to remove, store, reinstall and certify. Track is "H" track.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Can the facility provide as-built MEP info for the affected space for the purpose of equipment drawing generation, and Extended Installation price development?Yes, MEP as-built drawings are available.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Please define the level of work desired for wall, floor, and ceiling finishes (complete replacement, or patch and repair?) If no response, Philips will assume patch & repair onlyNew flooring; path and repair walls and ceiling finishes
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Please define the level of work desired for cabinets, counters and other millwork (complete replacement, repairs/updates to existing, or leave existing as-is?) If no response, Philips will assume existing to remain as-isComplete replacement with new, in kind
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Are there any VA update standards that will need to be considered in the Extended Installation Scope of Work? (ie: LED lighting for green energy, ceiling grid standards, etc….) If no response, Philips will assume re-use of existing lighting and ceiling grid unless work in the ceiling requires replacementReuse of existing
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Is the site located in a facility owned by the VA, or is the space in a facility being leased by the VA?VA owned
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40021Is there any CAD files or site drawings to be shared?Yes, there are CAD Drawings available.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026515B40025Are architect drawings available for our use?Yes, there are architect drawings available.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026Line 1c - Additional wireless detectors. Please confirm whether we should be quoting two wireless detectors. Please confirm you want a second 14x17 wireless detector for a total of three detectors. One fixed 17x17 for the table and two 14x17 wireless.

Line 2m - Minimum pulse rate. This spec is inconsistent with industry standards. Please change minimum to one frame per second or maximum to 15.

Line 2p - Minimum SID range. Please remove minimum for the SID range.

Line 3i - Imaging tower vertical movement. Please change to footswitch and tower or joystick controls.

Line 3s - Bar code reader. Please remove Bar code reader.

Line 6a - Minimum control room monitor size. Please change to 23 inches.

Line 6b - Minimum in room monitor size. Please change to 23 inches.Flooring:
1.Existing flooring to be replaced in the Exam and Control rooms?
2.If so, do you want heat welded seamless sheet vinyl flooring , VCT, or LVT?
3.4” or 6” rubber or vinyl base or flash cove

Walls:

1. Paint all existing walls or only where walls were patched?

Ceilings:

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork:

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting:

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power:

1.If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?
2.If full system UPS is requested where will this system be located and where will the source feeder for the UPS system fed from?

HVAC:

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?

Other:

1. If a patient lift exists will the VA remove existing patient lift, store, and reinstall the lift? Line 1c-Correct: CONFIRMED:: a second 14x17 wireless detector for a total of three detectors. One fixed 17x17 for the table and two 14x17 wireless.

Line 2m- Technical specification removed Line2p- Technical specification removed Line 3i- Tech Spec changed to footswitch and tower controls.

Line3s- Technical specification remove Line 6a- Change to 23”.

Line 6b- Change to 23”.Flooring:
1.No
2.N/A
3.N/A

Walls:

1. Paint all existing walls, LEVEL 4 finish Ceilings:

1. No Millwork:

1. No Lighting:

1.Yes
2.No

Power:

1 Unknown at this time

2. N/A, no full system UPS needed

HVAC:

1.Not needed
2.No

Other:

1.Contractor will have to remove, store, reinstall and certify. Track is "H" track.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026There was no matrix attached in the consolidation. Will there be a matrix sent?Matrix is reattached for use.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026Can the facility provide as-built MEP info for the affected space for the purpose of equipment drawing generation, and Extended Installation price development?Yes, MEP as-built drawings are available.
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026Please define the level of work desired for wall, floor, and ceiling finishes (complete replacement, or patch and repair?) If no response, Philips will assume patch & repair onlyNew flooring; path and repair walls and ceiling finishes
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026Please define the level of work desired for cabinets, counters and other millwork (complete replacement, repairs/updates to existing, or leave existing as-is?) If no response, Philips will assume existing to remain as-isComplete replacement with new, in kind
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026Are there any VA update standards that will need to be considered in the Extended Installation Scope of Work? (ie: LED lighting for green energy, ceiling grid standards, etc….) If no response, Philips will assume re-use of existing lighting and ceiling grid unless work in the ceiling requires replacementReuse of existing
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026Is the site located in a facility owned by the VA, or is the space in a facility being leased by the VA?Leased by the VA
VISN 10: VA Healthcare System of Ohio515 BATTLE CREEK, MI515B40026Is there any CAD files or site drawings to be shared?Yes, there are CAD Drawings available.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40009Line 67 3v Please change UPS requirements to minimum of 10 minutes for a safe shut downLarge enough for a safe shutdown. UPS – maintains full functionality of the system for a minimum of 60 minutes during a power outage was moved to added value
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40009Line 66 3u Please remove or move to added value this specification.This requirement was moved to added value.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40009Line 91 5d. Please remove Touchscreen acquisition workstation monitor to allow for fair competitionThis is a minimum requirement and to remain as is.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40009Line 22, 1a, 23 1b For the request of wireless detector in wall bucky, is 17 x 17 fixed acceptable?This is a minimum requirement and 17x17 is acceptable.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40009580B40011Q1 - Is the site willing to accept a Remote RF Room solution to offer expanded functionality for Fluoro and Radiographic flexibility? Q2 - 2.q. Respectfully request change for X-ray Tubes to 800kHU for Fluoro and 600kHU for OTC. Q3 - 2.v. UPS for 60 minutes of use during power outage. Not seen this before for RF purposes but more for CT and MR. Respectfully request adding a UPS to safely shut the RF system electronics down during a power outage before cutting over to the site back-up power supply.Q1: Yes. Will be put under added value.

Q2: Unit specification for xray tube is 800kHu and will remain as is.

Q3: Minimum requirement to maintain full functionality for 60 minutes during power outage and to remain as is.

VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B400091b. Please change Table detector to 14X17Table detector changed to 14x17 and 17x17 was moved to added value.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40011Please provide UPS requirements.Maintains full functionality of the system and large enough for a safe shutdown.
VISN 16: South Central VA Health Care Network580 HOUSTON, TX580B40011What is the approved pathway for ICRA exhaust to the exterior?The ICRA will be completed with the successful bidder in coordination with the Infection Prevention and Projects teams after award. The pathway for exhaust may be impacted by the specific work to be performed and/or quality of exhaust air.
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Will the flooring in room be newly replaced?

What is the existing Incoming Line Voltage to room?

Will there be additional Storage Area for Construction Equipment and Supplies?

Will there be additional parking space for construction vehicles?

Is the room lighting to be upgraded?

Any counters/Cabinets proposed for change/upgrade? Yes flooring to be replaced Existing Incoming Line Voltage is 480V No Additional Storage Area No Additional Parking Use General Parking Area Yes room lighting to be upgraded Yes Counters and Cabinets Proposed for change

VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Is the requirement for a total of 3 Detectors? Or 4 detectors? If so, what is the size requirement for the 3rd and 4th detector?3 detectors. Size requirement for the 3rd detector is 10x12.
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B400071c. Please confirm the quantity and size of desired detectors. If the vendor offer includes a wireless 17x17 wall detector, would you still like a 17X17 in the table and an additional 10X12 OR would you prefer 17X17 wireless wall, 14X17 wireless table, and an additional wireless 10X12?
5a. Is stitching preferred at the wall, table or both?RFI Questions – Room Finishes

Flooring:

1.Does the Existing flooring need to be replaced in the exam room and control room?
2.Heat welded seamless sheet vinyl or LVT?
3.4” or 6” rubber base or flash cove

Ceilings

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power

1. If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?

HVAC

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?3 detectors: 17x17 wall, 17x17 table, and 10x12 additional wireless.
Stitching is preferred at both wall and table.RFI Questions – Room Finishes

Flooring:

1. Does the Existing flooring need to be replaced in the exam room and control room? Yes

2. Heat welded seamless sheet vinyl or LVT? Vinyl welded seams

3. 4” or 6” rubber base or flash cove Ceilings? 6” cove based

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced? Yes all the ceiling grid and/or panels replaced Millwork

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)? Yes all millwork replaced Lighting

1. Do you want existing lighting to be replaced with new LED lighting? Yes

2. Do you need any additional lighting than what currently exists? No Power

1. If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.? yes, upon request

HVAC

1. Can you please provide a recent T&B (test and balance) report? No, recent (this year) T&B will be provided, if more recent is needed vendor should produce

2. If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning? Yes, HVAC may need replacement due to age pending install start date.

VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Is there a trade-in for this consolidation line? Not indicated on bottom of page 6 of the tech specs released with the consolidation.No trade in at this time
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Related to the compliance matrix Section 2 Line J [Minimum tilt of imaging surface (deg)] - What imaging surface are they referring to for tiling range? (X-ray tables do not tilt).Tilting refers to upright bucky
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Related to the compliance matrix Section 2 Line N (Tilting range for the wallstand) - Is this a duplicate questino from Line J?Yes
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Related to the compliance matrix Section 3 Line D (Grid attachments) - Are only physical grids being requested, or a virtual grid which is cleared for all body parts, or both physical and virtual?Both physical and virtual
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Turnkey question, does the VA require the existing main entrance of the suite to be replaced, repaired, or left as-is?Existing Main Door to Remain as-is
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Turnkey question, does the VA require removal and/or replacement of the existing cabinetry in the suite? If-so, please specify what is to be removed and/or replaced.Yes demo of existing counter desk / uppers at head end of table and base cabinet
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Turnkey question, does the VA require replacement of existing ceiling and cove lighting, or can existing lighting be re-used?Existing ceiling to be replaced

New electrical as required by new equipment

VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Turnkey question, does the VA require existing floor covering to be replaced, or patch and repaired where disturbed by the work? If full replacement, please specify the areas to be replaced. (exam room only, or control room area to be included?)Demo and replace exam room and control room floors
VISN 22: VA Desert Pacific Healthcare Network600 LONG BEACH, CA600B40007Line 4 XR Rad Long Beach: Turnkey question, is a new return air system to be provided? (Existing return is in control room area).Existing HVAC serving the room to be reused. Including adding one (1) new return grill in rad room ceiling
VISN 23: VA Midwest Health Care Network636 DES MOINES, IA636B43019636B43025Should the proposed PET/CT Scanner continuous bed motion whole body PET scanning?Continuous bed motion is desired but not required.
VISN 23: VA Midwest Health Care Network636 DES MOINES, IA636B43019636B43025Should the proposed PET/CT scanner dynamic PET acquisition capability and software?This is not a requirement but the vendor can propose it as an alternate.
VISN 23: VA Midwest Health Care Network636 DES MOINES, IA636B43019636B430251a. Please change minimum number of slices to 128

1c. Please clarify is minimum detector width (20mm) is for CT or PET Detector 1e. Table height range – Do you want range of table height or height from floor to lowest position (ie; 20in minimum distance from table to floor) 1h. Minimum number of crystals – Please update to minimum 14,000 crystals.

1j. Please change time of flight resolution to 385 1k. Please clarify in this requirement if you’re looking for the best spatial resolution using TOF?

1l. Please change time of flight coincidence window to 5.25

2e. How many concurrent user licenses are needed for reading, reviewing, and advanced post processing (cardiac, neuro, and oncology)?1.What is the path for the HEPA filter exhaust duct from the construction area to the exterior of the building?
2.Provide HVAC as-builts for the AC unit(s) serving the PET CT suite.
3.Provide structural slab detail for the Procedure room, as well as confirm if it is slab on grade or an occupied space below?
4.Should vendors include Vibration Testing as part of the scope of work/extended install or will the customer do that separately? If additional work from vibration testing is required, will a Modification be allowed?

Flooring:

1.Existing flooring replaced?
2.Exam and Control room or just Exam room? If so, do you want?
3.Heat welded seamless sheet vinyl or LVT?
4.4” or 6” rubber base or flash cove

Ceilings

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power

1. If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?

HVAC

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?1a. Changed.

1c. PET detector should be a minimum of 20mm.

1e. The distance from the floor to lowest table position should be minimum 20in.

1h. Changed.

1j. Changed to 245.

1k. The PET/CT system must use TOF.

1l. Changed.

2e. 2 concurrent licenses are needed.

1. ICRA negative air exhaust will need to be routed outside through the nearby wall. The wall penetration that is created during this will need to be patched when work is complete.

2. See attached as-builts.

3. See attached drawings.

4. Vibration testing is not expected. If it is determined to be required, a modification will be allowed.

Flooring:

1. Replace flooring in procedure, equipment, and control room.

2. See question 1.

3. Welded Seam Sheet Flooring (Heat Welded with Rod)

4. 4"

Ceiling:

1. Ceiling not required to be replaced but if damaged during construction contractor is responsible for replacement.

Millwork:

1. No

Lighting:

1. Yes

2. No

Power:

1. Estimated to be 150 feet

HVAC

1. VA does not have a recetn T&B avaliable. The HVAC system does not have room for expansion. We can provide the current CFM values for the rooms.

2. The NAC turnkey rubric does not allow for the replacement of HVAC units outside of the equipment and control room.

VISN 23: VA Midwest Health Care Network636 DES MOINES, IA636B43019636B43025What is the approved pathway for ICRA exhaust to the exterior?ICRA negative air exhaust will need to be routed outside through the nearby wall. The wall penetration that is created during this will need to be patched when work is complete.
VISN 23: VA Midwest Health Care Network636 DES MOINES, IA636B43019636B43025Requesting HVAC as-builts for the system serving the PET/CTSee attached as-builts. Contractor will need to block supply air to construction area during work.
VISN 20: VA Northwest Network648 PORTLAND, OR648B430002.h UPS for workstation. It was understood during the walkthrough that the system would likely be connected to a whole floor UPS that is being installed, or a Full System UPS would be required. Please verify which solution is required. Either way it sounds like a Workstation UPS is not required.UPS workstation only
VISN 20: VA Northwest Network648 PORTLAND, OR648B43000Please confirm that system should be configured for cardiology procedures, despite indications in the specifications for an IR SuiteYes this will support cardiology procedures as well.
VISN 20: VA Northwest Network648 PORTLAND, OR648B430001.j.) - Minimum number of workstation inputs = 8. Need clarification regarding this question. Is the requirement here for 8 Video Inputs to the primary Exam Room Large Display? Or is it referring to 8 Workstation monitors located in the Control Room? Or is it referring to something else?8 Workstations monitors in the control room.
VISN 20: VA Northwest Network648 PORTLAND, OR648B430003.a.) – Software Requirements, “Repeat rate…ability to track repeat/retake data to include such items as technologist (required unique identifier), reason for repeat, patient dose, exam type, etc. The data should be exportable to Excel or other database for tracking, trending, and combining with data from other imaging sources within the facility.” Needs clarification. Is the request here for the above information to be part of the DICOM Structured Report? Is the goal for the department to be able to track the number of times during a specific cases that images had to be re-taken and what the impact to patient dose is?Yes we do want it as a Dicom Structured report. Yes that is the goal.
VISN 20: VA Northwest Network648 PORTLAND, OR648B430003.g.) – “Software to aid with needle positioning using an ultrasound device”. Needs clarifications - does an Ultrasound machine also need to be quoted as part of this obligation? Or do they just need the Biplane configured with the Needle guidance Software and the ability to integrate the Ultrasound image to the Large Display as a selectable video source input?No we do not need an US as part of this proposal. Yes we do need Needle Guidance software and ability to integrate with US images to the large display as a selectable source.
VISN 20: VA Northwest Network648 PORTLAND, OR648B43000Drawings:
1.Can you provide Autocad as built drawings of the space to include MEP drawings ?
2.Can you provide vendor finals of the existing system in the room.

Flooring:

3.Existing flooring to be replaced in the Exam and Control rooms?
4.If so, do you want heat welded seamless sheet vinyl flooring , VCT, or LVT?
5.4” or 6” rubber or vinyl base or flash cove

Walls:

1. Paint all existing walls or only where walls were patched?

Ceilings:

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork:

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting:

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power:

1.If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?
2.If full system UPS is requested where will this system be located and where will the source feeder for the UPS system fed from?

HVAC:

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?

Other:

1. If patient exists will the VA remove existing patient lift, store, and reinstall the lift? Drawings:

1. Provided to NAC HTME

2. Porvided to NAC HTME Flooring:

3. Flooring to be replaced

4. Resilient sheet floor that is heat welded. In recent projects, MedinPure sheet flooring was installed.

Walls:

1. Paint all walls Ceilings:

1. Replace all tiles Millwork:

1. Yes, all millwork and countertops should be replaced Lighting:

1. Yes lighting should be upgraded to LED

2. No additional lighting is needed Power:

1. 2D-119 Angio is fed by 225A 3-Phase 480V SWBD 2SDE-M-3 in electrical room 2D-123. It’s approx. 50’ from the panel in 2D-123 electrical room to the disconnect in 2D-119 Angio room.

2. Full system UPS is not being requested

HVAC:

1. Provided to NAC HTME

2. No currect AC handler and HVAC are functioning well Other:

1. Yes, if there is a lift in the room, we can reinstall the lift motor, but the lift rails will need to remain in place unless the entire ceiling is being redone, which in that case the VA would be responsible for replacing the ceiling lift structure.

VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B400036.n. Is calcium scoring a requirement or a recommendation?No.
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40003Line 65 – Continuous Gating. Please clarify what “Continuous Gating” means.

Line 36 – Is diagnostic CT truly a requirement? Or, are you wanting a non-diagnostic CT?

Line 43 – Please remove to allow for full and fair competition as only one vendor offers this.

Line 66 – Enhance Whole Body Package. Please clarify what this is. Seems to be the exact name of a package offered only by Siemens.

Line 99 – Please remove as the required 8 slice CT cannot perform CaSc.

Line 101 – Does this refer to the ability to apply CTAC to both stress and rest from a single CT?Flooring:
1.Existing flooring to be replaced in the Exam and Control rooms?
2.If so, do you want heat welded seamless sheet vinyl flooring , VCT, or LVT?
3.4” or 6” rubber or vinyl base or flash cove

Walls:

1. Paint all existing walls or only where walls were patched?

Ceilings:

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork:

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting:

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power:

1.If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?
2.If full system UPS is requested where will this system be located and where will the source feeder for the UPS system fed from?

HVAC:

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?

Other:

1. If a patient lift exists will the VA remove existing patient lift, store, and reinstall the lift? Line 65 - Yes. Continuous gaiting means turning the camera on and off.

Line 36 - Non-Diagnostic.

Line 43 - This is required to meet requirements for daily, weekly, monthly, and quarterly QC requirements for NRC and NHPP.

Line 66 - This is a clinical requirement that facilitates fusion of the 2 modalities together. Also reduces artifacts due to metal implants.

Line 99 - This can be removed.

Line 101 - Yes. Flooring

1. Flooring will be replaced.

2. Welded sheet vinyl

3. 6" Vinyl Wall

1. Paint all existing walls and patch.

Ceiling

1. Yes. Ceiling lift will need to be relocated.

Millwork

1. No.

2. No, existing lighting may need to be relocated.

Power

1. Equipment will be fed from 1-B255 in the basement switchgear room located floors below equipment approximately 15 feet vertically and another 25 feet horizontal.

2. Yes, waiting on location information UPS will be fed from same source location as equipment.

HVAC

1. we do not have a recent T&B report to provide.

2. Current mini-split unit is aged, please anticipate replacing unit.

VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40006For the control room, can we move the wall between the control room and SPECT/CT room back 2 ft to allow for all the existing equipment to fit into the exam room.Yes.
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40007Please provide additional trade-in information: Generator Size:

Tube Usage: (Specify Numbers for MAS, Rotation, Slices or Scan Seconds) Tube Manufacturer and Model:

Tube Size (Mhu):

Date of Last Tube Replacement:

Average Patient Flow Per Day:

Gantry Usage:

(Specify Numbers for MAS, Rotation, Slices or Scan Seconds) Generator Size: 80 KW Tube Usage: (Specify Numbers for MAS, Rotation, Slices or Scan Seconds)

MAS: 18,088,126

Scan seconds: 93,337 Tube Manufacturer and Model: GE LB Perfomix model #217686BC5 Tube Size (Mhu): 6.3 MHU Date of Last Tube Replacement: 17 nov 2023 Average Patient Flow Per Day: Avg. 20-25 patients per day Gantry Usage:

(Specify Numbers for MAS, Rotation, Slices or Scan Seconds)

MAS:207,383,772

Scan seconds: 949,817 Rotations: 1,997,599

VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40007Is CT Fluoroscopy required? The statements mention the users being able to access table, gantry, and CTF from inside control room (Part B, Section 2, item a & b) but I do not see the line item for CTF itself and if it needs to be ceiling or floor mounted. In the past, CTF had its own item listing.No CT Fluoroscopy is required.
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40007Is Cardiac CTA required? Mentioned the need for triggered studies using ROI for CTA and CCTA in Part B, Section 2, item g but not requested in its own line item.Cardiac CTA is not required at this time.
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40007Lung CAD. Which post processing solution will be employed?RiverRain V5.8.0
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40007Are there as-builts available - Structural, Architectural, Electrical, Mechanical? Are there any finishes proposed for change/upgrade outside of what is required to install new equipment? Any counters/Cabinets proposed for change/upgrade? Is there a UPS planned for this room?There are as-builts available. No finish for changes and upgrades. No counter or cabinets proposed. Yes, UPS is planned for this room.
VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B400072a.The CT scanner shall provide the ability for the user to independently operate the table, gantry, and CT fluoroscopy mode from the control room. Please confirm if you need fluoro biopsy capabilities on this scanner..
2i.UPS – maintains full functionality of the system for a minimum of 30 minutes during a power outage. Please clarify if you are looking for a full or partial UPS. If Full, please advise siting for Full UPS. Please remove 30 min runtime as no full UPS can accommodate that.
1f. Table Height Range. Please change table height range from 43-99 to 53-99 cm to allow full and fair competition.Please clarify whether or not the existing ceiling mounted injector support location shown on drawing 14407500 would be reused for the new injector and no additional work will be required.

Flooring:

1.Existing flooring to be replaced in the Exam and Control rooms?
2.If so, do you want heat welded seamless sheet vinyl flooring , VCT, or LVT?
3.4” or 6” rubber or vinyl base or flash cove

Walls:

1. Paint all existing walls or only where walls were patched?

Ceilings:

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork:

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting:

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power:

1.If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?
2.If full system UPS is requested where will this system be located and where will the source feeder for the UPS system fed from?

HVAC:

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?

Other:

1. If a patient lift exists will the VA remove existing patient lift, store, and reinstall the lift? 2a. No, fluro biospy capabilties are not required.

2i. Full, 15 minutes runtime will suffice.

1f. This can be changed to 53-99 to accommodate competition. Yes. Ceiling mounted injector support will be reused.

Flooring

1. Flooring will be replaced.

2. welded seamless vinyl.

3. 6" vinyl.

Walls

1. Paint all existing walls and patch.

2. Yes. Ceiling lift will need to be relocated.

Millwork

1. No.

Lighting No, existing lighting may need to be relocated.

Power Equipment will be fed from 1-B255 in the basement switchgear room located 2 floors below equipment approximately 15 feet vertically and another 25 feet horizontal.

2. Yes, waiting on location information UPS will be fed from same source location as equipment.

HVAC

1. we do not have a recent T&B report to provide.

2. Current mini-split unit is aged, please anticipate replacing unit.

VISN 10: VA Healthcare System of Ohio655 SAGINAW, MI655B40007There was no matrix attached in the consolidation. Will there be a matrix sent?Matrix is reattached for use.
VISN 20: VA Northwest Network663 SEATTLE, WA663B430051a. There are no commercially available scanners that acquire 512 slices. Please clarify this specification.This requirement is defined as the number of slices capable of being acquired simultaneously and several manufacturers and models meet this requirement.
VISN 20: VA Northwest Network663 SEATTLE, WA663B430052c. There are multiple methods of conventional EID spectral/dual energy imaging, including Dual Spiral, kV switching (fast or slow), pre-patient filtration, sandwich detector and dual-source. Spectral imaging is also available with advanced Photon Counting technology. Does this request award any additional weighting based upon the scanning method?As long as the scanning method provides equivalent results on imaging capabilities then this requirement should be considered met. No additional weighting will be given past that.
VISN 20: VA Northwest Network663 SEATTLE, WA663B430053a-g. What is the facilities post processing requirement? Scanner or workstation?The requirement is to be able to acquire and process images without impact to acquistion. These requirements are not facility post processing requirements.
VISN 20: VA Northwest Network663 SEATTLE, WA663B43005Is seismic anchoring a requirement for this scanner?Yes
VISN 20: VA Northwest Network663 SEATTLE, WA663B43005Line 46 - power conditioner. Is there space allotted for this equipment?Location will be deteremined after award. Reminder this is for a power conditioner not a UPS.
VISN 20: VA Northwest Network663 SEATTLE, WA663B430051c. Please clarify detector coverage should be160mm?

2k. Please indicate if a full or partial UPS is required. If Full, please indicate location for siting purposes.

3d. Does the VAs current Server solution meet this requirement if Vendor provides additional licenses?

4a, b ,c, d. Does the VAs current Server solution meet this requirement if Vendor provides additional licenses? 1c. This is not the specification for 1c. Specification is .625 detector width in z axis.

2k. Workstation UPS 3d. This is a specification for processing workstation not a post-processing workstation.

4a, This is a specification for processing workstation not a post-processing workstation.

VISN 8: VA Sunshine Healthcare Network 673 TAMPA, FL 673B40031 Line 34 of the technical specification states…The CT scanner shall provide the ability for the user to independently operate the table, gantry, and CT fluoroscopy mode from the control room.

Is CT Fluoro needed? This system is only used for oncology simulationFluoro mode is not a requirement for this project. Tech specs have been updated to properly reflect that.
VISN 8: VA Sunshine Healthcare Network673 TAMPA, FL673B40031Line 84 of the technical specification states…Contrast Injector with proven reliable synchronization

Does the customer request a ceiling mount or pedestal injector? A Contrast Injector would be considered as an enhancement/value added but is not a requirement for this project. We would prefer a pedestal injector if one is included.

Tech specs have been updated to properly reflect that.

VISN 8: VA Sunshine Healthcare Network 673 TAMPA, FL 673B40031 1b. Please change to 80cm to allow for open competition 1c. Please update to 0.625mm 1k. Please update to 6200 lbs 2a. Please confirm if Fluoro is required

2e. Please confirm if this requirement is for full or partial UPSFlooring:
1.Existing flooring replaced?
2.Exam and Control room or just Exam room? If so, do you want?
3.Heat welded seamless sheet vinyl or LVT?
4.4” or 6” rubber base or flash cove

Ceilings

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power

1. If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?

HVAC

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?

Equipment Layout:

1. Can the room where the ice maker be utilized as an equipment room? 1b. Tech specs updated 1c. Tech specs updated 1k. Tech specs updated 2a. Fluoro is not required. Tech specs updated 2e. Partial UPS is fine Flooring

1. Yes

2. Both Exam and Control room

3. Heat welded seamless sheet vinyl

4. 4"

Ceilings

1. Yes, replace to new standard grid and tile

Milwork

1. Yes, all new millwork

Lighting

1. Yes, LED lighting needs to be dimmable. Meet the TIL design guide.

2. Preferred dimmable console lighting also. Meet the TIL design guide.

Power

1. GZNL1-panel circuit 13, 15, and 17

HVAC

1. No current T&B (only has 950 cfm currently to the best of our knowledge)

2. Yes, will need new Air Handler unit to meet the new TIL design requirement

Equipment Layout

1. Per the turnkey rubric, no.

VISN 8: VA Sunshine Healthcare Network673 TAMPA, FL673B40035Please provide the latest HVAC Testing and Balance (T&B) report in order to determine if additional HVAC work is required.There is no current T&B (only has 950 cfm currently to the best of our knowledge)
VISN 22: VA Desert Pacific Healthcare Network678 TUCSON, AZ678B42017678B42023Q1 - 2.d. 1000mA @100kVp. Our Cesium detector is 20% lower in dose. Respectfully request adjust to 800mA at 100kVp. Q2. 2.e. Respectfully request adjustment of minimum lp/mm to minimumof 3.4 lp/mm for open and fair competition. Q3. 2.h. Respectfully request tube height from floor to be expanded from 1" to 16" to actual level of X-ray Tube and not handle distance to the floor. Q4. 2.K&L please adjust table minimum load capacity 649lbs max to allow for open and fair competition. Q5. Respectfully request minimum table height from 19.7 to 21" to allow for open and fair competition. Q6. 3.r. Respectfully request ability to provide Body Tomosynthesis verses Linear Tomography capabilities to expand fair and open competition. Q7. 4.a. Respectfully request change from Minimum Acquisition Workstation from 24" down to a minimum of 19". This appears to be a lockout spec. and doesn't allow for fair and open competition. Q8. 4.d. Respectfully request change from Minimum processing workstation from 24" down to 19". This appears to be a lockout spec and and doesn't allow for fair and open competition. Q9. 5.f. FDA cleared AI algorithms appear to be lockout specs to focus on a single vendor and doesn't allow for fair and open competition.Q1. Accept Change

Q2. Accept Change Q3. Accept Change Q4. Accept Change Q5. Accept Change Q6. Accept Change Q7. Accept Change Q8. Accept Change Q9. 5.f - AI algorithms must be FDA approved and are necessary.

VISN 22: VA Desert Pacific Healthcare Network678 TUCSON, AZ678B420171c. Please confirm quantity of detectors required, if a third wireless detector is required, what size?
5a. Do you need to do stitching at the wall and table or wall only?RFI Questions – Room Finishes

Flooring:

1.Does the Existing flooring need to be replaced in the exam room and control room?
2.Heat welded seamless sheet vinyl or LVT?
3.4” or 6” rubber base or flash cove

Ceilings

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced?

Millwork

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)?

Lighting

1.Do you want existing lighting to be replaced with new LED lighting?
2.Do you need any additional lighting than what currently exists?

Power

1. If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.?

HVAC

1.Can you please provide a recent T&B (test and balance) report?
2.If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning?3 detectors. Size requirement for the 3rd detector is 10x12.
Stitching is preferred at both wall and table.RFI Questions – Room Finishes 1832-80

Flooring:

1. Does the Existing flooring need to be replaced in the exam room and control room? Yes

2. Heat welded seamless sheet vinyl or LVT? Vinyl welded seams

3. 4” or 6” rubber base or flash cove Ceilings? 6” cove based

1. If the new imaging system doesn’t require modifying the ceiling, do you want any or all the ceiling grid and/or panels replaced? Yes all the ceiling grid and/or panels replaced Millwork

1. Do you want any or all millwork replaced (upper/base cabinets, counter tops, etc.)? Yes all millwork replaced Lighting

1. Do you want existing lighting to be replaced with new LED lighting? Yes

2. Do you need any additional lighting than what currently exists? No Power

1. If source panel for lineside feeder was not identified during walkthrough, can you please provide location, distance, name of panel, etc.? Panel AC1HE (in room 1832) 277/480V fed from panel DSACH 277/480V via 250A breaker in room 1621 building 80.

HVAC

1. Can you please provide a recent T&B (test and balance) report? No, recent (this year) T&B will be provided, if more recent is needed vendor should produce

2. If the proposed imaging system does not require additional AC, do you need HVAC unit(s) replaced due to age or not functioning? Yes, HVAC may need replacement due to age pending install start date.

VISN 22: VA Desert Pacific Healthcare Network678 TUCSON, AZ678B42017Line 13 XR Rad Southern AZ: Is a Riverain Bone Suppression solution acceptable (rather than dual energy)?Yes, if FDA approved
VISN 22: VA Desert Pacific Healthcare Network678 TUCSON, AZ678B42018678B42021Q1 - 2.d. 1000mA @100kVp. Our Cesium detector is 20% lower in dose. Respectfully request adjust to 800mA at 100kVp. Q2. 2.e. Respectfully request adjustment of minimum lp/mm to minimumof 3.4 lp/mm for open and fair competition. Q3. 2.h. Respectfully request tube height from floor to be expanded from 1" to 16" to actual level of X-ray Tube and not handle distance to the floor. Q4. 2.K&L please adjust table minimum load capacity 649lbs max to allow for open and fair competition. Q5. Respectfully request minimum table height from 19.7 to 21" to allow for open and fair competition. Q6. 3.r. Respectfully request ability to provide Body Tomosynthesis verses Linear Tomography capabilities to expand fair and open competition. Q7. 4.a. Respectfully request change from Minimum Acquisition Workstation from 24" down to a minimum of 19". This appears to be a lockout spec. and doesn't allow for fair and open competition. Q8. 4.d. Respectfully request change from Minimum processing workstation from 24" down to 19". This appears to be a lockout spec and and doesn't allow for fair and open competition. Q9. 5.f. FDA cleared AI algorithms appear to be lockout specs to focus on a single vendor and doesn't allow for fair and open competition.Q1. Accept Change

Q2. Accept Change Q3. Accept Change Q4. Accept Change Q5. Accept Change Q6. Accept Change Q7. Accept Change Q8. Accept Change Q9. 5.f - AI algorithms must be FDA approved and are necessary.

VISN 22: VA Desert Pacific Healthcare Network678 TUCSON, AZ678B420181c. Please confirm quantity of detectors required, if a third wireless detector is required, what size?
5a. Do you need to do stitching at the wall and table or wall only?RFI Questions – Room Finishes

Flooring:

1.Does the Existing flooring need to be replaced in the exam room and control room?
2.Heat welded seamless sheet vinyl or LVT?
3.4” or 6” rubber base or flash cove

Ceilings

1. If the new imaging system doesn’t require modifying the ceiling, do you want…