About this file

36A77618Q9083 ATTACHMENT M - Key Milestone Dates - Perry Point - 08162018.docx

View the file

Other files

File Type Posted
36A77618Q9083-0002000.docx DOCX document
36A77618Q9083-0002001.docx DOCX document
36A77618Q9083-0002003.docx DOCX document
36A77618Q9083-0002002.docx DOCX document
36A77618Q9083-0001000.docx DOCX document
36A77618Q9083-011.docx DOCX document
36A77618Q9083-012.pdf PDF
36A77618Q9083-006.pdf PDF
36A77618Q9083-007.pdf PDF
36A77618Q9083-003.docx DOCX document
36A77618Q9083-017.xls XLS spreadsheet
36A77618Q9083-010.docx DOCX document
36A77618Q9083-008.pdf PDF
36A77618Q9083-004.doc DOC document
36A77618Q9083-009.pdf PDF
36A77618Q9083-015.pdf PDF
36A77618Q9083-014.xlsx XLSX spreadsheet
36A77618Q9083-013.docx DOCX document
36A77618Q9083-018.docx DOCX document
36A77618Q9083-005.xlsx XLSX spreadsheet
36A77618Q9083-002.docx DOCX document
36A77618Q9083-001.docx DOCX document
36A77618Q9083-000.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Event Anticipated Date

Construction Award
31 October 2018
Construction Start
7 November 2018
Beneficial Occupancy Date (BOD)
7 May 2021
Day One Date
8 November 2021
IO Contract Completion
6 May 2022