36A77618Q9073-0001000.docx
DOCX document 33 KB Posted
- Attached to
- Orlando VA Medical Center - Daytona Beach IOT&A IDIQ Daytona Beach Multi Specialty Out Patient Clinic
- Solicitation number
- 36A77618Q9073
About this file
36A77618Q9073 0001 36A77618Q9073 0001.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36A77618Q9073-0001001.docx | DOCX document | |
| 36A77618Q9073-017.docx | DOCX document | |
| 36A77618Q9073-007.pdf | ||
| 36A77618Q9073-016.xls | XLS spreadsheet | |
| 36A77618Q9073-012.docx | DOCX document | |
| 36A77618Q9073-008.pdf | ||
| 36A77618Q9073-002.docx | DOCX document | |
| 36A77618Q9073-015.docx | DOCX document | |
| 36A77618Q9073-004.doc | DOC document | |
| 36A77618Q9073-005.xlsx | XLSX spreadsheet | |
| 36A77618Q9073-009.docx | DOCX document | |
| 36A77618Q9073-010.docx | DOCX document | |
| 36A77618Q9073-013.xlsx | XLSX spreadsheet | |
| 36A77618Q9073-003.docx | DOCX document | |
| 36A77618Q9073-011.pdf | ||
| 36A77618Q9073-014.pdf | ||
| 36A77618Q9073-006.pdf | ||
| 36A77618Q9073-001.docx | DOCX document | |
| 36A77618Q9073-000.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 36C776 Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence
OH
44131 00776 Department of Veterans Affairs Department of Veterans Affairs 6150 Oak Tree Blvd, Suite 300 Independence
OH
44131 To all Offerors/Bidders
36A77618Q9073 08-30-2018
X X X x The purpose of this amendment is to answer submitted questions to the solicitation and to provide an updated Task Order #1 Pre-Planning Services dated August 30, 2018.
Heidi Gallaher Contracting Officer
CONTINUATION PAGE
Orlando/Daytona Beach Initial Outfitting Activation and Transitioning IDIQ/Task Order #1 Questions/Answers to Solicitation RFQ 36A77618Q9073 The purpose of this amendment is to:
1. Replace original solicitation - Task Order 1 PWS Pre-Planning Services with a revised version –dated 30 Aug 2018. Task 7.5 Activation Support Services was added to provide for the Gap Analysis meeting and report.
2. Answer the questions Submitted for Solicitation: 36A77618Q9073 – Initial Outfitting, Transition, and Activation IDIQ RFQ Orlando Medical Center, Daytona Beach Multispecialty Out-Patient Clinic:
All other terms and conditions of the solicitation remain the same and in full force and effect.
*** The Government received several questions concerning deliverable due dates. The Government will not be changing any due dates for its requirements during the solicitation process. If applicable, these suggestions can be addressed after award. ***
1. Question: In initial review of scope I noticed the PM must be PMP certified. One of my PM’s has a Masters Certificate in Project Management and I myself have a MBA in Project Management. Both of which far exceed the PMP certification. Can either of these two be used in lieu of the PMP cert?
Answer: Key Personnel requirements for Project Manager are amended as follows:
Project Manager
1. A minimum of five (5) years of experience in Project Management
1. A minimum of three (3) years of experience in healthcare initial outfitting, transition, and activation services
1. Certified Project Management Professional (PMP). Other certifications the offeror believes to be equivalent may be provided and the Contracting Officer will determine its equivalency.
1. Experience in activating Federal healthcare facilities
1. Well versed in healthcare infrastructure, operations, and/or practice and have direct experience in transition activities
2. Question: The contractor shall assure that all appropriate personnel are invited to attend each meeting either telephonically or in person. The contractor’s PM should be available to attend all requested meetings in person, unless other arrangements have been approved by the COR prior to the meeting. Since this is a FFP contract how do we price this effort if PM is not onsite fulltime unless attend could be understood is via conf call and not in person. Otherwise can you identify how many times we should price for this request? Since we have to price without arrangements with the COR can you provide some guidance?
Answer: At first the team should be in person for the kick off meeting , then present for user group meetings. We plan to use Skype and telephone calls for regular ongoing follow up calls weekly . Refer to 7.1 of the Task 1 document. The PM must be on-site to facilitate, schedule, and lead regular meetings with the OVAMC/Daytona staff, to ensure the timely and effective completion of tasks and deliverables.
3. Question: The contractor shall conduct briefings and prepare comprehensive reports to keep managers and executives advised of project plans and progress and to communicate findings and recommendations. Contractor shall provide monthly status reports to the Activation Steering Committee and as needed or upon request. Concern forms around the language as needed. Can we stipulate monthly for all reports?
How do we price serious reports like activation steering committee reports which require input from multiple team members if more than monthly? The term as needed or upon request seems to be open to interpretation. Can you provide some guidance?
Answer: Reports are due monthly. There may be an instance where a report is requested more than once in a month. The Government is not paying “Per deliverable” but as a whole task.
4. Question: Provide and coordinate comprehensive interior design (CID) services or coordination of CID services, ensuring incorporation of evidence-based health care concepts Are we creating the CID or just coordinating others work? If creating can you identify what you want included in the CID specifically? If just coordinating can you describe who we would be coordinating?
Answer: On site VA Interior Design will coordinate with the IOT&A contractor to select furniture, fixtures, and finishes and artwork.
5. Question: The contractor shall develop the initial design based upon the FF&E list (Attachment C). The contractor will lay into the drawings provided by the VA all the FF&E based upon the equipment list and program for design information. The drawings provided by VA may be limited to walls and mechanical, electrical, and plumbing (MEP) locations. When will we be given the drawings in order to complete the task? The process needs to be the IO contractor provide room typical drawings to the AE in time for them to lay into their drawings which will be sent to the VA. The IO contractor and the AE must work on the same version of the drawings or the risk to the project will be significantly increased. The mandate to the AE must be that they need to take the typicals provided by the IO Contractor and include them in their drawings.
Answer: Drawings to be provided around the second half of 2019.
6. Question: The general contractor will be required to identify all MEP information necessary and timelines needed. The IOT&A contractor is to develop the make and model of all equipment with the DD2 submittal.
Does this mean the GC will ask the pre-planner to do all the investigative work and provide the engineering information necessary to design the MEP of the facility? No Please modify the scope to clearly show the pre-planner only provides the JSN, room location, cut sheet of the basis of design equipment and or a spreadsheet that lists the salient characteristics? The IO contractor does not mandate for provide engineering design services.
Answer: The IO contractor does not need to provide engineering design services however they need to obtain shop drawings for specific items to be determined by VA and maintain a log of shop drawings.
7. Question: contractor shall review for code and work flow efficiency. In addition, the contractor shall call out in each room all utility conflicts and recommended resolutions. What is the expectation regarding call out? Does this mean we have notes that suggest locations of the utilities, adding additional locations for capacity or location of equipment? As for code review this is part of the design review report typically. Are they two requirements different?
Answer: No
8. Question -Please explain how the pricing template will account for companies that may have higher hourly rate personnel but can complete the tasks in less man hours? It appears all we can do is insert our hourly rate but all companies are based upon a mandated number of hours.
1. Answer: In the pricing sheet for TO1 the offerors will propose the hours they will actually need to complete the tasks and this will factor into the Total Evaluated Price. In the Task Order 1 Technical submission the offerors will include both a narrative detailing the offerors technical approach as well as a Basis of Estimate detailing how the proposed hours and labor mix was determined. Both of these submissions should identify offerors who have a more efficient or cost reductive approach to their allocation of labor hours across labor categories.
In the IDIQ Management Plan offerors will detail their overall approach to managing the IDIQ as a whole. This should include their approach to hiring and execution (for example higher paid employees who require less hours to complete their tasks).
9. Question -Can PMP be attained within first 9 mos for PM?
Answer: See response to question #1
10. Question - Since this is a FFP contract how do we price this effort if PM is not onsite fulltime unless attend could be understood is via conf call and not in person. Otherwise can you identify how many times we should price for this request? Since we have to price without arrangements with the COR can you provide some guidance?
Answer: Refer to 7.1 of the Task 1 document. The PM must be on-site to facilitate, schedule, and lead regular meetings with the OVAMC/Daytona staff, to ensure the timely and effective completion of tasks and deliverables.
11. Question - How do we price serious reports like activation steering committee reports which require input from multiple team members if more than monthly? The term as needed or upon request seems to be open to interpretation. Can you provide some guidance?
Answer: Deliverables and Deliverable Due dates will be finalized upon kick-off and Gap Analysis meeting. The total task should be firm fixed price, not per deliverable (i.e., monthly report, rather than the totality of reports needed to the activation steering committee)
12. Question -Are we creating the CID or just coordinating others work? If creating can you identify what you want included in the CID specifically? If just coordinating can you describe who we would be coordinating?
Answer: : Daytona Beach, VA Interior Design will coordinate with the IOT&A contractor to select furniture, fixtures, and finishes and artwork.
13. Question/Statement - When will we be given the drawings in order to complete the task? The process needs to be the IO contractor provide room typical drawings to the AE in time for them to lay into their drawings which will be sent to the VA. The IO contractor and the AE must work on the same version of the drawings or the risk to the project will be significantly increased. The mandate to the AE must be that they need to take the typicals provided by the IO Contractor and include them in their drawings.
Answer: See response to question #5. Drawings to be provided around July/August 2019.
14. Question - Does this mean the GC will ask the pre planner to do all the investigative work and provide the engineering information necessary to design the MEP of the facility? Please modify the scope to clearly show the pre-planner only provides the JSN, room location, cut sheet of the basis of design equipment and or a spreadsheet that lists the salient characteristics? The IO contractor does not mandate for provide engineering design services.
Answer: Correct. The IO contractor does do all investigative work and provide engineering information such as obtaining shop drawings from vendors for specific items to be determined by VA. IOT&A contractor will maintain a log of shop drawings. Also note, this is a combination IDIQ which includes Pre-Planning and activation. This IDIQ is not for pre-planning services only.
15. Question -What is the expectation regarding call out? Does this mean we have notes that suggest locations of the utilities, adding additional locations for capacity or location of equipment? As for code review this is part of the design review report typically. Are they two requirements different?
Answer: No
16. Question – Can we confirm the AE will lay in all the CC items (items that they are providing).
Answer: Yes
17. Question: Can we confirm the AE will lay in all the CC items (items that they are providing) Answer: Duplicate
18. Question: When is the projected award date?
Answer: NLT 9/28/2018
19. Question: When is the projected contract start?
Answer: NLT 9/28/2018
20. Question: Does the site have a dedicated activation team assigned for the activities?
Answer: Yes, however not for all activities.
21. Question: Has the site assigned a dedicated activation program / project manager to lead the effort?
Answer: Yes
22. Question: Will the site issue contractor facility badges until the appropriate security investigations are completed and badges are issued?
Answer: Contractors who will be on-site before any necessary security investigations are complete will be given a flash bade or if on-site meetings are required, the site will provide an escort.
23. Question: Will the contractor's Share site need to interface with the VA SharePoint for the facility?
Answer: Orlando VA has their own share-point site that will be used. Contractor to Maintain, upload and organize activation related documents.
24. Question: Are the section F 1-5 write ups to be submitted as a single volume and section F 6-7 as a separate price volume? Are we submitting all information in section F as a single volume plus the Activation TEP Calculation Workbook?
Answer: All Section F write-ups should be submitted in one volume and the Activation TEP Calculation Workbook will be submitted in the Excel spreadsheet.
25. Question: Is there a preferred format (MS Word®, PDF) for submission of the technical volume?
Answer: Prefer PDF
26. Question: Please clarify that the places for performance are those identified in Orlando FL and Daytona Beach, FL Answer: Both Orlando and Daytona are both places for performance. Initial planning is primarily Orlando.
27. Question: Will the government provide job descriptions for key personnel? Other listed personnel?
Answer: No, the Government's minimum requirement is to have the key personnel meet the stated specific experience and certification requirements; the contractor is able to infer the necessary level of experience and qualifications to meet other PWS task requirements and propose accordingly.
28. Question: Are there any page margin requirements for this submission?
Answer: No
29. Question: Are cover letters and title pages included in the page max count?
Answer: No
30. Question: Is the OPC in a leased space in an existing building? Is the project a tenant fit-out type?
Answer: The OPC is a leased space in an existing building. The project is a tenant fit-out type.
31. Question: In what stage is the design/construction process currently? Have all floor plans/ceiling plans/interior elevations been developed?
Answer: No, solicitation for design/build project expected to be sent out at end of September 2018.
32. Question: Have the Basis of Design furniture and equipment plans been developed and approved by the VA to a Design Development level?
Answer: No, initial planning has been done in SEPS and users have reviewed equipment lists.
33. Question: Is the site and user groups prepared to provide input and feedback to maintain the accelerated timelines presented?
Answer: Yes
34. Question: Has an artwork budget been established?
Answer: No, but an artwork budget will be developed
35. Question: Will the artwork program be developed as a Basis of Design with Artwork types defined, or are the individual artwork pieces to be selected? If so, how can artwork program be bid out, rather than sole source?
Answer: Yes, and can be bid out.
36. Question: How many 3-D renditions should be planned for?
Answer: 2 versions
37. Question: Has a wayfinding plan been developed for the project?
Answer: TBD, not developed at this time
38. Question: Has the signage scope been assigned to a contractor? Who is responsible to develop the Message Schedule?
Answer: Yes, VA in conjunction and Lessor of Building
39. Question: “Approval for Rental Vehicles is discouraged?” Please clarify Answer: For any travel awarded on a cost-reimbursable basis, pre-approval for all travel costs must be submitted to the COR before travel is approved. The COR will review to make sure that the Government is approving the appropriate number of car rentals for contractor personnel expected to travel and be on site. In the instant of the first task order, travel is being quoted as firm fixed price, no prior authorization to travel is needed.
40. Question: Enterprise – Project Manager “on-site” - clarification desired, i.e. on-site full-time; on demand, in the locality Answer: It is up to the contractor to determine when the PM is required on site, how many days, and where they are located. Location obviously affects travel costs.
41. Question: Will contractor team members be allowed or offered on-site space at government site?
Answer: Yes, temporarily and limited space.
42. Question: "Please clarify The PM must be on-site" Answer: The PM must be on-site to facilitate, schedule, and lead regular meetings as well as any other ad hoc meetings that may occur during the period of performance. The PM does not need to be on site fulltime. PM work can be completed at the contractor’s site.
43. Question: Same as above – Contractor provides Share-point like site – since interconnectivity cannot occur, does this site have to be physically at government site, or, physical access to the Sharepoint to the Sharepoint site? Also Deliverables, page 14, Deliverable 010 Answer: Orlando VA has their own share-point site that will be used. Contractor to Maintain, upload and organize activation related documents.
44. Question: Does the government have a timeline for the release of a subsequent Task Order (TO2) to support this effort?
Answer: Not at this time.
45. Question: Since award of the lease for the Daytona location is not until December of 2018 or later, is it projected that the award date for this IDIQ be dependent on the actual award date of the lease?
Answer: No. This IDIQ and first task order will be awarded NLT 9/28/2018
46. Question: Will the contract office assign task level CLINs to the solicitation for pricing or will the pricing depend on the spreadsheet provided?
Answer: Pricing is per Task Order, using the awarded labor rates and labor categories provided for in the IDIQ solicitation. Firm fixed priced CLINS are at the Task Order level. Task Order 1 pricing is provided for in the spreadsheet provided. Each Task in Task Order #1 is a CLIN. Each CLIN pricing is to be provided for in the Basis of Estimate for evaluation and award.
47. Question: Section B-2(e) Travel can be awarded under a Firm Fixed Price Basis. Is the travel Firm Fixed Price total priced on the travel sheet for each task order? Will travel has it's own CLIN or included in other CLINS? For FFP travel, how is the monthly invoice amount determined? Will a travel authorization form be required for each travel trip?
Answer: The travel authorization form is only used when a task order includes cost reimbursable travel. For Firm Fixed Price travel, travel will be a separate CLIN and invoiced monthly (or according to the contractor’s proposed schedule of values). We are only asking for firm fixed price travel for Task Order 1 in the pricing spreadsheet.
48. Question: Was there meant to be a TO1-015, TO1-005 and TO1-010 deliverable listed?
Answer: No. These deliverables are not part of task order 1.
49. Question: Was there meant to be a TO1-015, and TO1-019 deliverable listed?
Answer: No. These deliverables are not part of task order 1. Site does not require an Artwork Package at this time. Correct…Artwork will be considered for future task.
50. Question: Is there to be any requirement for Signage/Way-Finding?
Answer: AE to develop. Coordination with VA Interior Design.
51. Question: Was there meant to be Concept Of Operations (Conops) and Transition Planning Services and STRATCOM Services listed?
Answer: No, not with this task order
52. Question: Would the Contracting Officer consider changing the PMP requirement of the Project Manager to preferred but not required?
Answer: See answer to questions #1
53. Question: Please add language to exempt the AIMS from the 30-page count limit. Suggested Edit: Please change the last sentence of the included requirement to say “The page limit does not apply to Section F, Paragraph (3) bullet (d.) “Sample Activation Integrated Master Schedule (AIMS)”; Section F, Paragraph (6), Price Submission; or Paragraph (7), Other Requested Submittals.”
Answer: This exemption language is already included in the header to Section F, Paragraph 3 - "IDIQ Management Plan (maximum 8 pages, excluding AIMS):"
54. Question: In order to best present information to the government, would the government consider allowing smaller font sizes in graphics and tables? Suggested Edit: Please change the included requirement to say “Font type shall be no smaller than size 12 font (excluding graphics and tables) on standard 8.5” x 11” pages.”
Answer: Yes for presentation purpose but not smaller than 10. However graphs and tables must be able to print legible on 8.5 X 14 and/or 11 x 17 . Graph should be readable version for printing purposes.
55. Question: In order to avoid shipping on the Labor Day holiday, can the government please change the due date to 9-4-2018 or later? Suggested Edit: Please change the due date to 9-4-2018 or later.
Answer: Shipping is not a requirement for submission. If you prefer to “ship”, you will have to send it earlier to guarantee receipt before Monday, September 4th. Quotes are accepted (and referred) via email.
56. Question: IDIQ Solicitation, Pg. 29 (4) b-c Context: The instructions say:
“b. A Basis of Estimate worksheet shall be created and submitted to show the details of the proposed labor mix for each CLIN in Task Order 1. This worksheet is separate from attachment N “Activation Total Evaluated Price (TEP) Calculation Workbook”; however, the proposed labor categories and labor hours must match the “Activation TEP Calculation Workbook” for Task Order 1. c. A narrative describing how fixed price travel was determined, to include the number of trips, number of days, number of travelers, and description of any additional costs that were identified in the “Activation TEP Calculation Workbook”, “4-TO 1 Travel” tab under Column M “Additional Costs.” This narrative shall not contain any cost information.” Question/Comment: These items appear to relate to pricing information, and appear to belong under (6) Price Submission. Suggested Edit: Please move (4) b. and c. under (6) Price Submission or exclude (4) b and c from the 8-page limit.
Answer: The basis of estimate for Task Order #1 is a technical submission, not pricing. Task Order #1 pricing is included in the overall pricing workbook.
57. Question: Is the IOT&A contractor expected to provide equipment recommendations prior to meeting with the staff?
Answer: No
58. Question: Is the Project Manager requested/required to be on-site full time for the duration of the Task Order?
Answer: No
59. Question: Are medical equipment items expected as part of the FFE design submittal process?
Answer: Yes
60. Question: When is the anticipated award and information cutoff dates for the lease agreement?
Answer: Design/build award to lessor expected January 2019 and VA planning to take possession of the building October 2021
61. Question: The identified schedule would require staff to be prepared to meet for the FFE design review/re-use inventories within 15/30 days of award respectively. Are these dates flexible or are they fixed in order to support other contract/construction deadlines?
Answer: Dates are flexible
62. Question: When is the anticipated date for the VA to sign the lease agreement?
Answer: October 2021
63. Question: The due date for proposal submission is currently Monday, September 3, 2018 no later than 10am. As this date is a federal holiday, would the Government consider extending the due date for proposal submissions to Wednesday, September 5, 2018?
Answer: Not at this time.
64. Question: Will the VA provide any workspace for contractors?
Answer: Yes temporarily and limited space.
65. Question: Will this VA provide IM/IT assets to contractor staff?
Answer: If this question is in regards to Government furnished computers/laptops, then no. Equipment is not available to be provided. (PIV reader for card and training is required)
66. Question: How many Attainia licenses will be available for the contractor’s use?
Answer: one, with multiple users
67. Question: Submittal 22, Master Key Plan indicates the IOT&A contractor will provide key cores for the facility. Is this accurate? Key cores are typically provided to the locksmith by the General Contractor.
Answer: Not accurate - key cores are provided by General Contractor to VA who will provide to locksmith.
68. Question: How much estimated reuse do the current clinics have?
Answer: Clarification – reuse of what? If referring to equipment 5-10% of equipment.
69. Question: Is AEMS/MERS still accurate? Will the organization transition to Maximo prior to the move?
Answer: No AEMS/MERS is obsolete at Orlando VA…our Logistics staff uses Maximo.
70. Question: 14.2.8 Warehousing and Warehousing Management Services: Please clarify what seems to be contradictory statements, the paragraph directs that only Government personnel can receive equipment at the warehouse; however, later under submittal 54 Receiving Logs, indicates the contractor will receive and manage all equipment inventory of FFE in the warehouse and report daily to the Government via the receiving logs.
Answer: If the Government issues a separate task order for Warehousing and Warehousing services, the Contractor will be expected to receive the items (FFE) into the warehouse and logged. The Government will sign off on official “Acceptance” for payment.
71. Question: 14.2.3 IT/IM Planning Support: Will the IO contractor be procuring the IM/IT systems or will those purchases be conducted through VAOI&T?
Answer: Through VA OIT
72. Question: 14.2.14. Information Technology: Will the IOT&A contractor be tasked with infrastructure installations i.e. Wireless Access Points (WAPs), and cabling requirements to Telecom Rooms (TRs)?
Answer: No
73. Question: 14.2.14. Information Technology: Bullet 10 is unclear if this is written as a requirement for the IOT&A contractor or information concerning what the General Contractor will perform. Many of the requirements are typical to infrastructure construction.
Answer: This is provided as information as some vendors have cabling requirements.
74. Question: Submittal 068: The description of the Biomedical Support Plan refers to paragraph 13.2.18. The paragraph is not in the submission. Could you elaborate on where the elements can be found?
Answer: That reference should say 14.2.15
75. Question: Warehouse Requirements: Is it the intent of the VA to place network equipment in the warehouse TR to accommodate receiving and IT equipment programming? If so, can you provide the specifications that the warehouse provider should meet?
Answer: Warehouse and Warehousing services will be ordered under a separate task order if required. Specifics will be provided for in a Warehouse PWS. You aren’t pricing the IDIQ.
76. Question: How many Government employees will need workstation accommodations in the provided warehouse?
Answer: Warehouse and Warehousing services will be ordered under a separate task order if required. Specifics will be provided for in a Warehouse PWS. You aren’t pricing the IDIQ.
77. Question: Are insurance requirements for the warehouse above and beyond the insurance required for the IDIQ?
Answer: Warehouse and Warehousing services will be ordered under a separate task order if required. Specifics will be provided for in a Warehouse PWS. You aren’t pricing the IDIQ.
78. Question: Please confirm the Offeror can use 10 point font type for graphics and tables.
Answer: Yes for presentation purpose but not smaller than 10. However graphs and tables must be able to print legible on 8.5 X 14 and/or 11 x 17 . Graph should be readable version for printing purposes.
79. Question: For the sample Activation Integrated Master Schedule (AIMS), can the Offeror use 11” x 17” pages to better show schedule detail? If so, would each 11” x 17” page count as one page or two pages?
Answer: 11” x 17” is acceptable for AMIS
80. Question: CONOPS and artwork are described in the PWS for the task order but in the deliverables section there are no deliverables listed. Does the government want an artwork package?
Answer: Yes, but this will be a later task.
81. Question: CONOPS is only stated but no Micro – Macro – IT – Transition CONOPS are mentioned or listed as deliverables can you further define the CONOPS deliverable expectation?
Answer: Not needed at this time, will be evaluated at a later date and if needed add as a separate task order.
82. Question: TO1-20. Below shows CONOPS but no deliverables – other than a statement initial CONOPS report. Can you please further define this expectation?
Answer: COPS is deleted from TO1-20 deliverable See attached document: Daytona Beach Task Order 1 Pre-Planning Services.