35572 Preliminary Bid Results.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
TVWD - 20230213 RFP for Progressive Design Builders for 189th Pump Station and Pipeline
Solicitation number
S-R34750-00005801
Issued by
Washington County, Barlow City, Oregon

About this file

This is a preliminary bid results tabulation for ITB No. S-73000-00005802/35572 issued by the State of Oregon on March 3, 2023, for the ESB D4 OR229 Stockpile Cleanups project located in multiple Oregon cities including Salem, Pendleton, Blodgett, Otis, Gresham, and Oregon City. The project involves a single line item for the removal of rock and woody debris on a lump sum basis. The bid closing occurred on March 3, 2023, at 11:00 AM, with six contractors submitting proposals for consideration.

Six contractors submitted bids for the removal work, with total prices ranging from $31,700.00 (Trees Plus Northwest LLC) to $457,198.08 (Western Construction LLC). The other bidders and their respective total bids were Alabar Construction, Inc. at $63,505.69; K&B Quality Excavating, LLC at $113,435.00; Page Concrete Construction Inc. at $178,451.25; and O'Malley Brothers Corporation at $324,500.00. All bidders held valid CCB (Contractors Craft Board) licenses. The tabulation document explicitly notes that it represents only a compilation of submitted bids and is not an indicator of award, with final contract award pending further evaluation and consideration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:3/3/23
ITB No.S-73000-00005802/35572BIDDER
NAME:Trees Plus Northwest LLCAlabar Construction, IncK&B Quality Excavating, LLCPage Concrete Construction Inc.O'Malley Brothers CorporationWestern Construction LLC
Bid Closing:March 3, 2023 11:00 AMCITY/STATE:Salem ORPendleton ORBlodgett OROtis ORGresham OROregon City OR
Description:ESB D4 OR229 Stockpile CleanupsCCB#:234684133424202260170832194179217484
This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Remove Rock and Wooddy Debris1LS$ 31,700.00$ 31,700.00$ 63,505.69$ 63,505.69$ 113,435.00$ 113,435.00$ 178,451.25$ 178,451.25$ 324,500.00$ 324,500.00$ 457,198.08$ 457,198.08
TOTAL$ 31,700.00$ 63,505.69$ 113,435.00$ 178,451.25$ 324,500.00$ 457,198.08