3-Addendum 1 2025.08.22.pdf

PDF 2 MB Posted

Attached to
Bowman Field
Solicitation number
US.198829
Issued by
Lycoming County, Pennsylvania

View the file

Other files

File Type Posted
1-2025.8.14 Bowman Field Construction Plan.pdf PDF
2-Project Manual 2025.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LIVIC Civil | 29 E Main Street, Bloomsburg, PA 17859 | (888) 987-1993

August 22, 2025

Bidders List

Re: Bowman Field Outfield Fence Replacement

ADDENDUM #1

Bowman Field Outfield Wall Replacement

Bids Due August 28, 2025

Summary:

No changes to the bid opening or construction dates. A summary of the changes is listed below this paragraph:

Changes to Project Manual:

1. C-410 Bid Form

a. Moved foul pole bid item from base bid to Alternate Bid #4

b. Added language allowing completion of paving and seeding/mulching to occur after March 1, 2026 since asphalt plants won’t be open and we won’t be able to grow grass until April.

2. C-520 Agreement Between Owner and Contractor

a. Moved foul pole bid item from base bid to Alternate Bid #4

b. Added language allowing completion of paving and seeding/mulching to occur after March 1, 2026 since asphalt plants won’t be open and we won’t be able to grow grass until April.

3. Section 012200 – Unit Prices

a. Moved foul pole bid item from base bid to Alternate Bid #4

b. Modified the Foul Pole Bid Item description to better match the revised detail.

Please note that placement of the poles is critical and a survey will be required to set and level them.

c. Clarified items with structural concrete – we will request concrete cylinder tests.

4. Section 116833 – Athletic Field Equipment

a. Modified the Foul Pole section.

Changes to Plans:

1. C801

a. Revised detail for the foul poles. The owner wants to re-use the existing foundations.

LIVIC Civil | 61 Duke Street, Suite 100, Northumberland, PA 17857 | (888) 987-1993

Sincerely, Andrew Keister

LIVIC Civil

635 N. Loyalsock Ave

Montoursville, PA 17754

Enclosures:

Bid Form

Agreement Between Owner and Contractor

012200 Unit Prices

116833 Athletic Field Equipment

Sheet C801

AndrewKeister

AK

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID FORM FOR CONSTRUCTION CONTRACT

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to

Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: www.pennbid.net – Bowman Field Outfield Fence Replacement

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. List of Proposed Subcontractors;

C. List of Proposed Suppliers;

D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids;

E. Contractor’s license number as evidence of Bidder’s State Contractor’s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids;

F. Required Bidder Qualification Statement with supporting data; and

G. Equal Employment Opportunity

H. Public Works Verification Form

I. Non-Collusion Affidavit

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Unit Price Bids

A. Bidder will perform the following Work at the indicated unit prices:

Item

No.

Description Unit Estimated

Quantity

Bid Unit Price Bid Amount

1 Mobilization LS 1 $

2 Clearing and Grubbing LS 1 $

3 Class 1 Excavation LS 1 $

4 Topsoil CY 80 $

5 Rock Construction Entrance EA 1 $

6 Inlet Filter Bag EA 3 $

7 Pumped Water Filter Bag EA 3 $

8 Concrete Washout EA 1 $

9 12” Thermoplastic Pipe, Group 3 LF 225 $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

10 8” Underdrain LF 430 $

11 Standard Inlet Box EA 2 $

12 Type M Frame and Bicycle Safe

Grate

Set 2 $

13 Nyloplast Inlets with Grates EA 9

14 Temporary Seeding LB 5 $

15 Seeding and Soil Supplements -

Permanent

LB 12 $

16 Dura Edge Crushed Shale

Warning Track Mix

CY 40 $

17 12’ Chainlink Fence LF 496 $

18 Temporary Construction Fence LF 1685 $

19 Concrete Curb LF 496 $

Total of All Unit Price Bid Items $

B. Bidder acknowledges that:

1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover

Contractor’s overhead and profit for each separately identified item, and

2. estimated quantities are not guaranteed, and are solely for the purpose of comparison of

Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.

3.02 Total Bid Price (Lump Sum and Unit Prices) Base Bid

Total Bid Price (Total of all Lump Sum and Unit Price Bids) Base Bid $

3.03 Alternate Bid #1

Batter’s Eye 40’x80’– Lump Sum Price to Add to Base Bid $

3.04 Alternate Bid #2

Batter’s Eye 36’x60’– Lump Sum Price to Add to Base Bid $

3.05 Alternate Bid #3

4” Underdrain in front of fence LF 576 $

3.06 Alternate Bid #4

Install New Foul Poles – Lump Sum Price to Add to Base Bid $

ARTICLE 4—TIME OF COMPLETION

4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

4.02 Bidder agrees that the Work will be substantially complete on or before February 20th, 2026, and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General

Conditions on or before March 1st, 2026. Incidental items like pavement restoration and seeding

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

and mulching will be permitted to be completed after March 1, 2026 but all work inside the fence including the stormwater collection system outside of the fence must be complete and the field ready for play by March 1, 2026.

4.03 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

5.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

5.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

5.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the

Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous

Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical

Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder’s (Contractor’s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract

Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

12. Bidder agrees to abide by the conditions of the Non-Discrimination/Sexual Harassment

Clause contained within the bid documents.

6.02 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

Address for giving notices:

Bidder’s Contact:

Name:

(typed or printed)

Title:

(typed or printed)

Phone:

Email:

Address:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Bidder’s Contractor License No.: (if applicable)

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

AGREEMENT BETWEEN OWNER AND CONTRACTOR

FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

This Agreement is by and between City of Williamsport (“Owner”) and ______________________

(“Contractor”).

Terms used in this Agreement have the meanings stated in the General Conditions and the Supplementary

Conditions.

Owner and Contractor hereby agree as follows:

ARTICLE 1—WORK

1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: Replacement of outfield fencing and related stormwater improvements at Journey Bank Ballpark at Historic Bowman Field.

ARTICLE 2—THE PROJECT

2.01 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: Bowman Field Outfield Fence Replacement

ARTICLE 3—ENGINEER

3.01 The Owner has retained LIVIC Civil, LLC (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities of Engineer, and have the rights and authority assigned to Engineer in the Contract.

3.02 The part of the Project that pertains to the Work has been designed by “Engineer.”

ARTICLE 4—CONTRACT TIMES

4.01 Time is of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

4.02 Contract Times: Dates

A. The Work will be substantially complete on or before February 20th, 2026, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before March 1st, 2026. Incidental items like pavement restoration and seeding and mulching will be permitted to be completed after March 1, 2026 but all work inside the fence including the stormwater collection system outside of the fence must be complete and the field ready for play by March 1, 2026.

4.05 Liquidated Damages

A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and

Milestones not achieved within the Contract Times, as duly modified. The parties also recognize the delays, expense, and difficulties involved in proving, in a legal or arbitration

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

proceeding, the actual loss suffered by Owner if the Work is not completed on time.

Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):

1. Substantial Completion: Contractor shall pay Owner $1,000.00 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial

Completion, until the Work is substantially complete.

2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $1,000.00 for each day that expires after such time until the Work is completed and ready for final payment.

4. Liquidated damages for failing to timely attain Milestones, Substantial Completion, and final completion are not additive, and will not be imposed concurrently.

B. If Owner recovers liquidated damages for a delay in completion by Contractor, then such liquidated damages are Owner’s sole and exclusive remedy for such delay, and Owner is precluded from recovering any other damages, whether actual, direct, excess, or consequential, for such delay, except for special damages (if any) specified in this Agreement.

4.06 Special Damages

A. Contractor shall reimburse Owner (1) for any fines or penalties imposed on Owner as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract

Times, and (2) for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in

Paragraph 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete.

B. After Contractor achieves Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, Contractor shall reimburse Owner for the actual costs reasonably incurred by Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for

Work to be completed and ready for final payment (as duly adjusted pursuant to the

Contract), until the Work is completed and ready for final payment.

C. The special damages imposed in this paragraph are supplemental to any liquidated damages for delayed completion established in this Agreement.

ARTICLE 5—CONTRACT PRICE

5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract

Documents, the amounts that follow, subject to adjustment under the Contract:

B. For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item).

Item

No.

Description Unit Estimated

Quantity

Bid Unit Price Bid Amount

1 Mobilization LS 1 $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

2 Clearing and Grubbing LS 1 $

3 Class 1 Excavation LS 1 $

4 Topsoil CY 80 $

5 Rock Construction Entrance EA 1 $

6 Inlet Filter Bag EA 3 $

7 Pumped Water Filter Bag EA 3 $

8 Concrete Washout EA 1 $

9 12” Thermoplastic Pipe, Group 3 LF 225 $

10 8” Underdrain LF 430 $

11 Standard Inlet Box EA 2 $

12 Type M Frame and Bicycle Safe

Grate

Set 2 $

13 Nyloplast Inlets with Grates EA 9

14 Temporary Seeding LB 5 $

15 Seeding and Soil Supplements -

Permanent

LB 12 $

16 Dura Edge Crushed Shale

Warning Track Mix

CY 40 $

17 12’ Chainlink Fence LF 496 $

18 Temporary Construction Fence LF 1685 $

19 Concrete Curb LF 496 $

Total of All Unit Price Bid Items $

Alternate Bid #1

Batter’s Eye 40’x80’– Lump Sum Price to Add to Base Bid $

Alternate Bid #2

Batter’s Eye 36’x60’– Lump Sum Price to Add to Base Bid $

Alternate Bid #3

4” Underdrain in front of fence LF 576 $

5.01 Alternate Bid #4

Install New Foul Poles – Lump Sum Price to Add to Base Bid $

The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer.

D. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.

ARTICLE 6—PAYMENT PROCEDURES

6.01 Submittal and Processing of Payments

A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General

Conditions. Applications for Payment will be processed by Engineer as provided in the General

Conditions.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

6.02 Progress Payments; Retainage

A. Owner shall make progress payments on the basis of Contractor’s Applications for Payment on or about the 1st day of each month during performance of the Work as provided in

Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions

(and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.

a. Ninety (90) percent of the value of the Work completed (with the balance being retainage).

1) If 50 percent or more of the Work has been completed, as determined by

Engineer, and if the character and progress of the Work have been satisfactory to

Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, there will be no additional retainage;

and

b. Ninety (90) percent of cost of materials and equipment not incorporated in the Work

(with the balance being retainage).

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to One-Hundred (100) percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less

Two-Hundred (200) percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.

6.03 Final Payment

A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the

Contract Price in accordance with Paragraph 15.06 of the General Conditions.

6.04 Consent of Surety

A. Owner will not make final payment, or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release.

6.05 Interest

A. All amounts not paid when due will bear interest at the rate of six (6) percent per annum.

ARTICLE 7—CONTRACT DOCUMENTS

7.01 Contents

A. The Contract Documents consist of all of the following:

1. This Agreement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

2. Bonds:

a. Performance bond (together with power of attorney).

b. Payment bond (together with power of attorney).

3. General Conditions.

4. Supplementary Conditions.

5. Specifications as listed in the table of contents of the project manual (copy of list attached).

6. Drawings (not attached but incorporated by reference) consisting of 16 sheets with each sheet bearing the following general title: Construction Plans for Bowman Field Outfield

Fence Replacement.

7. Drawings listed on the attached sheet index.

8. Addenda (numbers ____ to ____, inclusive).

9. Exhibits to this Agreement (enumerated as follows):

a. Non-discrimination/sexual harassment clause

10. The following which may be delivered or issued on or after the Effective Date of the

Contract and are not attached hereto:

a. Notice to Proceed.

b. Work Change Directives.

c. Change Orders.

d. Field Orders.

e. Warranty Bond, if any.

B. The Contract Documents listed in Paragraph 7.01.A are attached to this Agreement (except as expressly noted otherwise above).

C. There are no Contract Documents other than those listed above in this Article 7.

D. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract.

ARTICLE 8—REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS

8.01 Contractor’s Representations

A. In order to induce Owner to enter into this Contract, Contractor makes the following representations:

1. Contractor has examined and carefully studied the Contract Documents, including

Addenda.

2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the

Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Contractor has carefully studied the reports and drawings relating to Hazardous

Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Technical

Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (c) Contractor’s safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the

Contract.

8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.

9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. Contractor’s entry into this Contract constitutes an incontrovertible representation by

Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.

12. Bidder agrees to abide by the conditions of the Non-Discrimination/Sexual Harassment

Clause contained within the bid documents.

8.02 Contractor’s Certifications

A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this

Paragraph 8.02:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner,

(b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive

Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

8.03 Standard General Conditions

A. Owner stipulates that if the General Conditions that are made a part of this Contract are

EJCDC® C-700, Standard General Conditions for the Construction Contract (2018), published by the Engineers Joint Contract Documents Committee, and if Owner is the party that has furnished said General Conditions, then Owner has plainly shown all modifications to the standard wording of such published document to the Contractor, through a process such as highlighting or “track changes” (redline/strikeout), or in the Supplementary Conditions.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement.

This Agreement will be effective on _____________ (which is the Effective Date of the Contract).

Owner: Contractor:

(typed or printed name of organization) (typed or printed name of organization)

By: By:

(individual’s signature) (individual’s signature)

Date: Date:

(date signed) (date signed)

Name: Name:

(typed or printed) (typed or printed)

Title: Title:

(typed or printed) (typed or printed)

(If Entity is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest: Attest:

(individual’s signature) (individual’s signature)

Title: Title:

Address for giving notices: Address for giving notices:

Designated Representative: Designated Representative:

Name: Name:

(typed or printed) (typed or printed)

Title: Title:

Address: Address:

Phone: Phone:

Email: Email:

(If Entity is a corporation, attach evidence of authority to sign. If Entity is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)

License No.:

(where applicable)

State:

UNIT PRICES 012200 - 1

SECTION 012200 - UNIT PRICES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

1.2 DEFINITIONS

A. Unit price is a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1.3 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, taxes, overhead, and profit.

B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 REFERENCE STANDARDS AND SPECIFICATIONS

A. Standards and other Publications referenced as part of the specifications shall be of the edition in effect at the time of bidding and shall form a part of this contract.

B. References are made to the Pennsylvania Department of Transportation specifications. Unless otherwise noted, those specifications referred to and all construction to be in accordance with the Pennsylvania Department of Transportation Specifications Publication 408/2020 and

UNIT PRICES 012200 - 2

supplements thereto, unless otherwise noted or otherwise directed by the specifications of this project on the following pages.

C. Reference in the State specifications to “State”, “Chief Engineer”, or “Department” shall be interpreted by the engineer as herein defined. When particular articles or sections are referred to, all paragraphs other than those relating to payment shall apply. Payment shall be as defined in these specifications.

D. Where applicable, all materials used shall be on the “Bulletin 15 — Approved Construction

Materials (PennDOT Publication 35)" with the Pennsylvania Department of Transportation.

E. All bituminous, concrete, and other products used shall be supplied by a plant approved by the

Pennsylvania Department of Transportation.

F. The enclosed list of technical specifications and supplements are provided for your quick reference of applicable PennDOT Sections. This list may not be inclusive.

3.2 SCHEDULE OF UNIT PRICES – GENERAL CONSTRUCTION

A. All items comply with and are specified in PennDOT 408 unless otherwise noted.

B. Unit Price No. 1 - Mobilization

1. In accordance with PennDOT 408 Section 608.

C. Unit Price No. 2 – Clearing and Grubbing

1. In accordance with PennDOT 408 Section 201. Includes removal of the existing fence including supports, posts, and foundations, stripping topsoil in areas to be graded or excavated and stripping warning track material.

D. Unit Price No. 3 – Class 1 Excavation

1. In accordance with PennDOT 408 Section 203.

2. Payment is lump sum.

E. Unit Price No. 4 – Topsoil

1. In accordance with PennDOT 408 Section 803 – Includes spreading stockpiled topsoil.

2. 803.4 – Payment per Cubic Yard measured in-place.

3. Intended to include topsoil placement behind the curb.

F. Unit Price No. 5 – Rock Construction Entrance

1. In accordance with PennDOT 408 Section 849.

G. Unit Price No. 6 – Inlet Filter Bag

1. In accordance with PennDOT 408 Section 860.

H. Unit Price No. 7 – Pumped Water Filter Bag

1. In accordance with PennDOT 408 Section 855. Used as needed.

I. Unit Price No. 8 – Concrete Washout

1. In accordance with the construction plans.

UNIT PRICES 012200 - 3

J. Unit Price No. 9 – 12” Thermoplastic Pipe, Group 3

1. In accordance with PennDOT 408, Section 601.

2. 601.4 – Measurement and Payment – Class 2 excavation, surface restoration (pavement or lawn) and connections to existing and proposed inlet boxes is also incidental to this pay item.

K. Unit Price No. 10 – 8” Underdrain

1. In accordance with the Construction Plans and PennDOT 408 Section 610.

2. Includes excavation, geotextile, underdrain piping, stone, backfill, restoration and connections to adjacent piping or inlet boxes.

L. Unit Price No. 11 – Standard Inlet Box

1. In accordance with PennDOT 408, Section 605 and RC-46

M. Unit Price No. 12 – Type M Frame and Bicycle Safe Grate

1. In accordance with PennDOT 408, Section 605 and RC-46

N. Unit Price No. 13 – Nyloplast Inlets with Grates

1. In accordance with the plans and details including inlet grates.

O. Unit Price No. 14 – Temporary Seeding

1. In accordance with PennDOT 408 Section 804 – Formula E/T.

2. 804.4.a – straw mulch is incidental to this pay item

P. Unit Price No. 15 – Seeding and Soil Supplements - Permanent

1. In accordance with the technical specifications, disregard any permanent seeding specs on the plans.

2. 804.4.a- straw mulch is incidental to this pay item.

Q. Unit Price No. 16 – Dura Edge Crushed Shale Warning Track Mix

1. In accordance with the technical specifications.

2. Includes furnishing and placing new material.

3. Re-laying and installing salvaged crushed shale warning track mix is incidental.

R. Unit Price No. 17 – 12’ Chainlink Fence

1. In accordance with the plans and specifications. Includes excavation, foundations, reinforcement, concrete, and surface restoration.

2. Take concrete cylinders at a rate of 1 per 100 CY of concrete. Test cylinders and provide break information.

3. All excavated material that can’t be used on site becomes the property of the contractor.

4. Conduit support/reattachment to fence is incidental to fence construction.

S. Unit Price No. 18 – Temporary Construction Fence

1. In accordance with the plans and specifications.

T. Unit Price No. 19 – Concrete Curb

1. In accordance with the Construction Plans and PennDOT 408, Section 704.

UNIT PRICES 012200 - 4

2. All excavation and backfill is incidental.

U. Unit Price No. 20 – Install new foul poles

1. Owner to supply foul poles as depicted on the plans.

2. Contractor to remove existing poles and foundations.

3. Supply new anchors and any mounting brackets

4. Construction new foundation

5. Install foul poles

6. All excavation and backfill is incidental.

7. Misc. restoration, temporary fence removal, fence reinstallation, etc. is incidental to this pay item.

V.U. ALT1 – Batter’s Eye 40’x80’

1. Includes purchase, supply and installation of Batter’s Eye, including all components, beams, etc., excavation of foundations, construction of foundations and site restoration.

2. Take concrete cylinders at a rate of 1 per 100 CY of concrete. Test cylinders and provide break information.

W.V. ALT2 – Batter’s Eye 36’x60’

1. Includes purchase, supply and installation of Batter’s Eye, including all components, beams, etc., excavation of foundations, construction of foundations and site restoration.

2. Take concrete cylinders at a rate of 1 per 100 CY of concrete. Test cylinders and provide break information.

X.W. ALT3 – 4” Underdrain

1. In accordance with the Construction Plans and PennDOT 408 Section 610.

2. Includes excavation, geotextile, underdrain piping, stone, backfill, restoration and connections to adjacent piping or inlet boxes.

X. ALT4 – Install new foul poles

1. Owner to supply foul poles as depicted on the plans.

2. Contractor to remove existing poles – cut flush with existing concrete

3. Fill void with concrete class AA

4. Field survey to precisely site outside edge of pole even with line from home plate to first/third base.

5. Install additional concrete and dowels around existing concrete base.

6. Install anchor bolts

7. Install foul poles

8. Field survey to precisely align posts to vertical

9. All excavation and backfill is incidental.

10. Misc. restoration, temporary fence removal, fence reinstallation, etc. is incidental to this pay item.

END OF SECTION 012200

City of Williamsport 11 68 33 -1

Bowman Field Outfield Fence Replacement Athletic Field Equipment

August 28, 2025

SECTION 11 68 33 – ATHLETIC FIELD EQUIPMENT

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Provide all equipment and materials, and do all work necessary to furnish and install the athletic equipment, as indicated on the drawings and as specified herein. Athletic equipment shall include, but not be limited to:

1. Batter’s Eye with Ribbed Profile Wall Panels

2. Warning Track Surface Material

3. Foul Poles

1.2 RELATED SECTIONS

A. Examine contract documents for requirements that affect work of this section. Other specification divisions and sections that directly relate to the work of this section include, but are not limited to:

1. PennDOT 408

2. Division 31 – Earthwork; Sections: Excavation and Backfill and Establishment of Sub-Grade

Elevations

1.3 REFERENCES

A. Comply with applicable requirements of the following standards. Where these standards conflict with other specified requirements, the most restrictive requirements shall govern.

1. National Federation of State High School Associations (NFHS)

2. World Athletics (WA), Formerly International Association of Athletics Federations (IAAF)

3. National Collegiate Athletic Association (NCAA)

4. Major League Baseball (MLB)

5. American Sports Builders Association (ASBA)

6. Manufacturer’s Data and Recommended Installation Requirements

1.4 SUBMITTALS

A. Manufacturers Product Data

1. Provide manufacturers product data prior to actual field installation work, for Architects or Owners representative’s review.

B. Shop Drawings

1. Provide drawings of the manufacturers recommended installation and foundation requirements prior to actual field installation work, for Architects or Owners representative’s review.

City of Williamsport 11 68 33 -2

1.5 QUALITY ASSURANCE

A. Manufacturers warranties shall pass to the Owner and certification made that the product materials meet all applicable grade trademarks or conform to industry standards and inspection requirements.

1.6 PRODUCT DELIVERY AND STORAGE

A. Materials delivered to the site shall be examined for damage or defects in shipping. Any defects shall be noted and reported to the Owners representative. Replacements, if necessary, shall be immediately re-ordered, so as to minimize any conflict with the construction schedule. Sound materials shall be stored above ground under protective cover or indoors so as to provide proper protection.

PART 2 - PRODUCTS

2.1 40’ x 80’ SINGLE-SIDED SOLID SURFACE BATTER’S EYE WITH RIBBED PROFILE WALL PANELS

A. BASE: Batter’s Eye and Accessories as Manufactured and/or Supplied by:

1. Sportsfield Specialties, Inc.

P.O. Box 231

41155 State Highway 10

Delhi, NY 13753

p. 888-975-3343 www.sportsfieldspecialties.com

2. Or Approved Equal.

B. COMPONENTS:

1. Overall System Dimensions: 40’H x 80’W

a. Panel Height 36’ 4”

2. Vertical Structure

a. Exterior Columns:

i. W16x67 Steel I Beams

ii. Powder Coated Finish

1. Color to be selected by Owner

iii. Embedment depth as depicted on structural plans

b. Interior Columns:

i. W16x77 Steel I Beam

ii. Powder Coated Finish

1. Color to be selected by Owner

iii. Embedment depth as depicted on structural plans.

3. Horizontal Structure:

a. Top and Bottom Beams:

i. W12x26 Steel I-Beam

ii. Powder Coated Finish

City of Williamsport 11 68 33 -3

1. Color to be selected by Owner

b. Horizontal Girts:

i. 4” Square x 11ga Steel Tube

ii. Bolted to Welded Steel Angles

iii. Spacing: 4’ o.c.

iv. Powder Coated Finish

1. Color to be selected by Owner

4. Wall Panels (Front Side Only):

a. Low Ribbed Profile Exposed Fastener Metal Wall Panels

i. 36” W 26 Gauge Metal Panels

ii. Galvalume® Coated Two-Coat Fluoropolymer Finish

1. Color to be selected by Owner

iii. Panels Field Assembled with Side Laps

iv. Fastened to Horizontal Girts with Exposed Fasteners Painted to Match

Paneling

b. Top, Bottom and Side Metal Trim with Attachment Hardware Included (Front Side

Only)

5. Includes Side Wind Shield and All Necessary Assembly Hardware

6. Foundations per the structural plans.

2.1 36’ x 60’ SINGLE-SIDED SOLID SURFACE BATTER’S EYE WITH RIBBED PROFILE WALL PANELS

C. BASE: Batter’s Eye and Accessories as Manufactured and/or Supplied by:

3. Sportsfield Specialties, Inc.

P.O. Box 231

41155 State Highway 10

Delhi, NY 13753

p. 888-975-3343 www.sportsfieldspecialties.com

4. Or Approved Equal.

D. COMPONENTS:

7. Overall System Dimensions: 36’H x 60’W

a. Panel Height 32’ 4”

8. Vertical Structure

a. Exterior Columns:

i. W14x61 Steel I Beams

ii. Powder Coated Finish

1. Color to be selected by Owner

iii. Embedment depth as depicted on structural plans

b. Interior Columns:

i. W14x68 Steel I Beam

ii. Powder Coated Finish

1. Color to be selected by Owner

iii. Embedment depth as depicted on structural plans.

9. Horizontal Structure:

City of Williamsport 11 68 33 -4

a. Top and Bottom Beams:

i. W12x26 Steel I-Beam

ii. Powder Coated Finish

1. Color to be selected by Owner

b. Horizontal Girts:

i. 4” Square x 11ga Steel Tube

ii. Bolted to Welded Steel Angles

iii. Spacing: 4’ o.c.

iv. Powder Coated Finish

1. Color to be selected by Owner

10. Wall Panels (Front Side Only):

a. Low Ribbed Profile Exposed Fastener Metal Wall Panels

i. 36” W 26 Gauge Metal Panels

ii. Galvalume® Coated Two-Coat Fluoropolymer Finish

2. Color to be selected by Owner

iii. Panels Field Assembled with Side Laps

iv. Fastened to Horizontal Girts with Exposed Fasteners Painted to Match

Paneling

b. Top, Bottom and Side Metal Trim with Attachment Hardware Included (Front Side

Only)

11. Includes Side Wind Shield and All Necessary Assembly Hardware

12. Foundations per the structural plans.

2.2 DURA EDGE CRUSHED SHALE WARNING TRACK MATERIAL

A. As Manufactured and/or Supplied by:

1. Dura Edge Products, Inc.

149 South Broad Street

Grove City, PA 16127

p. 866-867-0052 info@duraedge.com www.duraedge.com

2. No equals/alternates will be accepted as this is the current material utilized by MLB for the Bowman Field warning track.

2.3 Q-FP-CUSTON 60’ FOUL POLE WITH 51’ LONG WING, BASE PLATE MOUNT

A. Foul Pole – owner supplied

A.B. Anchor bolts/hardware as shown on the plans

B. Base Plate Mounting Kit (anchor bolts and hardware) supplied by contractor

PART 3 - EXECUTION

3.1 INSTALLATION OF EQUIPMENT

City of Williamsport 11 68 33 -5

A. Batter’s Eye systems shall be installed as recommended per manufacturer's written instructions and as indicated on the drawings. Installer should have a minimum of five (5)

Batter’s Eye system installations or similar experience in the previous three (3) years.

3.2 DURA EDGE CRUSHED SHALE WARNING TRACK MATERIAL -PLACEMENT

A. Sequence of Construction:

a. Excavate/pull back existing warning track material a sufficient distance so that fence post foundations, underdrain and concrete L curb can be installed. Contractor is limited to the warning track area – temporary construction fence will limit contractor from entering the grass field.

b. If irrigation system is encountered, pull back piping to keep it out of the way.

c. Excavate for subdrainage, L curb and concrete foundations.

d. Install concrete foundations and fence posts as depicted on the plans.

e. Install concrete L curb.

f. Install geotextile, drainage pipe and drainage stone.

g. Backfill any over excavated areas.

h. Install warning track material which will be a combination of existing salvaged warning track material and new material purchased and supplied by the contractor.

B. Procedures:

a. Compact subgrade to 90-95%.

b. Install warning track material in 2-inch lifts. Compact each lift from 90-95%. Install to depths and elevations indicated.

C. Inspection

a. Warning track material must be free of dirt, mud, topsoil, stone, etc. that may result from excavation. Any warning track material that is contaminated or unpure in any way will be rejected and must be disposed of by the contractor and replaced with new material.

b. The finished surface of the warning track shall be smooth and free from visible dips, humps, bumps or other blemishes which would hinder the removal of water through positive surface drainage. Where warranted, an as-built survey shall be conducted to assure proper installation.

3.3 Q-FP-CUSTON 60’ FOUL POLE WITH 51’ LONG WING, BASE PLATE MOUNT

A. Install per manufacturer’s instructions.

END OF SECTION 116833

MATERIALS

A. FABRIC - VINYL COATED STEEL CHAIN LINK FABRIC SHALL BE FURNISHED IN ACCORDANCE WITH ASTM F-668-TYPE

2B. THE STEEL CORE WIRE SHALL BE GALVANIZED IN ACCORDANCE WITH ASTM A-641-71A. THE COLOR SHALL BE BLACK, A.1-TYPE-STANDARD INDUSTRIAL, 2"X1/8" MESH, 9-GUAGE, 0.14" CORE WIRE DIA., 1290 LB. BREAKLOAD.

B. FRAMING & FITTINGS - ALL STEEL PARTS SHALL BE HOT-DIPPED GALVANIZED AS PER ASTM, PRIOR TO VINYL COATING. THICKNESS OF VINYL COATING SHALL BE 10-14 MILS APPLIED BY FUSION BONDING.

24"

6"

72"

12'

8' SPACING O.C.

TENSION BAR

CONCRETE POST FOOTING

(TYP OF ALL POSTS)

BOTTOM SELVAGE

KNUCKLED

HOG RING

POST CAP (DOME TYPE)

ROUND END & CORNER POST

4" SCHEDULE 80

CHAIN LINK FABRIC

(TOP SELVAGE KNUCKLED)

LINE POST LOOP CAP

COILED SPRING

TENSION WIRE

LINE POST TIE

LINE POST

(ROUND OR "C")

TOP RAILTIE WIRE

CHAIN LINK FENCE - 12' HEIGHT

NOT TO SCALE

2" MESH 9-GA POLYMER COATED CHAIN

LINK FABRIC, COLOR TO BE BLACK;

KNUCKLED TOP & BOTTOM SELVAGES

KNUCKLE SELVAGE

1 5 8" TOP RAIL

1 5 8" MIDDLE RAIL

1 5 8" BOTTOM RAIL

24"

12' HEIGHT CHAINLINK

FENCE POST (TYP.)

FENCE PADDING

(INSTALLED BY OTHERS)

FENCE SECTION A-A

NOT TO SCALE

WARNING TRACK

CONCRETE PADDED FENCE POST

FOUNDATION, SEE DETAIL

NOTE:

PROVIDE 12" OVERLAP OF FABRIC

AASHTO NO. 57

COARSE AGGREGATE

8" HDPE SINGLE WALL

PERFORATED PIPE

CLASS 1

GEOTEXTILE FABRIC

6" 6"

UNDERDRAIN

NOT TO SCALE

12" MIN

COVER

FINISHED GRADE

12"

OVERLAP

8" HDPE SINGLE WALL

PERFORATED PIPE

CLASS 1

GEOTEXTILE FABRIC

12" MIN

COVER

6" WARNING

TRACK MIX (MIN.)

12"

8" EXPOSED @

BACK OF CURB

12" MIN

COVER

18"

12"

8"

24"

5% VARIES

INV: 518.19

ELEV: 521.13

VARIES

EXISTING PAVEMENT

SEE NOTE

PAVEMENT JOINT

NOT TO SCALE

REFERENCE BITUMINOUS PAVEMENT

NOTE

SAWCUT CLEAN, STRAIGHT EDGE IN EX PAVEMENT AND REMOVE

EX MATERIAL. INSTALL NEW PAVEMENT AGAINST EDGE,

FORMING A SMOOTH, FLUSH JOINT. SEAL WITH CRAFCO

ASPAHLT RUBBER TYPE 2 CRAFCO SUPERFLEX, OR EQUIVALENT.

1.5” (9.5MM) SUPERPAVE ASPHALT MIXTURE DESIGN, HMA

WEARING COURSE, PG.64-22, 0 TO 0.3 MILLION ESAL’S

4” (25MM) SUPERPAVE ASPHALT MIXTURE DESIGN, HMA

BINDING COURSE, PG.64-22, 0 TO 0.3 MILLION ESAL’S

6.0" 2A MODIFIED STONE SUBBASECOMPACTED SUBBGRADE

BITUMINOUS PAVEMENT

NOT TO SCALE

4" WIDE SAWN OR

TOOLED CONTROL JOINT,

2 12" MIN DEPTH

SEALANT, 1" DEPTH

8" WIDE PREFORMED EXPANSION

JOINT, FULL DEPTH OF CONCRETE SLAB

PROVIDE TOOLED EDGE

EXPANSION AND CONTROL JOINTS

NOT TO SCALE

NOTE:

SEE DRAWINGS AND SPECIFICATION FOR PLACEMENT OF

ISOLATION AND CONTROL JOINTS FOR CONCRETE.

CONCRETE

SUBBASE

FOUL POLES

(TO BE PROVIDED BY OWNER)

NOT TO SCALE

NOTES:

1. FIELD SURVEY IS REQUIRED TO PRECISELY ALIGN THE OUTSIDE EDGE OF THE FOUL POLE TO

THE LINE FROM HOME PLATE TO FIRST/THIRD BASE. NO DEVIATIONS WILL BE ALLOWED.

2. DETAILS FOR FOUL POLES INCLUDING FOUNDATIONS WERE DEVELOPED BY THE CITY OF

WILLIAMSPORT AND ARE NOT A DESIGN PRODUCT OF LIVIC CIVIL, LLC. ANY SEALS OR

CERTIFICATION ON THESE PLANS DO NOT INCLUDE THE FOUL POLES.

FOUL POLE FOUNDATIONS

NOT TO SCALE

EXISTING GRADE

30" DIA ±

EXISTING 40' FOUL POLE

CUT FLUSH WITH CONCRETE

FILL VOID WITH

CLASS AA CONCRETE

DEPTH

UNKNOWN

NEW 60' FOUL POLE

EXCAVATE AND POUR

12" CLASS AA CONCRETE

AROUND PERIMETER

DEPTH

UNKNOWN

1"

HEX NUTS FOR LEVELING

" E

M

BE

DM

EN

T

12" 12"

1" DIA, GRADE 8 ALL-THREAD

SECURE WITH SIMPSON STRONG TIE SET 3G EPOXY

#5 DOWELS, 12" LONG

EMBEDDED 6", 12" ON…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .