34944 Intent to Award.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- ITB - US97: MP 179. 97 - 183. 15 Wildlife Fence
- Solicitation number
- S-73000-00000076
- Issued by
- Jackson County, Oregon
About this file
This document is an Intent to Award for a wildlife fence construction project along US97 in Central Oregon. The project includes 34,000 linear feet of wildlife fence, 6 foot and 24 foot gates, and several metal deer guards of varying widths between mileposts 179.97 and 183.15. The total contract value is $588,536 and will be awarded to Central Oregon Homes. The project is being administered by the Oregon Department of Transportation and involves the jurisdictions of Deschutes County and the City of Bend.
The bid items include mobilization, traffic control, erosion control, construction surveying, clearing and grubbing, the wildlife fence itself, and the installation of the various deer guard sizes. Pricing is provided for each line item. No information is provided on any set-asides, incumbent contractors, funding sources, or renewal options.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Standard Drawings.pdf | ||
| 00000076 Amendment 1.docx | DOCX document | |
| 34944 Prelim Bid Results.xlsx | XLSX spreadsheet | |
| 34936 Preliminary Bid Tab.xlsx | XLSX spreadsheet | |
| Plans.pdf | ||
| Special Provisions.doc | DOC document | |
| Invitation to Bid~1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| S-73000-00000076 US97: MP 179.97-183.15 Wildlife Fence | ||||
| Intent to Award | Central Oregon Homes | |||
| Bid Item # | Description | Est | ||
| QTY | UNIT | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | Lump Sum | $ 55,000.000 | $ 55,000.00 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | Lump Sum | $ 27,756.000 | $ 27,756.00 |
| 3 | Erosion Control | 1 | Lump Sum | $ 5,000.000 | $ 5,000.00 |
| 4 | Construction Survey Work | 1 | Lump Sum | $ 13,000.000 | $ 13,000.00 |
| 5 | Clearing and Grubbing | 1 | Lump Sum | $ 5,000.000 | $ 5,000.00 |
| 6 | Wildlife Fence | 34,000 | Lin. Ft. | $ 8.670 | $ 294,780.00 |
| 7 | 6 Foot X 96 Inches Wildlife Fence Single Gate | 4 | Each | $ 3,000.000 | $ 12,000.00 |
| 8 | 24 Foot X 96 Inches Wildlife Fence Double Gate | 1 | Each | $ 6,000.000 | $ 6,000.00 |
| 9 | Metal Deer Guard, 18 Feet Wide | 1 | Each | $ 28,000.00 | $ 28,000.00 |
| 10 | Metal Deer Guard, 24 Feet Wide | 2 | Each | $ 33,000.00 | $ 66,000.00 |
| 11 | Metal Deer Guard, 26 Feet Wide | 2 | Each | $ 18,000.00 | $ 36,000.00 |
| 12 | Metal Deer Guard, 28 Feet Wide | 1 | Each | $ 40,000.00 | $ 40,000.00 |
| TOTAL | $ 588,536.00 |