2-RFB 26-01 Addendum 1 Roof Maintenance Repairs and Replacement for Sheriffs Office.docx

DOCX document 171 KB Posted

Attached to
Roof Replacement of Jail Pod, Maintenance, Repairs to Existing Roofs and Possible Future Roof Replacements for Sheriff's Facilities
Solicitation number
26-01
Issued by
Lanier County, Georgia

View the file

Other files

File Type Posted
1-RFB 26-01 Roof Maintenance Repairs and Replacement for Sheriff Facilities.docx DOCX document
3-Bid Tabulation.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM # 1

RFB 26-01 Roof Maintenance, Repairs and Replacement for Sheriff’s Office

This Addendum modifies the Advertisement for Request for Bid for Roof Maintenance, Repairs and Replacement for Sheriff’s Office. Unless specifically modified by this Addendum, the previously issued documents remain unchanged and in the event of a conflict between this Addendum and previously issued documents, this Addendum shall prevail.

1. When will plans be available for bidding? 2. When you state Mandatory, will this be on site requirement or remote be allowed?

All available information is in the solicitation documents.

1. Will there be posted a job budget range for bidding?

No.

1. I do not see plans or specifications. when will they be made available or is there is a separate ftp site to download them? I only see the front end and its available for download.

All available information can be downloaded from the County’s website.

1. If I am the prime and I have a gc or contractor that has all insurance and bonding requirements, do I as the prime have to have all the same required insurances and bonding as well?

Prime needs to be bonded and hold a business license/secretary of state per solicitation documents.

1. I also wanted to ask if you had any information about the current roof composition or recent core cut information? If not, is that information something that can be provided or sent out in an addendum? Or would it be possible to set up a time to come back out to the property to take a core sample so we know what we'll be working with when it comes time for tear off?

There was an on-site mandatory bid meeting for contractors to come and assess the roofs themselves.

NOTE:

Bid Bond is Exhibit L in the solicitation documents.

Performance and Payment Bond is Exhibit M in the solicitation documents.

There is no Exhibit N.