33-4050 Meade MDCOS 1X On-Site.pdf

PDF 1 MB Posted

Attached to
GOVT. SCRAP SALE: DEMILITARIZATION/MUTILATION AS CONDITION OF SALE, SCRAP RESIDUE SALE, IFB 33-4050, PHILADELPHIA, PA
Solicitation number
IFB-33-4050
Issued by

About this file

This document is an Invitation for Bid (IFB) for the sale of scrap residue derived from the demilitarization and mutilation of controlled property by the Defense Logistics Agency (DLA).

The key details are:

  • The material for sale is a GE LM500 marine gas turbine and Froude Dyometer located at Naval Surface Warfare Center Philadelphia Division, S LOT, 5001 S. Broad St. Philadelphia, PA 19112.
  • The total quantity is 326,000 lbs with a minimum guaranteed quantity of 200,000 lbs.
  • Bidders must complete the SF 114 and SF 114A forms to submit a bid as a price per unit of issue not to exceed five decimal places.
  • Bids must be received by 10/23/2024, 1:00 p.m. Eastern Standard Time.
  • A pre-award survey will be conducted on the apparent high bidder to assess responsibility, including an environmental responsibility determination and trade security control assessment.
  • The contract will be awarded to the highest responsive, responsible bidder. The purchaser will be required to demilitarize/mutilate the property and certify the process before title transfer.

View the file

Other files

File Type Posted
FAR 52.204-24.pdf PDF
SBR 2012 (Ref. Only).pdf PDF
SF114A FILLABLE.pdf PDF
FAR 52.204-25 Clause.pdf PDF
SF114.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEFENSE LOGISTICS AGENCY

DISPOSITION SERVICES

74 WASHINGTON AVENUE NORTH

BATTLE CREEK, MICHIGAN 49037-3092

INVITATION FOR BID (IFB)

FOR SALE OF

DEMILITARIZATION/MUTILATION AS CONDITION OF SALE (DCOS/MCOS) SCRAP RESIDUE

SALE

IFB 33-4050

SEALED BID

FOR

DLA Disposition Services Meade, MD

Offer Closing Date/Time: 10/23/2024, 1:00 p.m. Eastern Standard Time (EST)

Inspection Period Begins 09/23/2024, 1:00 p.m. EST By appointment only

Sales Contracting Officer: Nam Nguyen

EMAIL: Nam.Nguyen@dla.mil

PHONE: 269-961-4077

Sales Point of Contact (SPOC) to set up inspection date and time:

Mansfield Brooker, 240-319-1694, Mansfield.Brooker@dla.mil

Andrew Walls, 410-874-6048, Andrew.Walls@dla.mil mailto:Mansfield.Brooker@dla.mil mailto:Andrew.Walls@dla.mil

A INTRODUCTION

A.1 Base Access Requirements:

A.2 Useful Websites:

A.3 Item Description:

A.4 Table 1 IFB Item Number Details:

A.5 Table 2: CLIN, Material, SCL, Descriptions:

A.6 Packing:

A.7 Inspection:

A.8 Loading and Removal:

B TERMS AND CONDITIONS OF SALE

B.1 FAR Provision 52.204-24:

B.2 FAR Provision 52.204-25:

B.3 Training B.4 Demilitarization/Mutilation Operations:

B.5 Equipment:

B.6 Meetings:

B.7 Personal Protective Equipment (PPE):

B.8 Inventories:

B.9 Certifier/Verifier:

B.10 Demilitarization/Mutilation Timeframe:

B.11 Military Markings:

B.12 Title:

B.13 Hazards:

B.14 Spill Responsibility:

C SALE BY REFERENCE (SBR)

C.1 SBR Part 1:

C.2 SBR Part 2:

C.3 SBR Part 3:

C.4 SBR Part 4:

C.5 SBR Part 5:

C.6 SBR Part 6:

C.7 SBR Part 7:

C.8 SBR Part 8:

C.9 SBR Part 9:

C.10 SBR Part 10:

D BID EVALUATION AND CONTRACT AWARD

D.1 Bidding Process:

D.2 Identification of Sales Purchaser:

D.3 How to Bid:

D.4 A Responsive Bid:

D.5 When to Send Bid:

D.6 How to Modify/Cancel Bid:

D.7 Bid Evaluation:

D.8 Ineligible Bidder:

D.9 Pre-Award Survey:

D.9.1 Environmental Responsibility Determination (ERD):

D.10 Necessary Licenses, Permits and Certifications Shall be Reviewed:

D.11 Contract Award:

D.12 Start Work Meeting:

E PARTIES TO THE CONTRACT

E.1 Purchaser Information:

E.2 Transfer and Hypothecation:

E.3 Contract of Sale:

E.4 Authority of Sales Contracting Officer (SCO):

E.5 Authority of Sales Point of Contact (SPOC):

F CONTRACT FINANCIAL RETENTION & INSURANCE AND BOND REQUIREMENTS

F.1 Payment:

F.2 Insurance and Bond Contract Requirements:

G CONTRACT PERFORMANCE

G.1 Performance Period:

G.2 Regulatory Compliance:

G.3 Environmental and Safety Notice:

G.4 Termination for Default:

G.5 Records:

H PAYMENTS

H.1 The Billing Cycle:

H.2 Types of Acceptable Payments:

H.3 Payment Confirmation:

I AUTHORIZED AND UNAUTHORIZED MATERIAL

I.1 Classified Material:

I.2 Material Potentially Presenting an Explosive Hazard (MPPEH):

I.3 Radioactive Property:

I.4 Hazardous Property:

I.5 Notice of Default/Cure Notice:

I.6 Response to Notice:

J COMPLIANCE WITH GOVERNMENT REGULATIONS

J.1 Bureau of Industry and Security (BIS):

J.2 Disposition and Use of Property:

K PURCHASER RESPONSIBILITIES

K.1 Scrap Yard Activity:

K.2 Weighing:

K.3 Letter of Authorization (LOA):

K.4 Purchaser Awareness of the Agency’s Environmental Management System (EMS):

K.5 Purchaser will not be allowed to sell material at Agency locations:

K.6 Purchaser use of sub-contractors:

L GOVERNMENT FURNISHED EQUIPMENT (GFE) & PURCHASER OWNED EQUIPMENT

L.1 Material Handling Equipment (MHE):

L.2 Requirement for Purchaser to use Purchaser owned MHE:

L.3 Government Furnished Equipment (GFE):

M CONTRACT COMPLIANCE, AUDITS AND REVIEWS

M.1 Compliance with Applicable Laws and Regulations:

M.2 Duties of Care and Loyalty:

M.3 Prohibited Activities:

M.4 Purchaser’s Cooperation is Investigations/Audits/Compliance Reviews:

M.5 Purchaser’s Responsibility for Independent Audit at Government’s Request:

M.6 Purchaser Record Retention:

M.7 Inspection of Records and Workplace by Government:

M.8 Purpose and Content of Compliance Audits, Reviews and Further Reviews:

M.9 Methods and Procedures for Compliance Reviews:

M.10 Further Reviews:

M.11 Compliance Notification:

M.12 Costs of Oversight:

M.13 Contracts with Third Parties:

N DISPUTES AND CLAIMS

N.1 Disputes:

N.2 Alternative Dispute Resolution (ADR):

O MISCELLANEOUS PROVISIONS

O.1 Binding Effect:

O.2 Notices:

O.3 Severability:

O.4 Headings:

O.5 Survival:

O.6 Waiver:

O.7 Force Majeure:

O.8 Use of the Agency Name and Public Communications:

O.9 Tense and Gender:

O.10 Entire Agreement and Modification:

O.11 Computation of Time:

O.12 Electronic Communication:

O.13 No Reimbursements:

O.14 Market, Resale and/or Export:

P GOVERNMENT REQUIRED REPORTS

P.1 Government Use of Purchaser Reported Information:

Q ADDITIONAL CONTRACT ADVISEMENTS

Q.1 Public Law Pertaining to Location Operations:

Q.2 Public Law Pertaining to Material:

Q.3 Resource Conservation and Recovery Act (RCRA) Notice:

Q.4 Chemical Agent Resistant Coating (CARC) Paint:

Q.5 Refrigerant:

Q.6 Pollution Prevention and Right-to-Know Information Definitions (As used in this clause):

R DEFINITIONS

A INTRODUCTION

The Defense Logistics Agency (DLA) Disposition Services (hereinafter, the “Agency”) is offering for sale, scrap residue derived from the Mutilation and Demilitarization of controlled property. A Mutilation/Demilitarization Condition of Sale (MCOS/DCOS) contract requires property to be demilitarized or mutilated and certified prior to title transfer. A Government DEMIL verifier will oversee processing of property. This contract will consist of processing materials on-site Government facilities. This contract will be for a 45-calendar days period of performance.

A.1 Base Access Requirements:

All locations where property is located may have strict rules that may prohibit access to some individuals. To access our facilities, an apparent high bidder or their agent shall be required to obtain base access through the host installation. The local location will be able to provide information on how to obtain base access. Purchaser is solely responsible for determining installation access requirements and complying accordingly. If necessary, the SCO or SPOC can confirm that Purchaser is performing requirements under this IFB and the resulting contract.

Applicant must show vehicle registration, proof of current vehicle insurance and identification that meets the requirements of the REAL ID ACT of 2005 to register for enrollment in the Defense Biometric Identification System

(DBIDS).

Purchaser is responsible to obtain all base badging for laborers and transportation drivers with coordination and assistance from the Government. All personnel accessing the base must have state-approved identification or state-approved appropriate driver’s licenses and be free of any warrants. The base will deny access to personnel with warrants. Base access requirements are subject to change. It is the Purchaser’s responsibility to be aware of all changes and comply as needed. (Purchaser will provide a list of personnel who will work on base prior to start of work).

A.2 Useful Websites:

DLA Disposition Services: https://www.dla.mil/DispositionServices.aspx DLA Auction Site: https://www.sales.dla.mil/dlab2b/init.do System for Award Management: https://sam.gov/ Bureau of Industry and Security: https://www.bis.doc.gov/ U.S. Department of the Treasury: https://home.treasury.gov/ Consolidated Screening List Search Engine: https://legacy.export.gov/csl-search

The following is for reference only and does not indicate endorsement of the information provided.

Commercial Scale Locator: https://catscale.com/cat-scale-locator/

A.3 Item Description:

The Agency expects the Purchaser to perform all requirements under this contract at the bid price provided by the Purchaser.

GE LM500 marine gas turbine and Froude Dyometer consisting of metallic and non-metallic scrap located at Naval Surface Warfare Center Philadelphia Division, S LOT, 5001 S. Broad St. Philadelphia, PA 19112. GE LM500 marine gas turbine is 12ft wide by 30ft long by 12ft height at approximately 150,000 lbs. Froude Dyometer is 14ft wide by 15ft long by 20ft height at approximately 176,000 lbs.

https://www.dla.mil/DispositionServices.aspx https://www.sales.dla.mil/dlab2b/init.do https://sam.gov/ https://www.bis.doc.gov/ https://home.treasury.gov/ https://legacy.export.gov/csl-search https://catscale.com/cat-scale-locator/

The pictures are of items to be included in this sale but are for illustrative purpose only and may not be a current representation of item (s) for sale, site location (s), or other images displayed in the pictures. Bidders are highly encouraged to perform a pre-bid site inspection to make an intelligent bid.

All potential Bidders are advised to read all terms and conditions of this IFB prior to submitting their bids to ensure they have a complete and full understanding of all requirements under this contract for sale. The Purchaser is cautioned that some requirements for information are required before the start of work on this contract. The Purchaser agrees to provide all services necessary for the contract in accordance with all Federal, state, local laws, and regulations and in accordance with the terms of this contract. All terms in this IFB will also apply to Purchaser sub-contractor(s).

Government guarantees to issue the Purchaser a minimum total weight equal to the “Minimum Guaranteed QTY (LBS.)” listed in Table 1.

A.4 Table 1 IFB Item Number Details:

Item Material Total QTY

(LBS.)

Minimum Guaranteed

QTY (LBS.)

Maximum Allowed

QTY (LBS.)

10 DS000MUTB 326,000 200,000 500,000

A.5 Table 2: CLIN, Material, SCL, Descriptions:

Table 2 is material description(s) for the Contract Line-Item Number (CLIN) for the material listed in Table 1.

A.6 Packing:

Property is a large item and not packaged. All disposal costs, recycling of containers, pallets and dunnage material are the responsibility of the Purchaser.

A.7 Inspection:

Monday-Friday 8:00a.m. – 2:00p.m. Eastern Standard Time (EST) excluding federally recognized holidays.

Both physical and/or photograph inspection is by appointment only and 24-hour notice required. Contact Sales Point of Contact for inspection.

Bidders are highly encouraged to physical inspect property and site requirements prior to submitting their bid.

A.8 Loading and Removal:

Monday-Friday 7:00a.m. – 3:30p.m. Eastern Standard Time (EST) excluding federally recognized holidays.

Purchaser will do all the loading without Government’s assistance. Purchaser is required to have on-hand Storage Bins/Roll off containers to collect scrap and residue resulting from the loading, removal, and/or mutilation operations. Scrap and residue will not be accumulated on the ground.

Property is located at Naval Surface Warfare Center Philadelphia Division, S LOT, 5001 S. Broad St. Philadelphia, PA 19112.

Scale is not on-site. It is located at TA Paulsboro I-295 Exit 18 Paulsboro, NJ 08066. Approximately 17 miles from property location. Total weight cannot exceed 80k due to local bridge weight limitation.

B TERMS AND CONDITIONS OF SALE

Certain contents and provisions of this IFB, including Appendices, Attachments and Schedules, are described in general.

B.1 FAR Provision 52.204-24:

FAR Provision 52.204-24 is applicable.

PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO

SURVEILLANCE SERVICES OR EQUIPMENT (AUG 2020)

Full clause text included in attachment. The provision at FAR 52.204-24 requires an offeror to represent, on an Offer-by-offer basis, whether it will or will not provide any “covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation.”

The Representation that must be signed will be sent at the same time the Statement of Intent (SOI) is sent to apparent high bidder as part of the pre-award process.

Full clause text included in attachment.

B.2 FAR Provision 52.204-25:

FAR Provision 52.204-25 is applicable.

FAR Provision 52.204-25 titled, “Prohibition on Contracting for Certain Telecommunications and Video

CLIN MATERIAL SCL DESCRIPTION

10 DS000MUTB MUT GE LM500 marine gas turbine and Froude Dyometer

Surveillance Services or Equipment” is incorporated by reference from the Federal Acquisition Regulation.

https://www.acquisition.gov/far/52.204-25

Full clause text included in attachment.

B.3 Training During the pre-award process the SCO will provide the Purchaser with “DEMIL Certifier” training material (MS PowerPoint or PDF version). Purchaser will retain the training certificate(s) and make them available to the Government within twenty-four (24) hours upon request. Purchaser must complete training certificate and submit an appointment letter on company letterhead in accordance with (IAW) DoDM 4160.28 Vol 2 with the Certifier(s) name and signature to the SCO before work can begin.

B.4 Demilitarization/Mutilation Operations:

Agency Verifier(s) must be present for all Demilitarization/Mutilation operations. If the Agency Verifier is unavailable for any reason, Demilitarization/Mutilation operations are to be shut down until the Verifier(s) return.

Purchaser is responsible for obtaining and providing all required permits to accomplish Demilitarization/Mutilation processing and transportation. All conveyance will display applicable Department of Transportation (DOT) placards. If an oversized vehicle or load is required, site will assist by providing a POC for base permits.

Purchaser will not be provided with permanent indoor or outdoor storage space for property or equipment (including material handling equipment (MHE)). Outdoor temporary storage may be made available as the need arises to ensure DEMIL operations and property flow are not impacted. Only the Agency can authorize the temporary storage space and the Purchaser must request the space in writing to the SCO and SPOC.

Purchaser is required to Demilitarize/Mutilate all property streams. No parts harvesting is authorized.

Property needs to be cut no larger than 4ft x 4ft x 4ft pieces.

If operation hazards are discovered during loading or Demilitarization/Mutilation operations, all work will cease immediately. SCO and DLA Operations will be notified by the SPOC. Operations will not resume until cleared by the SCO and DLA Operations.

Method and degree of Demilitarization recommended are in the best interest of the U.S. and according to DoDM

4160.28 Vol 2. The use of precision tools of ANY kind, including precision cutting tools, will not be permitted during the Demilitarization/Mutilation of this property.

B.5 Equipment:

Purchaser will supply all equipment and personnel to accomplish the Demilitarization of all property and associated parts/material. Additionally, Purchaser will provide necessary equipment to react to leaks, spills, and clean-up of work area at the end of each day.

Equipment may include, but is not limited, to a shear, scrap knuckle boom, shredder, torch machine, plasma cutter and Personal Protective Equipment.

Purchaser is required to have on-hand Storage Bins/Roll off containers to collect scrap and residue resulting from the loading, removal, segregation and/or Demilitarization/Mutilation operations. Scrap and residue shall not be accumulated on the ground. Purchaser must return the site to its original condition after property has been fully militated and removed. Photos of the cutting area is required before cutting begins and after cutting has completed.

Purchaser, SPOC, and generator will inspect the site before work start and after work completed.

B.6 Meetings:

Purchaser’s Certifier and the Agency’s Verifier will conduct end of week meeting to coordinate/determine work schedule for the following week.

https://www.acquisition.gov/far/52.204-25

B.7 Personal Protective Equipment (PPE):

According to 29 Code of Federal Regulation (CFR) 1910.132-140, Purchaser is hereby informed of the requirement to supply/provide Purchaser employees safety gear needed to protect from lethal projectiles, hot metal, sparks, and flames. The act of Demilitarization/Mutilation to render the property to the point of scrap can be extremely dangerous and adequate safeguards must be adhered to by Purchaser employees performing the Demilitarization/Mutilation on expended cartridge casing and associated dangerous property.

B.8 Inventories:

Joint inventory of property will be conducted by the Certifier and Verifier before property is Demilitarized/Mutilated.

All weighing of the processed material, dunnage and packaging must be witnessed by DLA personnel and issued on a 1367, weight ticket and MRO. Purchaser and DLA personnel shall be required to retain a copy for their contract records.

B.9 Certifier/Verifier:

Purchaser Certifier will be present and watch or perform 100% of material being mutilated. Government Verifier will be present and watch 100% of the process. Verifier will determine if property has been adequately Demilitarized/Mutilated. Any material not demilitarized/mutilated to the point of scrap will be further processed until proper destruction is accomplished.

B.10 Demilitarization/Mutilation Timeframe:

All Demilitarization performance will be completed prior to residue removal from Government site. The receiving process begins once the DLA Disposition Services Verifier and Certifier complete the Kind Count (KC) process and the property has been turned over to the Purchaser for processing. Demilitarization Certificates will be completed for each item when verifier has confirmed processing has been completed according to Government requirements.

B.11 Military Markings:

All military markings and data plates are to be destroyed during the Demilitarization process. All Technical Data is considered Demilitarization required and must not be thrown away as dunnage. Demilitarization of Technical Data, Drawings, CD’s, Manuals, etc. must be destroyed by burning, cross-cut shredding or pulping according to Government regulations.

B.12 Title:

Title will pass to Purchaser when the Demilitarization/Mutilation has been completed and the Certificate of Demilitarization/Mutilation has been signed by both the Purchaser Certifier and the Agency Verifier and the 1367s is signed by both the Purchaser Certifier and the Agency Verifier.

B.13 Hazards:

Property may contain residual hazardous materials, batteries, Petroleum, Oil, Lubricants (POL), hydraulic oils, coolant, fuels, washer fluids, etc. Accumulations during the processing will be the Purchaser’s responsibility to recover, store, and dispose of according to Federal, state, and local requirements.

B.14 Spill Responsibility:

The Purchaser is solely responsible for clean-up and disposal of all spills or leaks according to 40 CFR Part 112 during the loading and or Demilitarization/Mutilation operations of this contract that occur because of, or are contributed to, by the actions of its agents, employees, or Sub-Contractors, at no cost to the Government. Spill response will be performed by the Purchaser according to local or host installation spill response procedures. The Purchaser shall have all necessary spill response kits, equipment and supplies pre-positioned in-case of spills that may occur during these operations.

C SALE BY REFERENCE (SBR)

The following general information, instructions and special conditions of sales contained in DLA Disposition Services pamphlet entitled the “Sale by Reference Instructions, Terms and Conditions Applicable to Department of Defense (DoD) Personal Property Offered for Sale by DLA Disposition Services”, published July 2012, are hereby incorporated by reference and become a part of this IFB and any contract resulting from acceptance of a bid submitted pursuant to this IFB as fully as though such instructions, terms and conditions had been specifically set forth herein:

The Terms and Conditions of this IFB supersede the Sales by Reference wherever conflicted.

C.1 SBR Part 1:

General Information and Instructions: All conditions apply except 2, 5, 8, 12, and 13.

C.2 SBR Part 2:

Sale of Government Property General Sale Terms and Conditions: All conditions apply except 12, 13(c), 28, 29.

Modified Paragraph 33. DISPUTES is changed to read “Any contract awarded as a result of this sale is subject to the Contract Disputes Act 1978 (41 U.S.C. 7101-7109)”

C.3 SBR Part 3:

Sale of Government Property Special Sealed Bid Conditions: Does not apply.

C.4 SBR Part 4:

Sale of Government Property Special Sealed - Term Conditions: All articles apply except 5.

C.5 SBR Part 5:

Additional Special Circumstance Conditions - Miscellaneous: All articles apply except: G.

Article D. Paragraph D(a) is amended to: The Purchaser shall, at no expense to the Government and prior to contract award, will confirm with the Sales Contracting Officer the following Certificates of Insurance will be effective throughout the term of the contract or any extensions thereof.

C.6 SBR Part 6:

Additional Special Circumstance Conditions - Demilitarization and Mutilation: All articles apply except:

Article B, H and I.

C.7 SBR Part 7:

SALE BY REFERENCE PART 7: Additional Special Circumstance Conditions - Hazardous and Dangerous Property: Only articles E and S apply.

C.8 SBR Part 8:

Additional Special Circumstance Conditions - Foreign Excess Personal Property: Does not apply.

C.9 SBR Part 9:

Special Spot Bid Conditions of Sale of Government Property: Does not apply.

C.10 SBR Part 10:

Sale of Government Property Special Auction Conditions: Does not apply.

D BID EVALUATION AND CONTRACT AWARD

D.1 Bidding Process:

The Purchaser’s bid shall consist of an amount per unit of issue specified in U.S. currency. Prospective bidders should be aware of certain risk factors that could affect a bidder’s assessment of this contract and the calculations supporting the resulting bid. Under no circumstances is the Agency or the Government responsible for any assumptions, planning factors, or decisions the Purchaser made related to determining their high bid. This is a firm fixed price contract where the bid price is expressed in U.S. currency specified by the bidder, per unit of issue.

The Purchaser will perform all the requirements under this contract at the bid price submitted by the Purchaser. At no time shall the Government pay the Purchaser to take material offered. There shall be no reimbursement to the Purchaser under this contract except for the limited circumstances related to reimbursement of actual expenses incurred for return of property directed by the Government. The Government is not responsible for any indirect, inconsequential, or completeness (through assumption of sales value, act, or omission of factors) of expenses related to performance under this contract. The measure of the Government’s liability, in any case where liability of the Government to the Purchaser has been established, shall not exceed refund of such portion of the purchase price as the Government may have received.

D.2 Identification of Sales Purchaser:

Bidders should take care to ensure that their bid submission indicates whether they are submitting the bid as an authorized representative of a legal entity such as a corporation or limited liability company, or in their individual capacity or as owner of a sole proprietorship. The legal entity designated as the bidder on the SF 114 is the entity to whom the contract will be awarded upon receiving an affirmative responsibility assessment. Individuals or companies may use subsidiaries, affiliates or partners in a joint venture as subcontractors with SCO approval as per the contract terms (however such entities may also require an ERD) but may not substitute such entities as a party to the DLA sales contract. AHBs should ensure the SOI and other pre-award documentation identify any subcontractors that will be performing removals or processing materials on its behalf so that the appropriate reviews may be conducted.

D.3 How to Bid:

Bidders shall use the following documents provided with this IFB to submit a bid: the SF114 and SF114A. Bidder shall enter bid as a price per unit of issue not to exceed five (5) decimal places (example 0.01005). Minimum bid is $0.00001 per unit of issue. Multiply your bid price by the quantity indicated in the “Total QTY” column advertised to calculate your extended bid amount.

The highest priced cumulative bid will be determined by each bidder’s total contract price identified in the “total amount” on the SF114. “Total Amount” block on the SF 114 will be equal to the cumulative total from all CLINs from column “Total Price Bid” on the SF 114A.

The bidder with the highest “TOTAL AMOUNT” bid will be considered the apparent high bidder and will be vetted prior to award in accordance with provisions in Section D below. It is expected that the awarded company will remove all the items in this IFB or none of the items in this IFB. The awarded company must possess all appropriate license for all items or have sub-contractors with appropriate licenses to remove all Items. Award will not be made to a bidder who demonstrates a capability to remove some, but not all, of the items listed in the IFB.

For illustrative purposes, if the four items advertised for sale in the IFB are in pounds, CLIN 1- 500,000 lbs., CLIN 2- 1,000,000 lbs., CLIN 3- 2,500,000 lbs., and CLIN 4- 150,000 lbs. Bidder A bids- CLIN 1 $0.10, CLIN 2 $0.02, CLIN 3- $0.02, CLIN 4 $0.20. “Total Priced Bid” on Example 1 shows Bidder A’s total bid price per CLIN.

Example 2 shows Bidder A’s “Total Amount” equals $150,000 for all CLINs awarded.

Do not email bids or call-in bids directly to the SCO. Email bid to: DRMSSALESBIDS@DLA.MIL mailto:DRMSSALESBIDS@DLA.MIL

EXAMPLE 1: SF 114A

EXAMPLE 2: SF 114

D.4 A Responsive Bid:

Complies with the terms and conditions of the sales offering and satisfies the requirements as to the method and timeliness of the submission. Only responsive bids may be considered for award. A responsive bid submission shall contain at a minimum:

• SF114 completed and signed.

• SF114A

• The bid must remain valid ninety (90) calendar days from the bid opening unless otherwise modified or cancelled.

D.5 When to Send Bid:

Bids must be in the possession of the Agency’s Public Sales Contracting Division by the offer closing date and time specified in this IFB. If the bid is not submitted on time, it shall be considered non-responsive. Late rules are outlined in FAR 52.212-1(f). Pay particular attention to the provisions that relate to the timing of e-mail submissions.

D.6 How to Modify/Cancel Bid:

In addition to SBR Part 4, Paragraphs 3 and 4, by submitting a new bid in the same manner as the previous bid.

Separately, without disclosing bid amounts, notify the SCO of the modification. To cancel a bid, submit a zero (0) bid in the same manner as the original bid. Notify the SCO of the bid cancellation (specify date, time and method of bid submission).

D.7 Bid Evaluation:

A responsible bidder is one that has the necessary organization, experience, financial resources, accounting process, operational controls, technical equipment and facilities, or the ability to obtain them, to perform the requirements of the sales contract, has no disqualifying factors (i.e., is not suspended, debarred or an ineligible transferee) and able to pass the Agency’s vetting process. A responsive bid is one that has complied with all instructions for properly submitting a bid. Submitting the highest bid price does not convey any special right nor does it imply that the Purchaser shall be the primary removal company or exclusively allowed to remove throughout the term of this contract. The Government reserves the right to reject any bids that are not in the best interest of the Government. The general standards in FAR Part 9 on contractor responsibility determinations that are applicable to procurement contracts are not directly applicable to sales contracts awarded under 40 U.S. Code § 545 but may be considered by the Sales Contracting Officer in evaluating bidder responsibility.

The Government intends that a single award will be made to a responsible bidder with the highest priced responsive bid inclusive of all lines unless a determination is made to reject the bid under 41 CFR § 102-38.205. For illustrative purposes, if Bidder A’s bid submission cumulative total submits a bid for $150,000.00 “Total Amount,” and if Bidder B’s bid submission cumulative total submits a bid for $160,000.00 “Total Amount,” then Bidder B is the apparent high bidder since he/she would have the highest total amount priced responsive bid.

D.8 Ineligible Bidder:

Bidder will not be eligible for award if they are:

• Officially indebted to the Government.

• Excluded from Federal programs by the General Services Administration as identified in the System for Award

Management at https://sam.gov/.

• Subject to denial, suspension, debarment, or other sanctions pursuant to export control and related laws, regulations, or orders administered by the DOS, DOC, DHS, or USTD. The DOS, DOC, DHS, and USTD name these entities, individuals, and countries in the Federal Register and at the following website: Consolidated Screening List Search Engine (https://legacy.export.gov/csl-search).

D.9 Pre-Award Survey:

The Agency will conduct a Pre-Award survey of only the Apparent High Bidder (AHB). The SCO will provide notification that you are the AHB.

The End Use Certificate (EUC) DLA Form 1822, Statement of Intent (SOI) DLA Form 2536, FAR Clause, and Certifier training will be included in the notification. A Trade Security Contract Assessment will be made by Agency personnel. The SOI must have parts 1-6 completed and signed. Complete the EUC according to the instructions provided and sign.

The apparent high bidder shall be required to provide detailed information on every storage location the apparent high bidder intends to use. The pre-award survey may be conducted at the apparent high bidder’s facility(ies), or other location(s) as deemed necessary by the Agency and may include but is not limited to a review of the apparent high bidder’s facilities and equipment, financial capability or disclosure of the apparent high bidder’s financial condition, quality assurance, safety, environmental responsibility, and transportation. The apparent high bidder is advised that accomplishment of a pre-award survey or furnishing documents to the Agency in support of the pre-award survey is part of the assessment of the bidder’s responsibility and is not a guarantee the bidder will receive award of a contract. The SCO may rely upon information obtained in the pre-award survey in making the assessment of the bidder’s present responsibility.

Once notified that you are the apparent high bidder, you will have five (5) business days to complete and return to the SCO all documents provided in the AHB Notification. Be advised that the Pre-Award survey and providing documents to the Government is part of the evaluation to determine responsibility and is not a guarantee of contract award.

Pre-Award Survey will include but is not limited to the following:

https://sam.gov/

a. Pass a responsibility check conducted through the Consolidated Screening List (CSL) search; however, this does not limit the requirements to be deemed responsible in accordance with FAR Part 9.

b. An Environmental Responsibility Determination (ERD) will be conducted by Agency personnel.

c. A Trade Security Control Assessment will be made by agency personnel.

d. Necessary licenses, permits and certifications will be reviewed.

e. Validate FAR Provision 52.204-24 is marked and signed.

f. Complete and return the End Use Certificate (EUC), DLA Form 1822 to the SCO.

g. Provide Demilitarization/Mutilation Certifier appointment letters to the SCO.

If at any point the Agency determines the bidder that submitted the apparent high, responsive bid cannot be found responsible, the next highest bidder will be assessed in the same pre-award survey process. This same process of vetting the next highest responsive bidder may continue, until a responsive bidder is identified and is determined to be responsible.

D.9.1 Environmental Responsibility Determination (ERD):

The Environmental Support Branch of Disposition Services will conduct an ERD on sale destinations to verify if the DoD purchased property will be managed in accordance with the Invitation for Bid, Statement of Intent, Federal, state, and local regulations. All downstream facilities receiving Government property to be processed shall be listed in the Statement of Intent. Downstream recipients of Government property which has already been processed need not be listed.

ERDs typically take up to ten (10) business days to complete. Any findings annotated by the Government during an ERD must be corrected prior to a proposed destination/facility’s use. Purchaser is not authorized to process Government material at a site other than those listed on the SOI.

D.10 Necessary Licenses, Permits and Certifications Shall be Reviewed:

Prior to the award of a contract, the Agency shall determine whether the potential Purchaser has the necessary permits/licenses, experience, organization, and technical qualifications (either through its own facilities or facilities of a sub-contractor) to perform the work specified in this contract and can comply with the applicable Federal, state, and local laws, ordinances, and regulations.

D.11 Contract Award:

The SCO shall determine if each bid is responsive prior to award of the contract. The contract shall be awarded to the highest responsive bid submitted by a responsible bidder. In the event of termination of the original Purchaser, the SCO may award the contract to the next highest responsive, responsible bidder if bids have not expired, and such award is otherwise determined to be in the Government's best interest.

Under 41 CFR § 102-38.205, the Agency reserves the right to accept or reject any or all bids. The Agency may reject any or all bids when such action is advantageous to the Government, or when it is in the public interest to do so.

When you have successfully completed the pre-award assessment as the apparent high bidder, you will receive a Statement indicating the amount of payment due. Submit payment within three business days of the Statement (An extension of up to ten (10) business days may be authorized by the SCO upon written request by the AHB that is submitted before the initial three business day suspense).

When payment is posted and confirmed by the SCO; and all other vetting has been completed, a Start of Work meeting will be scheduled.

D.12 Start Work Meeting:

The purpose of the conference is to ensure the Purchaser fully understands the terms and conditions of this contract.

The Agency shall determine the method, date, time, and location of the start of work meeting. The Purchaser is responsible for any cost incurred by their organization and staff. The Government shall not provide any compensation for costs incurred to attend meetings. At the conclusion of this meeting the official signed Notice of Award will be sent to the Purchaser and SPOC. After the start of work meeting, property is authorized for release.

E PARTIES TO THE CONTRACT

E.1 Purchaser Information:

Within ten (10) calendar days of the date of contract award, the Purchaser shall provide the Agency the following information: Designation of key persons, to include their full name, title, telephone number, email address and a synopsis of their duties under the contract. Purchaser shall provide the SCO notification of any changes to the above within ten (10) calendar days of the change.

E.2 Transfer and Hypothecation:

General Prohibition - Except as specifically provided herein or specifically approved by the Agency in writing, the Purchaser shall not directly or indirectly sell, transfer, assign, pledge, offer as collateral or otherwise hypothecate all or any part of its rights or obligations under the contract.

Attempted Transfer - Any attempted transfer in violation of the provisions of this Article shall be invalid and shall constitute a material breach of this contract.

E.3 Contract of Sale:

Relationship of Parties - This contract is an agreement for the sale of the material by the Agency as seller to the Purchaser. Purchaser and the Agency expressly disavow the creation of any other relationship, including without limitation principal-agent, master-servant, employer-employee, general or limited partnership, or joint venture, between the Agency and the Purchaser.

Parties to the Contract: The parties to this contract are the Agency and the Purchaser.

E.4 Authority of Sales Contracting Officer (SCO):

On behalf of the Agency, the SCO has the authority to represent the Agency and to commit the Agency to take such actions as permitted or required and to extend or waive timing requirements or deadlines as may reasonably be required under the performance of this contract. The exclusive representative of the Agency for all purposes under this contract is the SCO, and all notices, demands, requests, consents, approvals, declarations, reports and other communications to the Agency from the Purchaser shall be deemed invalid unless addressed to the SCO.

Communications from the Purchaser to anyone other than an SCO shall not be deemed received by the Agency.

E.5 Authority of Sales Point of Contact (SPOC):

The SCO designates the SPOC to provide direct oversight of the Purchaser and/or their agents to ensure they meet the terms and conditions of the contract. The SPOC does not have the authority to make binding contractual obligations, such as adding, deleting, or modifying terms and provisions in this IFB. All changes or modifications to contractual provisions in this IFB must be approved in advance by the SCO.

F CONTRACT FINANCIAL RETENTION & INSURANCE AND BOND

REQUIREMENTS

F.1 Payment:

This is a one-time sale. Full payment for must be received prior to the removal of any property. Credit or debit will be adjusted depending on actual quantity removed.

F.2 Insurance and Bond Contract Requirements:

Purchaser shall obtain the minimum coverage specified unless the Agency approves a variance from such minimum coverage. Purchaser shall obtain and maintain the insurance and bond requirements throughout the performance period.

G CONTRACT PERFORMANCE

G.1 Performance Period:

The Purchaser will have 45 calendar days to remove the material specified in this IFB. The performance period start date will be agreed upon at the Start of Work (SOW) meeting. That date must be within 15 calendar days from the SOW meeting’s date. Once the performance period date is determined at the SOW, any changes must be agreed both by the Government and Purchaser in writing. There are no extensions available. The SCO may extend the removal period for extenuating circumstances. Prior to the end of the removal period, a written request for extension must be received from the Purchaser detailing the circumstances that delayed the removal.

G.2 Regulatory Compliance:

The Purchaser shall assume full responsibility and liability for compliance with all applicable Federal, state, local codes and DoD regulations pertaining to the health and safety of personnel and environmental management during the execution and loading operations. All work shall be completed and performed IAW the best practices of the trade and in compliance with all- applicable Federal, state, local codes and IAW regulations.

Purchaser shall also comply with all Host facility Safety, Environmental and Security requirements.

Purchaser shall comply with all local, state and Federal Department of Transportation rules and regulations while transporting scrap materials on post and to its ultimate destination.

Anticipated Regulatory Changes: Performance under any contract resulting from this solicitation must follow all local, state, and federal laws and regulations. Accordingly, it is the responsibility of the offeror to ensure that all such laws and regulations are considered in the preparation of its proposal. Such consideration should include not only relevant laws and regulations currently in effect, but also revisions there to for which public notice has been given that may reasonably be anticipated to be effective during the life of the contract.

G.3 Environmental and Safety Notice:

It is the responsibility of the Purchaser to ensure that the ultimate end use of the property is performed in an environmentally compliant manner. As such, prior to the award of any hazardous item, each high bidder’s premises and/or the intended disposal facility may be subject to an on-site inspection by Government representative. All Bidders/Purchasers are advised that they must comply with all applicable Federal, state, and local laws, ordinances, regulations, etc. with respect to human safety and the environment during the processing, use, or disposal of material purchased from the DoD.

G.4 Termination for Default:

Termination shall be effective immediately upon written notice by the government to the Purchaser (breaching party) served upon or after the date of such decision. If the Purchaser is terminated for default, the Purchaser is put on notice that this acts as a Sales Contracting Officer’s Final Decision (SCOFD), and the Purchaser’s appeal rights if incidentally not included within the termination for default letter, then the Purchaser has been placed on notice of their appeals right that commences the time the Purchaser has to appeal the SCOFD because this SBR is incorporated into the Invitation for Bid.

Appeal Rights - This is the final decision of the Contracting Officer. You may appeal this decision to the Armed Services Board of Contract Appeals (ASBCA). If you decide to appeal, you must, within ninety (90) days from the date you receive this decision, mail, or otherwise furnish written notice to the ASBCA and provide a copy to the Contracting Officer from whose decision the appeal is taken.

The notice shall indicate that an appeal is intended, reference this decision, and identity the contract(s) by number.

With regard to appeals to the agency board of contract appeals, you may, solely at your election, proceed under the board’s small claim procedure for claims of $50,000 or less or its accelerated procedure for claims of $100,000 or less. Instead of appealing to the ASBCA, you may bring an action directly in the United States Court of Federal Claims (except as provided in the Contract Disputes Act of 1978, 41 U.S.C. 603, regarding Maritime Contracts) within 12 months of the date you receive this decision.

G.5 Records:

Unless otherwise provided in this contract or by statute, the Purchaser shall maintain all records and documents relating to the terminated portion of this contract for six years after final settlement. This includes all books and other evidence bearing on the Purchaser’s costs and expenses under this contract. The Purchaser shall make these records and documents available to the Government, at the Purchaser’s office during normal business hours without charge.

Records and documents may be digitally scanned for electronic storage at no cost to the Government.

H PAYMENTS

H.1 The Billing Cycle:

This is a one-time sale; full payment must be received prior to the removal of any property. The “Notice of Award, Statement and Removal” document is the only invoice or billing document.

H.2 Types of Acceptable Payments:

All payments, including those for storage charges, liquidated damages and interest shall be in U.S. currency.

Acceptable forms of payment include Electronic Fund Transfer (EFT), Bank Account (ACH), cashier’s check, certified check, travelers check, bank draft, money order or credit card (Master Card, Visa, Discover Card, and/or American Express).

Make checks payable to the U.S. Treasury are acceptable. When using a credit card method of payment, the credit card number, credit card security code (3-or 4-digit code on the back of the card), name as printed on the credit card, and the expiration date shall be provided. The U.S. Treasury limits all credit card transactions to $24,999.99.

Transactions greater than $24,999.99 cannot be split into two or more credit card transactions. Bidders whose payment is accompanied by a letter of credit or who have on file an approved bid bond (SF 24 or SF 34) may make their payments by uncertified personal or company checks, but only up to an amount equal to the penal sum of their bond or the amount of their letter of credit.

Address all hand-carried or delivered payments to the following:

DLA FINANCE, J8B

ATTN: CASHIERS OFFICE

74 WASHINGTON AVENUE, N

BATTLE CREEK, MI 49037-3092

Credit Card and Bank Account (ACH) payments within the United States can be made using the website at:

https://www.pay.gov/paygov/forms/formInstance.html?agencyFormId=25176217

Should Purchaser need to make a payment for less than $1.00, the website credit card payment method cannot be used.

Instead, Purchaser will be required to complete the manual credit card form and fax it to (269) 961-7230.

H.3 Payment Confirmation:

The Government does not provide payment confirmation. Purchaser shall submit proof of payment to the SCO, showing type of payment, amount, and date submitted. The SCO will ensure payment is applied to the Purchaser’s account. Payment submission through Pay.gov is recommended to reduce processing time. Pay.Gov confirmation email is proof of payment.

Pay.Gov Link https://www.pay.gov/paygov/forms/formInstance.html?agencyFormId=25176217

I AUTHORIZED AND UNAUTHORIZED MATERIAL

I.1 Classified Material:

Performance of this contract neither requires nor authorizes the Purchaser to handle classified property or documents. Should Purchaser’s employees handle actual or suspected classified property or documents, the Purchaser shall immediately secure the documents or property from both physical loss and compromise and immediately notify the Agency’s Site Lead and the SCO of the discovery. The Purchaser shall submit a SF364 ROD. The Agency will arrange for pick up and removal of such material. Under no circumstances shall the Purchaser release the property or documents to anyone other than designated personnel. If the contents of said documents or property are at a level that requires debriefing, the Purchaser’s personnel shall be made available to the proper Government authorities for this action.

I.2 Material Potentially Presenting an Explosive Hazard (MPPEH):

Performance of this contract does not require nor authorize the Purchaser to handle MPPEH. Despite all best efforts by the Government, MPPEH may be discovered; the Purchaser shall immediately take the necessary action for protection of personnel and property. This shall include the evacuation and security of the immediate area. The Purchaser shall not attempt to handle or move the suspected property until a technically qualified trained Government representative investigates the incident. The Purchaser shall notify the Agency’s Site Lead and the SCO of the discovery immediately and submit a SF364 ROD. The Agency will arrange for pick up and removal of such material.

I.3 Radioactive Property:

Performance of this contract does not require nor authorize the Purchaser to handle radioactive property. Despite all best efforts by the Government should property activate a radiation detector alarm; the Purchaser shall immediately take the necessary action for protection of personnel and property. This shall include the evacuation and security of the immediate area. The Purchaser shall not attempt to handle or move the suspected property until a technically qualified trained Government representative investigates the incident. The Purchaser shall notify the Agency’s Site Lead and the SCO of the discovery immediately and submit a SF364 ROD. The Government will arrange for pick up and removal of such material.

I.4 Hazardous Property:

Performance of this contract does not require nor authorize the Purchaser to handle Hazardous Property. Despite all best efforts by the Government, should Hazardous Property be discovered, the Purchaser shall immediately take the necessary action for protection of personnel and property. This shall include the evacuation and security of the immediate area. The Purchaser shall not attempt to handle or move the suspected property until a technically qualified trained Government representative investigates the incident. The Purchaser shall notify the Agency’s Site Lead and the SCO of the discovery immediately via email. The Government will arrange for pick up and removal of such material.

I.5 Notice of Default/Cure Notice:

In the event of a material breach or default of the respective duties in the performance of this contract, the Agency, will serve written notice upon such material breach. The Agency reserves the right, based on the severity of the default, to pursue lesser means of resolution to the default other than written notice. The Notice of Default, regardless of form, will provide corrective actions (cure) that must be taken and a date specific (cure date) to be completed. Failure to submit payment in full for monthly billing statements is directed by Treasury and DFAS Policies and the SCO has no discretion but to exercise actions stated in Section H above.

The SCO will, based on the severity of the default, choose to:

• Resolve through informal discussions.

• Request the Purchaser to provide a written plan of action on how the default will be corrected, a specific date to be completed, and what procedures will be implemented to prevent reoccurrence of the default. (Show Cause)

• Assess Liquidated Damages, normally in the form of storages charges or actual cost of repair.

• Terminate the contract.

The Agency may take any, a combination, or all, of the following actions to satisfy its claims for any non-payments or other damages:

• Present a claim against Purchaser.

• Present a claim upon the any other applicable insurance or surety policy.

• Seek appointment of a receiver or trustee for Purchaser.

• Seek monetary damages, restitution or any other legal or equitable remedy to which it is entitled.

• Assert any other right, claim, or remedy available pursuant to the Contract Disputes Act of 1978 (41 U.S.C. 7101-

7109).

I.6 Response to Notice:

Except as otherwise provided, the default will be cured within fourteen (14) calendar days of such notice, referred to as the cure period. However, the notice may provide a longer cure period.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .