326DP001_Park-n-Ride_Asphalt_Improvements_2026_SOW.pdf
PDF 166 KB Posted
- Solicitation number
- IFB 326DP001
- Issued by
- Denver County, Denver City, Colorado
About this file
This is a Statement of Work issued by the Regional Transportation District (RTD) in Denver, Colorado for the 2026 Park-n-Ride Asphalt Improvements project. RTD is seeking qualified contractors to remove and replace a portion of the existing Federal Center Station Park-n-Ride parking lot located at 11601 W. 2nd Place, Lakewood, Colorado 80225. The project scope consists of full-depth removal of the Southeast quadrant of the parking lot (approximately 8,350 square yards), scarification and re-compaction of the subgrade, installation of a new 6.5-inch pavement section with geotextile installation after the first 2.5-inch lift, and restriping of affected parking spaces. The contractor must complete permit acquisition, construction submittals, and mobilization within 30 days of receiving Notice of Award, reach substantial completion within 30 calendar days of Notice to Proceed, complete punch list closeout within 60 days of Notice to Proceed, and submit all close-out documents within 120 days of Notice to Proceed. No specific bidder's conference date, site visit requirements, or award date are identified in the Statement of Work.
Contractors shall prepare unit cost bids based on the bid schedule and be awarded as the lowest responsible bidder. The contractor is responsible for acquiring all permits, paying permit costs, providing all materials and labor, and managing removal and disposal of waste materials. RTD will provide construction oversight, material submittal review, and all testing necessary for the project through its on-call geotechnical consultant, including asphalt density tests and subgrade compaction tests. The project includes a Small Business Enterprise (SBE) goal of 15 percent. No specific funding amounts, sources, or pricing terms are detailed in the Statement of Work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Regional Transportation District Denver, CO
Statement of Work
Clayton S. Woodruff
2026 Park-n-Ride Asphalt Improvements
Version: 01 May 19, 2026
2026 Park-n-Ride Asphalt improvements 2
CONTENTS
1. Project Description
A. Scope of the Project
B. Location
This work will be performed at the Federal Center Station Park-n-Ride: 11601 W. 2nd Place
Lakewood, CO 80225
C. Period of Performance
D. Roles and Responsibilities
2. Project Requirements
A. Invitation to Bid
B. Project Management Requirements
C. Product and Service Requirements
3. Performance Measures
A. Verification and Testing
B. Project Milestones
2026 Park-n-Ride Asphalt improvements 3
1. Project Description
A. Scope of the Project
This project consists of the full depth removal of the Southeast quadrant of the parking lot at Federal Center Station Park-n-Ride, scarification and re-compaction of the subgrade and the installation of a new 6.5” pavement section with a pavement geotextile installed after the first 2.5” lift. Parking spaces affected by the project will be restriped following the asphalt work. The area of this portion of the parking lot is approximately 8,350 square yards. Only one quadrant of parking can be closed at a time.
This work will be performed at the Federal Center Station Park-n-Ride: 11601 W. 2nd Place Lakewood, CO 80225
B. Period of Performance
The contractor after receiving Notice of award will have 30 days to complete all permit acquisition, construction submittals and mobilization to site. At this time the contractor shall receive notice to proceed and will have 30 calendar days to reach substantial completion, and an additional 30 calendar days to complete punch list closeout. The contractor will then have 60 days to complete and submit all documents for contract close out and receive final acceptance.
C. Roles and Responsibilities
The contractor shall be responsible for acquiring all permits and paying all permit costs associated with this project, all materials and labor needed to complete this project and the removal and disposal of all waste materials.
The RTD is the owner of the property and shall provide construction oversite and material submittal review.
RTD shall provide, through our on-call geotechnical consultant, all testing necessary for this project including but not limited to asphalt density tests and all tests associated with subgrade compaction.
Judy Alcantara Cross-Out
2026 Park-n-Ride Asphalt improvements 4
2. Project Requirements
A. Invitation to Bid
Contractors shall prepare unit cost bids based on the bid schedule for this project and be awarded based on the lowest responsible bidder.
B. Project Management Requirements
The Contractor shall provide a schedule for the work necessary to complete the described work within the time frame set forth in the contract documents.
C. Product and Service Requirements
The contractor shall be responsible for providing a new paved and striped parking area that meets all requirements set forth in the specifications and drawings.
3. Performance Measures
A. Verification and Testing
The RTD shall be testing the pavement to confirm installation meets all CDOT requirements for asphalt pavement.
The RTD shall be requiring a proof roll to confirm subgrade preparation prior to any asphalt placement.
B. Project Milestones
# Milestone Description # of Calendar
Days to Delivery
Notice to Proceed complete permit acquisition and all submittal approvals.
The submittals and permits shall include but not be limited to: Project Schedule, City Permits, RTD building and Grounds permit, Quality Plan, Safety Plan, Traffic
Control Plan(s), Pedestrian Access Control Plan, Asphalt Mix Designs, Product Data Submittals
30 Days after notice of award
Substantial completion Installation of all contract items
30 days from
Notice to proceed
Punchlist
Closeout Complete all punch list items
60 days from notice to proceed
Final Acceptance
All close out documents and final payment submitted 120 Days after Notice to Proceed
2026 Park-n-Ride Asphalt improvements 5
File details come from the government source that posted it. Updated .