This document is a Special Provisions contract from the County of Sacramento's Department of Regional Parks for the Installation of Solar Pump and Motor, identified as Contract No. 32161. The project is located at 9980 Stablegate Rd., Wilton, CA 95693, and involves the installation of a solar pump and motor system. The contract has a fixed time of completion set at 30 calendar days, with the project manager being KC Sorgen from the County of Sacramento Department of Regional Parks.

The contract specifies that no onsite power exists, requiring the contractor to provide a portable generator for power needs, and the contractor will not have access to phones on-site, necessitating mobile phone arrangements for communication. The contractor must obtain prior approval for site access and storage areas, implement safety precautions, and provide temporary fencing and lock boxes to protect materials and equipment from theft and unauthorized entry. The contract will be awarded by the Assistant County Executive Officer, and the contractor must adhere to the County of Sacramento Standard Construction Specifications dated November 1, 2024, which can be downloaded at no cost from http://www.saccountyspecs.net.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COUNTY OF SACRAMENTO

DEPARTMENT OF REGIONAL PARKS

CUPCCAA CONTRACT

SPECIAL PROVISIONS

INSTALLATION OF SOLAR PUMP AND MOTOR

CONTRACT NO. 32161

NOTE: The County of Sacramento Standard Construction Specifications dated

November 1, 2024 is hereby made part of these Specifications. A copy of the Standard Construction Specifications may be viewed and downloaded for no cost at: http://www.saccountyspecs.net

Liz Bellas, Director, DEPARTMENT OF REGIONAL PARKS

SPECIAL PROVISIONS

INSTALLATION OF SOLAR PUMP AND MOTOR

9980 Stablegate Rd., Wilton, CA 95693

CONTRACT NO. 32161

PROJECT MANAGER

KC Sorgen

County of Sacramento

Department of Regional Parks

10361 Rockingham Dr., STE 100

Sacramento CA 95827

Email: sorgenkc@saccounty.gov

TABLE OF CONTENTS FOR CONTRACT DOCUMENTS

DIVISION 1 - GENERAL REQUIREMENTS

MODIFICATIONS TO STANDARD CONSTRUCTION SPECIFICATIONS

1-1 GENERAL

2-11 BID GUARANTEE

3-7 EXECUTION OF CONTRACT

7-9 TEMPORARY FACILITIES

7-9.01 CONSTRUCTION SITE UTILITIES

7-10 PROTECTION OF WORK, PERSONS AND PROPERTY

7-15 TIME OF COMPLETION

APPENDIX A – Sample Agreement

DIVISION 1 - GENERAL REQUIREMENTS

Modifications to the Standard Construction Specifications are noted below. The Standard

Construction Specifications, along with these project specifications, shall be considered as one body of specifications.

MODIFICATIONS TO STANDARD CONSTRUCTION SPECIFICATIONS

1-1 GENERAL

Pursuant to Section 22034 of the Public Contract Code and 2.61.058 of the Sacramento

County Code, the CUPCCAA Contract will be awarded by the Asst County Executive

Officer.

2-11 BID GUARANTEE

The County does not have a standard bid bond/guarantee form. The bid bond/guaranty form may be provided by the corporate surety.

3-7 EXECUTION OF CONTRACT

Agreement forms shall be those shown in Sample Forms of the Standard Construction

Specifications.

7-9 TEMPORARY FACILITIES

1. The Contractor shall obtain the prior approval of the Project Inspector for acceptable site access or before using any area or space for Contractor’s storage during construction operations. Any required safety precautions such as signs, danger signals, lanterns, barricades, etc., shall be installed by the Contractor during construction operations.

2. No advertising signs of any kind will be permitted except by written permission of the

Project Manager.

7-9.01 CONSTRUCTION SITE UTILITIES

1. ELECTRICAL POWER: No onsite power exists. The Contractor shall provide a portable generator for any power needs.

2. TELEPHONE: Contractor will not have access to phones on site and therefore, shall arrange for use of mobile phone if needed for on-site communication.

7-10 PROTECTION OF WORK, PERSONS AND PROPERTY

1. Provide temporary fencing, lock boxes etc., as required to protect material storage and equipment from theft, vandalism and unauthorized entry.

7-15 TIME OF COMPLETION

The time for completion of this contract shall be 30 calendar days commencing as specified in Section 7-1 of the Standard Construction Specifications.