3150323433GroupSpec947.pdf

PDF 184 KB Posted

Attached to
Bituminous Concrete Asphalt Mixtures (2026 VPP)
Contract number
Bituminous Concrete Asphalt Mixtures (2026 VPP)
Issued by
New York

About this file

Document Summary

Group Specification #947 is an awarded contract (Award #23433) issued by the State of New York Executive Department, Office of General Services, Procurement Services. This specification document, dated November 14, 2023, supersedes the previous SPEC-940 dated October 30, 2019, and applies to Commodity Group 31555 (Liquid Bituminous Materials) for use on 2026 VPP NYSDOT Specific Projects funded by Federal and State sources.

The specification establishes requirements for the supply of liquid bituminous materials, specifically asphalt emulsions, that must be sourced from NYS Department of Transportation approved primary sources listed on the NYS Approved List. Qualified suppliers must operate NYSDOT-approved manufacturing facilities and maintain permanent storage tanks of at least 10,000 gallons each for each type of asphalt emulsion bid. All materials must be sampled, tested, inspected, and certified in accordance with NYSDOT Materials Method 702-2 Asphalt Emulsion Quality Assurance. Quantity measurements must be documented through truck scales or meters tested annually for accuracy, with tickets machine-printed to show storage facility identification, ticket numbers, dates/times, item types, and quantities in 60°F gallons. Contractors must provide evidence of scale or meter calibration and, if applicable, documentation of 24/7 access to weighing operations. The State reserves the right to inspect supplier facilities at any time, with any identified deficiencies requiring correction within 10 days or risk contractor default.

View the file

Other files

File Type Posted
3150323433FederalAid.pdf PDF
315xxPriceAdjust26.xlsx XLSX spreadsheet
31502PriceAdjust24.xlsx XLSX spreadsheet
3150323433SuperpaveRebates.pdf PDF
3150323433GroupSpec951.pdf PDF
3150323433SuperpaveDesign.pdf PDF
3150323433DetailedSpec.pdf PDF
3150323433Regions.pdf PDF
3150323433Insurance.pdf PDF
3150323433a.pdf PDF
3150323433SuperpaveDimensions.pdf PDF
3150323433Notes.pdf PDF
31555PriceAdjust25.xlsx XLSX spreadsheet
3150323433WorkZone.pdf PDF
3150323433Pricing.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

23433_Group Specifications #947

Group Specifications #947

AWARD #23433

GROUP 31503 – BITUMINOUS CONCRETE ASPHALT MIXTURES Page 2 of 3 (2026 VPP NYSDOT Specific Projects) (Federal & State Funds)

State of New York Executive Department

Office of General Services Procurement Services

Corning Tower - 38th Floor Empire State Plaza

Albany, NY 12242

GROUP SPECIFICATION

COMMODITY GROUPS:

31555

LIQUID BITUMINOUS MATERIALS

DATE OF ISSUE 11/14/2023

NO. OF PAGES 3

SPECIFICATION NO. 947

(Supersedes SPEC-940 dated October 30, 2019)

BIDDERS ARE REQUESTED TO RETAIN THIS SPECIFICATION FOR FUTURE REFERENCE

Contents

GENERAL INFORMATION

MATERIALS:

SAMPLING, TESTING, INSPECTING, AND REPORTING:

REQUIRED QUALIFICATIONS:

GROUP 31503 – BITUMINOUS CONCRETE ASPHALT MIXTURES Page 3 of 3 (2026 VPP NYSDOT Specific Projects) (Federal & State Funds)

GENERAL INFORMATION

MATERIALS:

Materials supplied must be from a NYS Dept. of Transportation approved location/primary source (listed on the NYS Approved List).

SAMPLING, TESTING, INSPECTING, AND REPORTING:

All liquid bituminous material intended for use on State agency and non-State agency projects shall be sampled, tested, inspected, certified and shipped in accordance with NYSDOT Materials Method 702-2 Asphalt Emulsion Quality Assurance. The State reserves the right to inspect liquid bituminous material supply facilities and the equipment of any successful bidder at any time for conformance with the requirements listed herein; if deficiencies are found, such deficiencies shall be corrected within 10 days or the contractor will be considered in default.

REQUIRED QUALIFICATIONS:

A NYS approved primary source must meet the following conditions:

1. The Contractor’s liquid bituminous materials manufacturing facility shall have been approved by the NYSDOT.

2. The liquid bituminous material shall be obtained from a primary source listed on the NYSDOT approved list of primary sources. An approved primary source is a Contractor that samples, tests, and certifies that the materials are in conformance with the NYSDOT materials specifications.

3. Asphalt emulsions as defined in NYSDOT Standard Specifications §702, shall be stored in an approved facility having a minimum of one permanent storage tank for each type of asphalt emulsion bid. The tank(s) shall have a storage capacity of at least 10,000 gallons each, be capable of maintaining material homogeneity and have equipment capable of heating the material to the proper application temperature prior to shipment.

4. The Contractor shall have evidence available to show that the scale or meter(s) have been tested for accuracy by either a competent scale technician or the County Sealer of Weights and Measures. The scale or meter check shall be performed each calendar year before any material is supplied

5. The quantity of liquid bituminous material shall be measured by truck scale or meter(s) and a ticket shall be printed to document the quantity.

The ticket printed shall meet the following requirements:

a. Storage facility identification

b. Ticket Number

c. Date/time

d. Item Number and Type

e. Quantity ticket printed by machine

f. Quantity in 60° F gallons for emulsions.

6. Truck Scales: The ticket printer shall machine print in digital form a minimum of two of the following:

(1) Tare weight

(2) Gross weight

(3) Net weight

The scale system shall be interlocked to allow printing only when the scale has come to a complete rest.

A truck scale shall be located at the storage facility unless the following conditions are met:

(a) The Contractor owns the truck scale or has full control of the weighing operations. The scale shall be located in close proximity (approximately 1,000 feet or less) to the storage tanks. The acceptability of the distance will be determined by the NYSDOT.

(b) The Contractor provides documentation to the NYSDOT that it has complete access to the truck scale 24 hrs/day, 7 days/week.

7. Meters: The ticket printer shall machine print in digital form:

(1) Beginning meter reading

(2) Ending meter reading

(3) Total gallons at 60° F

C. If a meter is used, it shall be permanently installed to connect it with the approved storage tank(s), and shall be used to measure all quantities.

GENERAL INFORMATION
MATERIALS:
SAMPLING, TESTING, INSPECTING, AND REPORTING: