This Statement of Work (SOW) details a bathroom remodeling project for the U.S. Coast Guard at Station Golden Gate in Sausalito, California. The project requires a contractor to update ten bathroom sink/vanities and shower inserts, with equipment colors to be selected by the technical point of contact. Work must be performed between 7:00 AM and 5:00 PM, Monday through Friday, excluding federal holidays, and will involve complete removal and replacement of existing fixtures, proper disposal of old materials, and site cleanup in compliance with industry standards and environmental regulations. The contractor will provide all necessary labor, materials, and equipment, while the government will supply electricity, parking, and a laydown area.
The technical point of contact is Francisco Rivera, reachable at (909) 973-3879 or francisco.p.rivera@uscg.mil. Project tasks include mobilization, vanity and shower insert removal and replacement, disposal of old materials, and final demobilization with site restoration. The Coast Guard's technical POC will monitor and accept the completed work, with specific requirements including valid contractor vehicle registration, insurance, personnel identification, and minimal disruption to Coast Guard operations. Contractors must ensure daily cleanup and return all construction areas to their original condition upon project completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 30467PR250000020 Questions and Answers.pdf | ||
| 30467PR250000020 Remodel Bathrooms STA Golden Gate.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REMODEL BATHROOMS AT STATION GOLDEN GATE
PART 1 - GENERAL
The intent of this Statement of Work (SOW) is to have the contractor remodel bathrooms at Station Golden Gate, Sausalito, CA. The contractor will provide all labor, materials, and equipment necessary to complete the installation in compliance with industry standards and applicable regulations.
PART 2 - SCOPE
The contractor shall update ten (10) bathroom sink/vanities and shower inserts. Equipment colors shall be chosen by the technical POC.
PART 3 - FACILITY AND SECURITY REQUIRMENTS
1. Contractor vehicles must have valid registration and insurance, and vehicle operators must have a valid driver license. All personnel shall have valid photo identification.
2. The contractor shall clean up all areas to ensure they are clear of debris daily. At completion of the project all construction areas will be returned to their original condition. The contractor shall remove all waste material generated and dispose of in accordance with industry standards and applicable environmental rules and regulations.
3. Minimizing impact to Coast Guard operations. Work performed at Sausalito, CA shall be completed between the hours of 7:00AM and 5:00PM, Monday thru Friday (excluding Federal Holidays) unless authorized by the Contracting Officer.
PART 4 - GOVERNMENT FURNISHED MATERIAL
1. Contractor will provide all materials to complete the work necessary. The government will provide electricity, parking, and laydown area as available from the unit. Bathroom facilities will not be available for contractor personnel.
PART 5 - TECHNICAL POINT OF CONTACT DESIGNATION
1. Technical POC for this task is:
Francisco Rivera Office: (909) 973-3879 E-mail: francisco.p.rivera@uscg.mil
PART 6 – TASKS
1. Mobilization. Mobilize all necessary equipment and personnel to execute the bathroom sink/vanity and shower insert upgrade project.
2. Vanity Removal and Replacement. Remove existing 30-inch vanities and replace them with new bathroom vanities and sinks.
3. Shower Insert Removal and Replacement. Remove and replace shower inserts.
4. Disposal. Remove and dispose of all old vanities, sinks, and shower inserts in accordance with industry standards and applicable environmental regulations.
5. Demobilization. Remove all equipment and personnel from the site and restore the areas to their original condition.
PART 7 – ACCEPTANCE
1. Completion of work under this contract will be monitored and accepted by Coast Guard Technical POCs listed in
PART 4.
END
File details come from the government source that posted it. Updated .