This is a Questions and Answers document for federal contract opportunity 30252PR260000013 regarding sprinkler system repairs at Building 91 and Building 92. The document does not address specific products or services required, pricing, response dates, or award information, as it is limited to clarifications on project-related inquiries.
The Q&A addresses eight inquiries from potential bidders. Key points include: no previous inspection reports are available for the dry valves that have been rebuilt but continue experiencing issues; a missing Viking dry valve trim kit has been returned and will be available for the contractor, with the SOW requiring trim kit replacement; the bid date and time remain unchanged; no construction cost estimates or ranges are provided for this Fixed Price (FFP) solicitation; planholders and bidders lists cannot be released prior to award; non-mandatory pre-bid attendance information is not provided; no addenda have been published; and bidders should follow up approximately one week after solicitation closure for award results. The document emphasizes adherence to the Statement of Work (SOW) requirements and standard federal contracting protocols regarding information disclosure.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pricing Spreadsheet.xlsx | XLSX spreadsheet | |
| Sta Washington 12a. RFQ Schedule 30252PR2600000131.pdf | ||
| SOW STA Washington Dry Sprinkler System Valve Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions For 30252PR260000013 BLDG 91 and BLDG 92 sprinkler system repairs
• Do you have any past inspection reports available for the dry valves? Our representative was informed onsite that the valves had been rebuilt but are still experiencing issues. Could you please confirm whether any troubleshooting has been performed, and if so, what the findings were?
Answer: I do not have previous years inspection reports on hand.
• Additionally, one Viking dry valve appears to be missing its trim kit. Could you confirm whether the trim kit is available onsite or provide any information regarding why it may be missing?
Answer: The missing trim kit has been returned and will be available for the contractor. As a reminder for the contractor, the SOW states the trim kits shall be replaced
• Confirm that the bid date and time listed above are unchanged.
Answer: They are unchanged.
• Construction cost estimate or a construction cost range for the project.
Answer: We do not provide this information for FFP solicitations.
• Planholders list/bidders list.
Answer: We cannot provide this information. Only the winning contractor and their bid amount can be released after the award is made.
• Non-Mandatory pre-bid attendance list from April 9.
Answer: We do not provide this information.
• Have you issued any addenda?
Answer: If so, please attach them to this response. No addenda has been published.
• When is the best time to follow up for bid results?
Answer: One week following the close of the solicitation should be enough time for us to have the winning contractor identified and contract awarded.