Station_Fire_Island_Emergency_Doors_SOW.docx
DOCX document 4 MB Posted
- Attached to
- STA FIRE ISLAND EMERGENCY DOOR REPLACEMENT (4)
- Solicitation number
- 30199270000007
- Issued by
- Not on record
About this file
This is a Statement of Work (SOW) for the replacement of four exterior emergency exit door assemblies at U.S. Coast Guard Station Fire Island. The contractor must provide all labor, materials, tools, equipment, delivery, and disposal necessary to perform one-for-one replacement of existing doors in their current openings using standard installation methods. The work maintains existing opening sizes, locations, door handing, swing, and emergency exit function, with no structural alterations, opening enlargement, or changes to fire alarm or access control equipment included. Doors are approximately 35 3/4 inches by 82 inches; however, contractors are required to conduct a pre-bid site visit to field-verify all dimensions, door thickness, frame profiles, anchorage, thresholds, glazing, hardware, and existing fire labels before ordering.
The contractor must supply four complete commercial aluminum exterior door assemblies with compatible frames and factory finishes suitable for coastal salt-air environments, including vision lites matching existing configurations, heavy-duty panic exit devices, surface-mounted door closers, corrosion-resistant hardware, weatherstripping, and all associated components. Work shall be completed within 30 calendar days after contract award, performed Monday through Friday 0800-1500, excluding federal holidays, unless authorized otherwise. The contractor must coordinate with the Contracting Officer Representative (COR), CWO Coyet A. Carter at (475) 301-1053, regarding access, sequencing, material staging, and scheduling. Qualified commercial door installers must follow manufacturer instructions and applicable safety, building, accessibility, and life-safety requirements, maintaining required exit routes throughout the work. A minimum one-year warranty on installation workmanship and contractor-furnished materials is required, beginning at Government acceptance, in addition to any longer manufacturer warranties. Final acceptance requires Government inspection of all four completed assemblies and correction of any identified deficiencies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DEI CLAUSE FOR SOLICITATIONS.docx | DOCX document | |
| SF1449-21_BLANK.pdf | ||
| FAR CLAUSES_CONSTRUCTION 35K TO 250K.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Station Fire Island Emergency Door Replacement Scope of Work | Non-Complex Operational Maintenance 1 Purpose and Scope Provide all labor, materials, tools, equipment, delivery, and disposal necessary to replace four existing exterior emergency exit door assemblies at U.S. Coast Guard Station Fire Island. Perform one-for-one replacement in the existing openings using standard installation methods. Maintain the existing opening sizes, locations, door handing, swing, and emergency exit function. No structural alterations, opening enlargement, or changes to fire alarm or access control equipment are included.
2 Site Verification and Submittals A pre-bid site visit is highly encouraged. Field-verify all four openings, door thickness, frame profiles, anchorage, thresholds, glazing, hardware, and any existing fire labels before ordering. The reported door size of 35 3/4 inches by 82 inches is approximate and is not a fabrication dimension. The photographs show representative conditions and do not establish quantities or dimensions.
Submit product data for doors, frames, glazing, hardware, finish, and manufacturer installation instructions for Government review before procurement. Provide manufacturer documentation of the proposed storm and wind performance appropriate to the site and existing application. Verify and preserve any required fire rating; do not assume a rating from the photographs. Resolve rating and compatibility questions through the COR before ordering.
3 Materials and Installation Supply four complete commercial aluminum exterior door assemblies with compatible frames and factory finish suitable for a coastal salt-air environment. Provide vision lites matching the existing configuration, with safety glazing and compatible glazing stops, gaskets, and seals. Glazing shall meet the documented storm performance of the assembly where required.
Provide new heavy-duty panic exit devices, surface-mounted door closers, compatible hinges or continuous hinges, exterior pull and locking trim, thresholds, door bottoms, and perimeter weatherstripping. Use corrosion-resistant hardware and fasteners compatible with aluminum; isolate dissimilar metals. Coordinate cylinders and keying with the COR to match the unit keying requirements.
Carefully remove existing doors, frames, and associated hardware without damaging adjacent walls, sidelights, landings, or finishes. Protect components remaining in place. Remove and legally dispose of demolition debris off Government property.
Set frames plumb, level, square, and securely anchored to sound existing substrates in accordance with manufacturer instructions. Install doors with uniform manufacturer-specified clearances. Provide compatible exterior sealant at frame perimeters and threshold interfaces; maintain required drainage paths. Restore only minor installation-related surface damage to match adjacent finishes.
4 Operation and Acceptance Adjust hinges, strikes, panic devices, and closers so each door swings freely without binding or dragging, closes under control, and positively latches. Demonstrate emergency egress from the occupied side without a key, tool, or special knowledge. Verify exterior locking and key operation, secure anchorage, continuous weather seals, and proper threshold fit. Preserve required exit clearance and accessible operation. Correct deficiencies before requesting final acceptance.
Provide product data, keys, care instructions, warranty documents, and a brief operation and maintenance demonstration to unit personnel. Final acceptance requires Government inspection of all four completed assemblies and correction of identified deficiencies.
5 Work Controls and Existing Conditions Use qualified commercial door installers and follow manufacturer instructions and applicable safety, building, accessibility, and life-safety requirements. Coordinate sequencing with the COR and unit personnel. Keep required exit routes available; do not disable multiple required exits at the same time. Secure and weather-protect openings during the work and at the end of each workday.
Before disturbing existing coatings, sealants, or other suspect materials, coordinate with the COR for Government-provided lead and asbestos information and any required testing. If suspect hazardous materials or concealed deterioration are encountered, stop affected work, protect the area, and notify the COR. Lead or asbestos abatement, major substrate repair, structural modifications, and work requiring engineered design are outside this scope and require contracting officer review before proceeding.
6 Schedule and Warranty Work shall be completed within 30 calendar days after contract award. Submit the proposed delivery and installation schedule promptly after award. Normal work hours are Monday through Friday, 0800–1500, excluding federal holidays, unless otherwise authorized. Coordinate access, transportation, material staging, and work dates with the COR before mobilization; include required delivery and mobilization costs.
Provide a minimum one-year warranty on installation workmanship and contractor-furnished materials beginning at Government acceptance, in addition to any longer manufacturer warranties. Repair or replace defective work at no additional cost to the Government.
7 Coordination COR: CWO Coyet A. Carter, Sector Long Island Sound Email: Coyet.A.Carter@uscg.mil Phone: (475) 301-1053 Unit site contacts: MK1 Kyle Turcott and DCC Kyle Swann; confirm current availability through the COR before scheduling.
The COR coordinates access and technical review. Only the warranted contracting officer may authorize changes to contract scope, price, or performance period.
Existing Conditions Photographs
Photo 1 Interior door face and panic exit device
Photo 2 Deterioration below the vision lite
Existing Conditions Photographs Continued
Photo 3 Exterior door face and pull hardware
Photo 4 Existing hinge jamb and panic exit device image1.png image2.png image3.png image4.png