This file is a reference guide documenting typical Federal Acquisition Regulation (FAR) clauses required for fixed-price construction contracts valued between $35,000 and $250,000. The document provides a comprehensive table of standard clauses likely to be included in contracts within this range, which falls above the micro-purchase threshold but within the Simplified Acquisition Threshold (SAT). Key required clauses address labor restrictions (convict labor prohibition, equal opportunity requirements), subcontractor management (debarred entity restrictions, commercial items encouragement), payment procedures (progress and final payments under fixed-price construction), site conditions and contractor responsibilities (site investigation, material quality, workmanship standards, superintendent provisions), permitting and safety (permits and licenses, accident prevention), government oversight (inspection and testing rights), and termination rights (termination for convenience). Additional clauses that may apply include scheduling requirements for work exceeding 60 days and value engineering provisions for contracts exceeding the simplified acquisition threshold.

The document explicitly states it is not exhaustive and advises that the contracting officer determines the final applicable clauses for each specific project, with definitive requirements found in individual solicitation documents. This guide applies directly to the related Coast Guard Station Fire Island Emergency Door Replacement solicitation, a construction project involving replacement of four exterior emergency exit door assemblies, which would fall within the $35,000 to $250,000 contract range and therefore be subject to these standard FAR clause requirements.

View the file

Other files

File Type Posted
DEI CLAUSE FOR SOLICITATIONS.docx DOCX document
SF1449-21_BLANK.pdf PDF
Station_Fire_Island_Emergency_Doors_SOW.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Determining the exact Federal Acquisition Regulation (FAR) clauses for a construction contract between $35,000 and $250,000 can be complex as it depends on the specific details of the project. However, I can provide a general overview of the key clauses that are typically required for contracts within this range.

This contract value falls above the micro-purchase threshold and within the Simplified Acquisition Threshold (SAT). The magnitude of the project would be described as either "between $25,000 and $100,000" or "between $100,000 and $250,000" in advance notices and solicitations.

Below is a table of some of the most common FAR clauses that are likely to be included in a fixed-price construction contract between $35,000 and $250,000.

Clause Number
Clause Title
Description
52.203-6
Restrictions on Subcontractor Sales to the Government
Prohibits subcontractors from making direct sales to the government of items that are part of the prime contract.
52.204-25
Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
Prohibits the use of certain telecommunications and video surveillance services or equipment from specific companies.
52.209-6
Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment
Requires contractors to flow down the requirement to not subcontract with debarred or suspended entities.
52.222-3
Convict Labor
Prohibits the use of convict labor in the performance of the contract.
52.222-21
Prohibition of Segregated Facilities
Prohibits the contractor from maintaining segregated facilities for their employees.
52.222-26
Equal Opportunity
Requires the contractor to provide equal opportunity in employment.
52.222-50
Combating Trafficking in Persons
Prohibits trafficking in persons.
52.225-13
Restrictions on Certain Foreign Purchases
Restricts the acquisition of certain foreign products and services.
52.232-5
Payments under Fixed-Price Construction Contracts
Outlines the procedures for making payments to the contractor, including progress payments and final payment.
52.236-2
Differing Site Conditions
Provides for an equitable adjustment if the contractor encounters subsurface or latent physical conditions at the site that differ materially from those indicated in the contract.
52.236-3
Site Investigation and Conditions Affecting the Work
Requires the contractor to investigate the site and be responsible for all materials, equipment, and labor necessary to complete the work.
52.236-5
Material and Workmanship
Requires that all materials and workmanship be of good quality and that the work be performed in a skillful and workmanlike manner.
52.236-6
Superintendence by the Contractor
Requires the contractor to provide a competent superintendent who is authorized to act for the contractor.
52.236-7
Permits and Responsibilities
Requires the contractor to obtain all necessary permits and licenses and to be responsible for all damages to persons or property that occur as a result of the contractor's fault or negligence.
52.236-13
Accident Prevention
Requires the contractor to take all necessary precautions to prevent accidents.
52.244-6
Subcontracts for Commercial Items
Encourages the use of commercial items as components or end items.
52.246-12
Inspection of Construction
Gives the Government the right to inspect and test all work called for by the contract.
52.249-1
Termination for Convenience of the Government (Fixed-Price) (Short Form)
Allows the Government to terminate the contract for its convenience.

Clauses That May Be Applicable The following clauses may also be included depending on the specifics of the contract:

· 52.236-15, Schedules for Construction Contracts: This clause may be used if the work performance is expected to exceed 60 days.

· 52.248-3, Value Engineering-Construction: This clause is generally required for contracts exceeding the simplified acquisition threshold.

It is important to note that this is not an exhaustive list. The contracting officer for a specific project will determine the final list of applicable clauses. You should always refer to the solicitation documents for the definitive list of required FAR clauses.