3_Statement of Work Paint Mkg.pdf
PDF 85 KB Posted
- Attached to
- Pavement Paint Markings Federal contract opportunity
- Solicitation number
- FA4626-24-R-0003
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to selectively renew existing airfield, roadway, and parking lot pavement paint markings at Malmstrom Air Force Base (MAFB). The contractor shall provide all labor, materials, equipment, and incidentals necessary to renew cross walk markings, STOP lines, directional arrows, roadway markings, runway X's, and parking space lines. One traffic lane must remain open during the work, and the contractor shall remove and replace security bollards as needed. The related federal contract opportunity is solicitation FA4626-24-R-0003, a 100% small business set-aside with a 5-year ordering period and a 2-year optional ordering period. The total aggregate amount ordered under the contract shall not exceed $2,999,999.99.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation - FA462624R0003.pdf | ||
| 9_Special Contract Requirements.pdf | ||
| 5_MT20240079 - 05Jan24.pdf | ||
| 8_Past Performance Reference Sheet.pdf | ||
| 6_Sections L and M.pdf | ||
| 7_Technical Focus Areas.pdf | ||
| 2_Submittal Schedule Paint Markings.xlsx | XLSX spreadsheet | |
| 1_Combined Specs.pdf | ||
| 4_Bid Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 3 MAFB PAVEMENT PAINT MARKING
FA4626-24-R-0003
Statement of Work
Selectively renew existing airfield, roadway and parking lot pavement paint markings base-wide.
GENERAL: The contractor shall perform all services necessary to accomplish a complete and functional installation of the proposed work. The work shall be accomplished in accordance with the Pavement Paint Marking Maintenance Requirements Contract specifications, any associated drawings and additional requirements of the Statement of Work as discussed in the following paragraphs. The contractor shall comply with the pertinent sections of the Pavement Paint Marking
Maintenance Requirements Contract specifications in relation to the work identified in the project, whether or not specific sections are referenced.
REQUIREMENTS: The contractor shall provide all labor, materials, equipment and incidentals necessary to:
1. Renew cross walk markings on base maintained roadways (56 cross walks total)
2. Renew STOP lines and directional arrows at traffic lights (Goddard Dr and 10th Ave N)
3. Selectively renew roadway pavement paint markings.
4. Renew 6 ea. closed runway X’s.
6. Selectively renew parking space lines in parking lots.
6. One traffic lane to remain open during work.
7. Remove and replace security bollards as needed.
8. Please contact Mark Bovingdon at 731-7702 with any questions.