3-RFB FY25-0088 - Radio Booth Cabling.docx
DOCX document 386 KB Posted
- Attached to
- LEVI’S STADIUM RADIO BOOTH CABLING PROJECT
- Solicitation number
- RFB-FY25-0088
- Issued by
- Santa Clara County, San Francisco City, California
About this file
This document is a request for bids (RFB) issued by Forty Niners Stadium Management Company LLC for the Levi's Stadium Radio Booth Cabling Project located in Santa Clara, California. The project involves adding supplementary broadcast cabling, raceway, and custom plates from the 800-level booths to the truck dock at Levi's Stadium. Specifically, the work includes installing cable tray, conduit, J-hooks, and JBT enclosures; pulling new broadcast cabling from each booth to the truck dock; providing and terminating panels within JBT enclosures and truck dock racks; and providing a testing report for all cabling and connections. The bid was released on September 15, 2025, with a non-mandatory pre-bid conference and site visit scheduled for September 25, 2025. Electronic bid submissions are due on October 15, 2025, at 3:00 p.m. PT, with a public bid opening at 4:00 p.m. PT on the same day.
The project requires bidders to be licensed contractors, specifically a Class B General Building Contractor or a Class C7 Low Voltage Systems Contractor. The bid includes a 10% bid guarantee and requires compliance with prevailing wage laws, public works contractor registration, and various documentation requirements. The contract time for completion is 90 calendar days from the commencement date, with liquidated damages of $500 per day for delays. The total project scope covers fourteen booths, with twelve strands of SFMO and twelve channels of audio, and nine booths receiving a JBT enclosure. Funding and payment will be managed through progress payments, with a 5% retention held by the Stadium Manager, and the project is subject to various environmental, safety, and operational constraints specific to Levi's Stadium.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FORTY NINERS STADIUM MANAGEMENT COMPANY LLC
SANTA CLARA, CALIFORNIA
REQUEST FOR BIDS
CONTRACT DOCUMENTS AND SPECIFICATIONS
FOR
LEVI’S STADIUM RADIO BOOTH CABLING PROJECT
RFB Number: RFB-FY25-0088
ISSUE DATE:
September 15, 2025
ELECTRONIC SUBMISSION OF BIDS DUE DATE:
October 15, 2025 3:00 p.m. (PT)
PUBLIC BID OPENING
October 15, 2025 4:00 p.m. (PT)
Procurement Contact: Procurement Lead Telephone: 408-562-4986 Email: PROC@49ERS-SMC.COM
RFB COVERSHEET
Levi’s Stadium Radio Booth Cabling Project RFB Number: RFB-FY25-0088
| Event |
| Date/Information |
| RFB Release Date |
| September 15, 2025 |
| Non-Mandatory Pre-Bid Conference and Site Visit |
| September 25, 2025 @ 9:30 a.m. (PT) at Levi’s Stadium |
Email the name of each attendee, company name and email address to Proc@49ers-smc.com. Each attendee will receive a visitor pass with instructions to park and pass security to enter the Stadium.
Please arrive 15 minutes before the Pre-Bid Conference to park your vehicle at the designated area, pass security at the assigned gate and be escorted to the meeting conference room.
| Request for Clarification Due Date |
| September 30, 2025 @ 5:00 p.m. (PT) |
| Bid Due Date and Time |
| October 15, 2025 @ 3:00 p.m. (PT) |
| Bid Opening Date and Time |
| October 15, 2025 @ 4:00 p.m. (PT) via Zoom |
| End of Protest Period |
| October 22, 2025 |
| Bid Contact Information |
| Procurement Lead |
4900 Marie P DeBartolo Way Santa Clara, CA 95054
Email: Proc@49ers-smc.com
| Project Site Address |
| Levi’s Stadium |
4900 Marie P. DeBartolo Way Santa Clara, CA 95054
Services/Schedule and Plans and Specifications Documents
· See Technical Specifications
· Plans and Specifications attached as Exhibit “B”
TABLE OF CONTENTS
Page
-ii-
83784.00001\40155730.1 Table of Contents Page
| 00 11 16 – NOTICE INVITING BIDS | 5 | |
| 00 21 13 – INSTRUCTIONS TO BIDDERS | 10 | |
| ARTICLE 1. | SECURING DOCUMENTS | 10 |
| ARTICLE 2. | EXAMINATION OF SITE AND CONTRACT DOCUMENTS | 10 |
| ARTICLE 3. | INTERPRETATION OF DRAWINGS AND DOCUMENTS | 10 |
| ARTICLE 4. | ADDENDA | 11 |
| ARTICLE 5. | ALTERNATE BIDS | 11 |
| ARTICLE 6. | COMPLETION OF BID FORMS | 11 |
| ARTICLE 7. | MODIFICATIONS OF BID FORMS | 11 |
| ARTICLE 8. | SUBCONTRACTORS | 12 |
| ARTICLE 9. | LICENSING REQUIREMENTS | 12 |
| ARTICLE 10. | BID GUARANTEE (BOND) | 12 |
| ARTICLE 11. | IRAN CONTRACTING ACT OF 2010 | 13 |
| ARTICLE 12. | NONCOLLUSION DECLARATION; PROCUREMENT AND CONTRACT PROCESS INTEGRITY AND CONFLICT OF INTEREST GUIDELINES | 13 |
| ARTICLE 13. | PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION | 13 |
| ARTICLE 14. | BIDDER INFORMATION AND EXPERIENCE FORM | 13 |
| ARTICLE 15. | WORKERS' COMPENSATION CERTIFICATION | 14 |
| ARTICLE 16. | SIGNING OF BIDS | 14 |
| ARTICLE 17. | SUBMISSION OF SEALED BIDS | 14 |
| ARTICLE 18. | OPENING OF BIDS | 15 |
| ARTICLE 19. | WITHDRAWAL OF BID | 15 |
| ARTICLE 20. | BIDDERS INTERESTED IN MORE THAN ONE BID | 15 |
| ARTICLE 21. | SUBSTITUTION OF SECURITY | 16 |
| ARTICLE 22. | PREVAILING WAGES | 16 |
| ARTICLE 23. | PREVAILING WAGE COMPLIANCE DOCUMENTATION | 16 |
| ARTICLE 24. | DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS | 16 |
| ARTICLE 25. | INSURANCE REQUIREMENTS | 16 |
| ARTICLE 26. | PERFORMANCE BOND AND PAYMENT BOND REQUIREMENTS | 16 |
| ARTICLE 27. | SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES AND FEES | 17 |
| ARTICLE 28. | PERMIT AND INSPECTION FEE ALLOWANCE | 17 |
| ARTICLE 29. | FILING OF BID PROTESTS | 17 |
| ARTICLE 30. | BASIS OF AWARD; BALANCED BID | 18 |
| ARTICLE 31. | AWARD PROCESS | 18 |
| ARTICLE 32. | EXECUTION OF CONTRACT | 18 |
| ARTICLE 33. | QUESTIONS | 18 |
| 00 41 43 – BID FORMS | 19 | |
| 1.1 | BID. | 19 |
| 1.2 | BID BOND | 24 |
| 1.3 | LIST OF SUBCONTRACTORS | 27 |
| 1.4 | BIDDER INFORMATION AND EXPERIENCE FORM | 29 |
| 1.5 | NON-COLLUSION DECLARATION | 36 |
| 1.6 | IRAN CONTRACTING ACT CERTIFICATION (PUBLIC CONTRACT CODE SECTION 2200 ET SEQ.) | 37 |
| 1.7 | PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION | 38 |
| 1.8 | CONTRACTOR’S CERTIFICATE REGARDING WORKERS’ COMPENSATION. | 39 |
| 1.9 | REQUEST FOR APPROVED EQUALS FORM. | 40 |
| 00 52 13 – CONTRACT | 41 | |
| 00 61 13 – BOND FORMS | 46 | |
| 00 72 13 – GENERAL CONDITIONS | 55 | |
| ARTICLE 1. | DEFINED TERMS | 55 |
| ARTICLE 2. | CONTRACT DOCUMENTS | 59 |
| ARTICLE 3. | PRECONSTRUCTION AND CONSTRUCTION COMMUNICATION | 60 |
| ARTICLE 4. | CONTRACT DOCUMENTS: COPIES & MAINTENANCE | 61 |
| ARTICLE 5. | EXAMINATION OF DRAWINGS, SPECIFICATIONS AND SITE OF WORK | 61 |
| ARTICLE 6. | MOBILIZATION | 62 |
| ARTICLE 7. | EXISTENCE OF UTILITIES AT THE WORK SITE | 63 |
| ARTICLE 8. | SOILS INVESTIGATIONS | 63 |
| ARTICLE 9. | CONTRACTOR’S SUPERVISION | 64 |
| ARTICLE 10. | WORKERS | 64 |
| ARTICLE 11. | INDEPENDENT CONTRACTORS | 64 |
| ARTICLE 12. | SUBCONTRACTS | 65 |
| ARTICLE 13. | VERIFICATION OF EMPLOYMENT ELIGIBILITY | 65 |
| ARTICLE 14. | REQUESTS FOR SUBSTITUTION | 65 |
| ARTICLE 15. | SHOP DRAWINGS | 67 |
| ARTICLE 16. | SUBMITTALS | 67 |
| ARTICLE 17. | MATERIALS | 67 |
| ARTICLE 18. | PERMITS AND LICENSES | 68 |
| ARTICLE 19. | TRENCHES | 69 |
| ARTICLE 20. | TRAFFIC CONTROL | 70 |
| ARTICLE 21. | DIVERSION OF RECYCLABLE WASTE MATERIALS | 70 |
| ARTICLE 22. | REMOVAL OF HAZARDOUS MATERIALS | 70 |
| ARTICLE 23. | SANITARY FACILITIES | 71 |
| ARTICLE 24. | AIR POLLUTION CONTROL | 71 |
| ARTICLE 25. | LAYOUT AND FIELD ENGINEERING | 71 |
| ARTICLE 26. | TESTS AND INSPECTIONS | 71 |
| ARTICLE 27. | PROTECTION OF WORK AND PROPERTY | 72 |
| ARTICLE 28. | CONTRACTOR’S MEANS AND METHODS | 72 |
| ARTICLE 29. | AUTHORIZED REPRESENTATIVES | 72 |
| ARTICLE 30. | HOURS OF WORK | 72 |
| ARTICLE 31. | PAYROLL RECORDS; LABOR COMPLIANCE | 74 |
| ARTICLE 32. | PREVAILING RATES OF WAGES | 75 |
| ARTICLE 33. | PUBLIC WORKS CONTRACTOR REGISTRATION | 76 |
| ARTICLE 34. | EMPLOYMENT OF APPRENTICES | 76 |
| ARTICLE 35. | NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY | 76 |
| ARTICLE 36. | DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS | 77 |
| ARTICLE 37. | LABOR/EMPLOYMENT SAFETY | 77 |
| ARTICLE 38. | INSURANCE | 78 |
| ARTICLE 39. | FORM AND PROOF OF CARRIAGE OF INSURANCE | 81 |
| ARTICLE 40. | TIME FOR COMPLETION AND LIQUIDATED DAMAGES | 82 |
| ARTICLE 41. | COST BREAKDOWN AND PERIODIC ESTIMATES | 83 |
| ARTICLE 42. | PROGRESS ESTIMATES AND PAYMENT | 83 |
| ARTICLE 43. | SECURITIES FOR MONEY WITHHELD | 85 |
| ARTICLE 44. | CHANGES AND EXTRA WORK. | 85 |
| ARTICLE 45. | FINAL ACCEPTANCE AND PAYMENT | 99 |
| ARTICLE 46. | OCCUPANCY; BENEFICIAL USE | 100 |
| ARTICLE 47. | INDEMNIFICATION | 100 |
| ARTICLE 48. | PROCEDURE FOR RESOLVING DISPUTES | 101 |
| ARTICLE 49. | STADIUM MANAGER’S RIGHT TO TERMINATE CONTRACT | 105 |
| ARTICLE 50. | WARRANTY AND GUARANTEE OF WORK | 108 |
| ARTICLE 51. | DOCUMENT RETENTION & EXAMINATION | 111 |
| ARTICLE 52. | SEPARATE CONTRACTS | 112 |
| ARTICLE 53. | NOTICE AND SERVICE THEREOF | 112 |
| ARTICLE 54. | NOTICE OF THIRD PARTY CLAIMS | 112 |
| ARTICLE 55. | STATE LICENSE BOARD NOTICE | 112 |
| ARTICLE 56. | INTEGRATION | 113 |
| ARTICLE 57. | ASSIGNMENT OF CONTRACT | 113 |
| ARTICLE 58. | CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY | 113 |
| ARTICLE 59. | ASSIGNMENT OF ANTITRUST ACTIONS | 113 |
| ARTICLE 60. | PROHIBITED INTERESTS | 113 |
| ARTICLE 61. | CONTROLLING LAW | 114 |
| ARTICLE 62. | JURISDICTION; VENUE | 114 |
| ARTICLE 63. | LAWS AND REGULATIONS | 114 |
| ARTICLE 64. | PATENTS | 114 |
| ARTICLE 65. | OWNERSHIP OF CONTRACT DOCUMENTS | 114 |
| ARTICLE 66. | NOTICE OF TAXABLE POSSESSORY INTEREST | 114 |
| ARTICLE 67. | SURVIVAL OF OBLIGATIONS | 115 |
| 00 73 13 – SPECIAL CONDITIONS | 116 | |
| 01 00 00 – GENERAL REQUIREMENTS | 126 | |
| TECHNICAL SPECIFICATIONS | 145 | |
| EXHIBIT “A” Change Order Form | 147 | |
| EXHIBIT “B” PLANS AND SPECIFICATIONS | 149 |
TABLE OF CONTENTS
(Continued) Page
Levi’s Stadium Radio Booth Cabling Project RFB Number: RFB-FY25-0088
| -i- |
| TABLE OF CONTENTS |
Levi’s Stadium Radio Booth Cabling Project RFB Number: RFB-FY25-0088
| -19- |
| 00 11 16 – NOTICE INVITING BIDS |
00 11 16 – NOTICE INVITING BIDS
ARTICLE 1 – GENERAL
1.01 NOTICE
Notice is hereby given that the Forty Niners Stadium Management Company LLC (“Stadium Manager”) invites and will receive sealed Bids up to but not later than 3:00 p.m. on October 15, 2025 online via the Stadium Manager’s e-Procurement Portal, which can be found at https://49ers.bonfirehub.com/portal/ for the furnishing to Stadium Manager of all labor, equipment, materials, tools, services, transportation, permits, utilities, and all other items necessary for the Levi’s Stadium Radio Booth Cabling Project (the “Project”). At said time, bids will be opened and read aloud at the Stadium Manager Office. A bid opening will occur over a webcast shortly after the due date and time set forth above – details regarding the webcast are included in the Instructions to Bidders.
1.02 THE WORK
The Work will consist of:
The addition of supplementary broadcast cabling, raceway, and custom plates from the 800-level booths at Levi’s Stadium to the truck dock. The Work is further described in detail in the Technical Specifications attached hereto and the Plans and Specifications (attached hereto as Exhibit “B” and incorporated herein by reference).
1.03 SPECIAL INSPECTIONS/PERMITS
Contractor shall obtain all necessary permits and licenses for the construction of the Project, including encroachment permits, and shall pay all fees required by law and shall comply with all laws, ordinances, rules and regulations relating to the Work and to the preservation of public health and safety. Before acceptance of the Project, the Contractor shall submit all licenses, permits, certificates of inspection and required approvals to the Stadium Manager.
1.04 ADDITIVE/DEDUCTIVE BID ITEMS
There are no additive or deductive bid items specified for this Project.
1.05 CONTRACT TIME
The Contract Time for the completion of all of the Work of this Project is Ninety (90) calendar days from the Commencement Date in the Stadium Manager’s Notice to Proceed. Please see Section 00 73 13-1.12 (Special Conditions – Schedule Constraints) for additional information regarding schedule constraints.
1.06 LIQUIDATED DAMAGES
The liquidated damages rate is set forth in Document 00 73 13 (Special Conditions).
| 1.07 | BIDS MUST BE ADDRESSED TO the Stadium Manager. Bids must be submitted on the Stadium Manager’s Bid Forms. Bidders may obtain a copy of the Contract Documents online via Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/. Bidders must register online to view, download and submit bids. Bidders may register for free. For assistance related to technical questions on how to register with Bonfire, receive notifications via the e-procurement portal, and submit bids via the e-procurement portal, bidders should contact Bonfire at Support@GoBonfire.com. To the extent required by Section 20103.7 of the Public Contract Code, upon request from a contractor plan room service, the Stadium Manager shall provide an electronic copy of the Contract Documents at no charge to the contractor plan room. |
| 1.08 | BID GUARANTEE (BOND) |
| a. | Each bid shall be accompanied by cash, a certified or cashier’s check, or Bid Bond secured from a surety company satisfactory to the Stadium Manager, the amount of which shall not be less than ten percent (10%) of the submitted Total Bid Price, made payable to Forty Niners Stadium Management Company LLC as bid security. |
| b. | The bid security shall be provided as a guarantee that within fourteen (14) calendar days after the Stadium Manager provides the successful bidder the Notice of Award, the successful Bidder will enter into a contract and provide the necessary bonds and certificates of insurance. The bid security will be declared forfeited if the successful Bidder fails to comply within said time. No interest will be paid on funds deposited with Stadium Manager. If the Bidder intends on submitting a Bid Bond as its bid security, it shall do so through Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/. |
| c. | The Bid Bond uploaded shall be an identical scanned copy of the hardcopy original Bid Bond obtained by the Bidder, including all notary acknowledgments, signatures and seals, if any. If a Bidder is submitting cash or a certified or cashier’s check as bid security, these forms of bid security must be submitted by mail in a sealed envelope bearing the Bidder’s name, Project name and addressed as follows: |
4900 Marie P. DeBartolo Way Santa Clara, CA 95054 Attention: Procurement Lead Please be advised the bid security must be received by the Stadium Manager by the bid due date and time. Stadium Manager is not responsible for any carrier or delivery issues or delays and such will not excuse a late submission, which will be rejected.
1.09 ERRORS OR DISCREPANCIES IN THE BIDS
The Stadium Manager reserves the right to reject any and all Bids and to waive any errors or discrepancies in the Bids.
ARTICLE 2 – OTHER NOTICES
2.01 CONTRACTOR’S LICENSING REQUIREMENT
Unless otherwise provided in the Instructions for Bidders, each Bidder shall be a licensed contractor pursuant to Sections 7000 et seq. of the Business and Professions Code in the following classification(s) throughout the time it submits its Bid and for the duration of the contract:
· Class B - General Building Contractor OR
· Class C7 - Low Voltage Systems Contractor.
| 2.02 | COMPLIANCE WITH PREVAILING WAGE LAW |
| a. | Pursuant to Labor Code Section 1773, Stadium Manager has obtained the prevailing rate of per diem wages and the prevailing wage rate for holiday and overtime work applicable in Santa Clara County from the Director of the Department of Industrial Relations for each craft, classification, or type of worker needed to execute this contract. A copy of these prevailing wage rates may be obtained via the internet at: www.dir.ca.gov/dlsr/ |
| b. | In addition, a copy of the prevailing rate of per diem wages is available from the Stadium Manager and shall be made available to interested parties upon request. The successful bidder shall post a copy of the prevailing wage rates at each job site. It shall be mandatory upon the Bidder to whom the Contract is awarded, and upon any subcontractors, to comply with all Labor Code provisions, which include but are not limited to the payment of not less than the said specified prevailing wage rates to all workers employed by them in the execution of the Contract, employment of apprentices, hours of labor and debarment of contractors and subcontractors. |
| c. | Pursuant to Labor Code Sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No Bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a contract, the Bidder and its subcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1. |
| d. | This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Additionally, Bidders are advised of the requirements set forth in the Contract related to submission of documentation demonstrating compliance with applicable prevailing wage laws, the timely submission of which constitutes a condition of payment. Please be advised the Stadium Manager utilizes the LCPTracker platform and requires all contractors and subcontractors performing public works to submit compliance documentation outlined in the Contract through the LCPTracker platform. |
| e. | In bidding on this Project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance requirements under this contract and applicable law in its Bid. |
| 2.03 | PAYMENT AND PERFORMANCE BONDS AND INSURANCE |
The successful Bidder will be required to furnish a Faithful Performance Bond and a Labor and Material Payment Bond each in an amount equal to one hundred percent (100%) of the Contract Price. Each bond shall be in the forms set forth herein, shall be secured from a surety company that meets all State of California bonding requirements, as defined in California Code of Civil Procedure Section 995.120, and that is a California admitted surety insurer.
Insurance requirements are as set forth in the General Conditions. Bidders are directed to carefully review the insurance requirements therein.
2.04 SUBSTITUTION OF SECURITIES IN LIEU OF WITHHELD RETENTION
Pursuant to Section 22300 of the Public Contract Code of the State of California, the successful Bidder may substitute certain securities for funds withheld by Stadium Manager to ensure its performance under the contract.
2.05 PRE-BID CONFERENCE
A NON-MANDATORY In-Person Pre-Bid Conference and site walk is scheduled for September 25, 2025 at 9:30 a.m. at Levi’s Stadium to review the Project's existing conditions at Levi’s Stadium. Representatives of the Stadium Manager and consulting engineers, if any, will be present. Questions asked by Bidders at the Pre-Bid Conference not specifically addressed within the Contract Documents shall be answered in writing, and shall be posted on the Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/. At least forty-eight (48) hours prior to the scheduled date and time for the site walk, interested Bidders must provide the names and email addresses of all individuals attending the site walk on Bidder’s behalf. Please allow adequate time for security screening upon arrival. The Stadium Manager will provide Bidders information on where to enter and park at the stadium via email after the Bidder’s official request to attend the site walk is provided to the Procurement Lead.
2.06 BID PERIOD CLARIFICATIONS AND ADDENDA
a. Bidders must submit all requests for clarification, or interpretation of the Contract Documents in writing at least fourteen (14) calendar days before the deadline for receipt of Bids.
b. Stadium Manager may issue written Addenda as appropriate for clarification or other reasons during the bidding period.
c. Addenda will be posted on the Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/.
d. Stadium Manager is not responsible for any explanation or interpretation of the Bid Documents not communicated to Bidders via written addenda.
2.07 SUBSTITUTION
Substitution requests shall be made within seven (7) calendar days prior to the deadline for submission of bids specified above via submission of the Request for Approved Equals Form attached under Section 1.9 of the Bid Forms. Pursuant to Public Contract Code Section 3400(b), the Stadium Manager may make findings designating that certain additional materials, methods or services by specific brand or trade name other than those listed in the Standard Specifications be used for the Project. Such findings, if any, as well as the materials, methods or services and their specific brand or trade names that must be used for the Project may be found in the Special Conditions. Pursuant to Public Contract Code Section 3400(b), if the Stadium Manager has made any findings designating certain materials, products, things, or services by specific brand or trade name, such findings and the materials, products, things, or services and their specific brand or trade names will be set forth in the Special Conditions.
2.08 AWARD OF CONTRACT
Stadium Manager shall award the contract for the Project to the lowest responsible Bidder submitting a responsive bid as determined by the Stadium Manager from the Total Bid Price, which is calculated based upon BASE BID ALONE. Stadium Manager reserves the right to reject any or all bids or to waive any irregularities or informalities in any bids or in the bidding process.
For further information, contact us at PROC@49ERS-SMC.COM.
END OF NOTICE INVITING BIDS
00 21 13 – INSTRUCTIONS TO BIDDERS
SECURING DOCUMENTS
Bids must be submitted to the Stadium Manager on the Bid Forms which are a part of the Contract Documents for the Project. The Contract Documents may be obtained from Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/ as specified in the Notice Inviting Bids.
The Stadium Manager may also make the Contract Documents available for review at one or more plan rooms, as indicated in the Notice Inviting Bids. Please Note: Prospective Bidders who choose to review the Contract Documents at a plan room must utilize the Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/, in order to submit a bid for the Project.
Any addenda will be posted on Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/. Failure to acknowledge addenda may make a bid nonresponsive and not eligible for award of the contract.
EXAMINATION OF SITE AND CONTRACT DOCUMENTS
At its own expense and prior to submitting its Bid, each Bidder is strongly recommended to visit the site of the proposed work and fully acquaint itself with the conditions relating to the construction and labor required so that the Bidder may fully understand the work, including but not limited to difficulties and restrictions attending the execution of the work under the contract. Each Bidder shall carefully examine the Drawings, and shall read the Specifications, Contract, and all other documents referenced herein. Each Bidder shall also determine the local conditions which may in any way affect the performance of the work, including local tax structure, contractors’ licensing requirements, availability of required insurance, the prevailing wages and other relevant cost factors, shall familiarize itself with all federal, state and local laws, ordinances, rules, regulations and codes affecting the performance of the work, including the cost of permits and licenses required for the work, and shall make such surveys and investigations, including investigations of subsurface or latent physical conditions at the site or where work is to be performed as may be required. Bidders are responsible for consulting the standards referenced in the Contract. The failure or omission of any Bidder to receive or examine any contract documents, forms, instruments, addenda, or other documents, or to visit the site and acquaint itself with conditions there existing shall in no way relieve any Bidder from any obligation with respect to its Bid or to the contract and no relief for error or omission will be given except as required under State law. The submission of a Bid shall be taken as conclusive evidence of compliance with this Article.
INTERPRETATION OF DRAWINGS AND DOCUMENTS
Prospective Bidders unclear as to the true meaning of any part of the Drawings, Specifications or other proposed contract documents may submit to Stadium Manager a written request for interpretation via the clarification process established in the Notice Inviting Bids. The prospective Bidder submitting the request is responsible for timely delivery of the clarification request. Interpretation of the Drawings, Specifications or other proposed contract documents will be made only by a written addendum duly issued and a copy of such addenda will be made available to each prospective Bidder who has obtained a set of Drawings and Specifications through the Stadium Manager’s eProcurement Portal. The Stadium Manager will not be responsible for any other explanation or interpretations of the proposed documents. If a prospective Bidder becomes aware of any errors or omissions in any part of the Contract Documents, it is the obligation of the prospective Bidder to promptly bring it to the attention of the Stadium Manager.
ADDENDA
The Stadium Manager reserves the right to revise the Contract Documents prior to the bid submission deadline. Revisions, if any, shall be made by written Addenda. All Addenda issued by the Stadium Manager shall be included in the bid and made part of the Contract Documents. Pursuant to Public Contract Code Section 4104.5, if the Stadium Manager issues an Addendum which includes material changes to the Project less than 72 hours prior to the deadline for submission of bids, the Stadium Manager will extend the deadline for submission of bids. The Stadium Manager may determine, in its sole discretion, whether an Addendum warrants postponement of the bid submission date. Please Note: Bidders are responsible for ensuring that they have received any and all Addenda. To this end, each Bidder must register with Bonfire in order to access the Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/ to obtain all Addenda issued by the Stadium Manager, if any, prior to the bid submission deadline. The Bidder shall indicate the Addenda received prior to bidding in the space provided in the Bid Form. Failure to indicate all Addenda may be sufficient cause for rejecting the bid as determined by the Stadium Manager in its sole discretion.
ALTERNATE BIDS
If alternate bid items are called for in the Contract Documents, the time required for completion of the alternate bid items has already been factored into the Contract duration and no additional Contract time will be awarded for any of the alternate bid items. The Stadium Manager may elect to include one or more of the alternate bid items, or to otherwise remove certain work from the Project scope of work. Accordingly, each bidder must ensure that each bid item contains a proportionate share of profit, overhead, and other costs or expenses which will be incurred by the bidder.
COMPLETION OF BID FORMS
Bids shall only be prepared using copies of the Bid Forms which are included in the Contract Documents. The use of substitute Bid Forms other than clear and correct photocopies of those provided by the Stadium Manager will not be permitted. Bids shall be executed by an authorized signatory as described in these Instructions to Bidders. In addition, Bidders shall fill in all blank spaces (including inserting “N/A” where applicable), and initial all interlineations, alterations, or erasures to the Bid Forms. Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms nor make substitutions thereon. Except where bids are submitted via an electronic bidding platform, USE OF BLACK OR BLUE INK, INDELIBLE PENCIL, OR A TYPEWRITER IS REQUIRED. Deviations in the Bid Forms may result in the Bid being deemed non-responsive.
MODIFICATIONS OF BID FORMS
Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract Documents. Unauthorized additions, modifications, revisions, conditions, limitations, exclusions or provisions attached to a Bid may render it non-responsive and may cause its rejection. Bidders shall not delete, modify, or supplement the printed matter on the Bid Forms, or make substitutions thereon. Oral, telephonic and electronic modifications will not be considered.
SUBCONTRACTORS
Bidder shall set forth the name, address of the place of business, and contractor license number of each subcontractor who will perform work, labor, furnish materials or render services to the bidder on said contract and each subcontractor licensed by the State of California who, under subcontract to bidder, specially fabricates and installs a portion of the Work described in the Drawings and Specifications in an amount in excess of one half of one percent (0.5%) of the total bid price, and shall indicate the portion of the work to be done by such subcontractor in accordance with Public Contract Code Section 4104.
LICENSING REQUIREMENTS
Pursuant to Business and Professions Code Section 7028.15 and Public Contract Code Section 3300, all bidders must possess proper licenses for performance of this Contract. Subcontractors must possess the appropriate licenses for each specialty subcontracted. Pursuant to Business and Professions Code Section 7028.5, the Stadium Manager shall consider any bid submitted by a contractor not currently licensed in accordance with state law and pursuant to the requirements found in the Contract Documents to be nonresponsive, and the Stadium Manager shall reject the Bid. The Stadium Manager shall have the right to request, and Bidders shall provide within ten (10) calendar days, evidence satisfactory to the Stadium Manager of all valid license(s) currently held by that Bidder and each of the Bidder’s subcontractors, before awarding the Contract.
Notwithstanding anything contained herein, if the Work involves federal funds, the Contractor shall be properly licensed by the time the Contract is awarded, pursuant to the provisions of Public Contract Code Section 20103.5.
BID GUARANTEE (BOND)
Each bid shall be accompanied by: (a) cash; (b) a certified or cashier’s check made payable to Forty Niners Stadium Management Company LLC; or (c) a Bid Bond secured from a surety company satisfactory to the Stadium Manager, the amount of which shall not be less than ten percent (10%) of the Total Bid Price, made payable to Forty Niners Stadium Management Company LLC as bid security. Personal sureties and unregistered surety companies are unacceptable. The surety insurer shall be California admitted surety insurer, as defined in Code of Civil Procedure Section 995.120. The bid security shall be provided as a guarantee that within fourteen (14) calendar days after the Stadium Manager provides the successful bidder the Notice of Award, the successful bidder will enter into a contract and provide the necessary bonds and certificates of insurance. The bid security will be declared forfeited if the successful bidder fails to comply within said time, and Stadium Manager may enter into a contract with the next lowest responsive responsible bidder, or may call for new bids. No interest shall be paid on funds deposited with the Stadium Manager. Stadium Manager will return the security accompanying the bids of all unsuccessful bidders no later than 60 calendar days after award of the contract. If the Bidder intends on submitting a Bid Bond as its bid security, it shall do so through Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/. The Bid Bond uploaded shall be an identical scanned copy of the hardcopy original Bid Bond obtained by the Bidder, including all notary acknowledgments, signatures and seals, if any. If a Bidder is submitting cash or a certified or cashier’s check as bid security, these forms of bid security must be submitted by mail in a sealed envelope bearing the Bidder’s name, Project name and addressed as follows:
4900 Marie P. DeBartolo Way Santa Clara, CA 95054 Attention: Procurement Lead
IRAN CONTRACTING ACT OF 2010
In accordance with Public Contract Code Section 2200 et seq., the Stadium Manager requires that any person that submits a bid or proposal or otherwise proposes to enter into or renew a contract with the Stadium Manager with respect to goods or services of one million dollars ($1,000,000) or more, certify at the time the bid is submitted or the contract is renewed, that the person is not identified on a list created pursuant to subdivision (b) of Public Contract Code Section 2203 as a person engaging in investment activities in Iran described in subdivision (a) of Public Contract Code Section 2202.5, or as a person described in subdivision (b) of Public Contract Code Section 2202.5, as applicable.
The form of such Iran Contracting Certificate is included with the bid package and must be signed and dated under penalty of perjury.
NONCOLLUSION DECLARATION; PROCUREMENT AND CONTRACT PROCESS INTEGRITY AND CONFLICT OF INTEREST GUIDELINES Bidders on all public works contracts are required to submit a declaration of noncollusion with their bid. This form is included with the bid package and must be signed and dated under penalty of perjury.
Bidders are further directed to review and ensure full compliance with the Procurement and Contract Process Integrity and Conflict of Interest Guidelines, which are included in the Special Conditions.
PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION
Pursuant to Labor Code Sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a contract, the bidder and its subcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project. To this end, Bidder shall sign and submit with its Bid the Public Works Contractor Registration Certification on the form provided, attesting to the facts contained therein. Failure to submit this form may render the bid non-responsive. In addition, each Bidder shall provide the registration number for each listed subcontractor in the space provided in the Designation of Subcontractors form.
BIDDER INFORMATION AND EXPERIENCE FORM
Each Bidder shall complete the questionnaire provided herein and shall submit the questionnaire along with its Bid. Failure to provide all information requested within the questionnaire along with the Bid may cause the bid to be rejected as non-responsive. The Stadium Manager reserves the right to reject any Bid if an investigation of the information submitted does not satisfy the Stadium Manager’s Representative that the Bidder is qualified to properly carry out the terms of the contract.
WORKERS' COMPENSATION CERTIFICATION
In accordance with the provisions of Labor Code Section 3700, Contractor shall secure the payment of compensation to its employees. Contractor shall sign and file with the Stadium Manager the following certificate prior to performing the work under this Contract:
I am aware of the provisions of Section 3700 of the Labor Code, which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.
The form of such Workers' Compensation Certificate is included as part of this document.
SIGNING OF BIDS
All Bids submitted shall be executed by the Bidder or its authorized representative. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.
If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid; and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of Bidder assumed under the Bid and under any Contract arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.
SUBMISSION OF SEALED BIDS
Bids must be submitted through the Stadium Manager eProcurement Portal at:
https://49ers.bonfirehub.com/portal/
Submissions by any other method will not be accepted.
Minimum system requirements: Internet Explorer 11, Microsoft Edge, Google Chrome, or Mozilla Firefox. JavaScript must be enabled. Browser cookies must be enabled.
Bidders should contact Bonfire at Support@GoBonfire.com for technical questions related to submissions, or visit Bonfire’s help forum at https://bonfirehub.zendesk.com/hc.
Submission materials should be prepared in the file formats listed under Requested Information for this opportunity in the Portal. The maximum upload file size is 1000 MB. Documents should not be embedded within uploaded files, as the embedded files will not be accessible or evaluated. If the required bid form is mandatory, bidder will not be able to complete the submission until the requirement is met.
Bidder will receive an email confirmation receipt with a unique confirmation number once the submission is finalized. This will confirm that bidder has successfully submitted the bid.
OPENING OF BIDS
A bid opening will occur over a webcast shortly after the due date and time as referenced in Notice Inviting Bids.
Below is the information for attending the public bid webcast via Zoom:
Via: www.Zoom.us
· Click “Join a Meeting” in the bar on the right top
· Enter Meeting ID Number: 980 8431 9478
· Click Join Meeting
· Enter Meeting Password: 77777
· Enter the required contact information Join Zoom Meeting https://49ers.zoom.us/j/98084319478?pwd=262QsYbxqzBfAMLIuXk0LLRVSnbFcm.1 Via Phone
· Dial number: (669) 900-6833
· 877 853 5257 US Toll-free
It is the Bidder’s sole responsibility to ensure that its bid is received as specified. Bids may be submitted earlier than the date(s) and time(s) indicated in the Notice Inviting Bids.
The reading of each bid will include the following information:
B. The name of the Bidder.
C. The bid amount.
Bidders or their representatives and any other interested persons may participate in the virtual bid opening using the webcast information provided above. The Stadium Manager may, in its sole discretion, elect to postpone the opening of the submitted bids. The Stadium Manager reserves the right to reject any or all bids and to waive any informality or irregularity in any bid.
WITHDRAWAL OF BID
Any bid may be withdrawn online via Stadium Manager’s e-Procurement Portal, https://49ers.bonfirehub.com/portal/, at any time prior to the scheduled closing time for receipt of bids. Withdrawn bids may be resubmitted until the time and day set for the receipt of bids, provided that resubmitted bids are in conformance with the instructions herein.
Bids may be withdrawn after bid opening only by providing written notice to Stadium Manager within five (5) working days of the bid opening and in compliance with Public Contract Code Section 5100 et seq., or as otherwise may be allowed with the consent of the Stadium Manager.
BIDDERS INTERESTED IN MORE THAN ONE BID
No Bidder shall be allowed to make, file or be interested in more than one bid for the same work unless alternate bids are specifically called for. A person, firm or corporation that has submitted a sub-proposal to a Bidder, or that has quoted prices of materials to a Bidder, is not thereby disqualified from submitting a sub-proposal or quoting prices to other bidders. No person, firm, corporation, or other entity may submit a sub-proposal to a Bidder, or quote prices of materials to a Bidder, when also submitting a prime Bid on the same Project.
SUBSTITUTION OF SECURITY
The Contract Documents call for monthly progress payments based upon the percentage of the Work completed. The Stadium Manager will retain a percentage of each progress payment as provided by the Contract Documents. At the request and expense of the successful Bidder, the Stadium Manager will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.
PREVAILING WAGES
The Stadium Manager has obtained from the Director of the Department of Industrial Relations the general prevailing rate of per diem wages in the locality in which this work is to be performed for each craft or type of worker needed to execute the Contract. These rates are available from the Stadium Manager or may be obtained online at http://www.dir.ca.gov. Bidders are advised that a copy of these rates must be posted by the successful Bidder at the job site(s).
PREVAILING WAGE COMPLIANCE DOCUMENTATION
The Contract Documents require the successful Bidder to complete and submit various prevailing wage compliance documentation to Stadium Manager at various times during the course of the Project as a condition of payment. Bidders must take cognizance of these requirements and effect strict compliance with the same on behalf of Bidder and its subcontractors of every tier.
DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Labor Code Sections 1777.1 or 1777.7. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any money for performing work as a subcontractor on a public works contract. Any money that is paid to a debarred subcontractor by the Contractor for the Project shall be returned to the Stadium Manager. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the Project.
INSURANCE REQUIREMENTS
Prior to commencing work, the successful bidder shall purchase and maintain insurance as set forth in the General Conditions.
PERFORMANCE BOND AND PAYMENT BOND REQUIREMENTS
The successful bidder will be required to furnish a Labor and Material Payment Bond and a Faithful Performance Bond each in an amount equal to one hundred percent (100%) of the contract price. Each bond shall be secured from a surety company that meets all State of California bonding requirements, as defined in California Code of Civil Procedure Section 995.120 and is admitted by the State of California. Each bond shall be accompanied, upon the request of Stadium Manager, with all documents required by California Code of Civil Procedure Section 995.660 to the extent required by law. All bonding and insurance requirements shall be completed and submitted to Stadium Manager within fourteen (14) calendar days from the date the Stadium Manager provides the successful bidder with the Notice of Award.
SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES AND FEES
Contractor and its subcontractors performing work under this Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the Work will be located, unless otherwise expressly provided by the Contract Documents.
PERMIT AND INSPECTION FEE ALLOWANCE
Notwithstanding anything contained herein, if the Bid Form contains an allowance for the Contractor’s cost of acquiring permits and for construction inspection fees that may be charged to the Contractor by the Agency of Jurisdiction, the allowance is included within the Bid Form to eliminate the need by bidders to research or estimate the costs of permits and construction inspection fees prior to submitting a bid. The allowance is specifically intended to account for the costs of permits and construction inspection fees charged by the local Agency of Jurisdiction only. No other costs payable by Contractor to the Agency of Jurisdiction are included within the allowance.
FILING OF BID PROTESTS
Bidders may file a “protest” of a Bid with the Stadium Manager’s Procurement Lead. In order for a Bidder’s protest to be considered valid, the protest must:
Be filed in writing within seven (7) calendar days after the bid opening date;
Clearly identify the specific irregularity or accusation;
Clearly identify the specific Stadium Manager staff determination or recommendation being protested;
Specify in detail the grounds for protest and the facts supporting the protest; and Include all relevant, supporting documentation with the protest at time of filing.
If the protest does not comply with each of these requirements, the Stadium Manager may reject the protest without further review.
If the protest is timely and complies with the above requirements, the Stadium Manager’s designated Stadium Manager staff member, shall review the protest, any response from the challenged Bidder(s), and all other relevant information. The Stadium Manager will provide a written decision to the protestor.
The procedure and time limits set forth in this Article are mandatory and are the sole and exclusive remedy in the event of a Bid protest. Failure to comply with these procedures shall constitute a failure to exhaust administrative remedies and a waiver of any right to further pursue the Bid protest.
BASIS OF AWARD; BALANCED BID
The Stadium Manager shall award the Contract to the lowest responsible Bidder submitting a responsive Bid. The lowest Bid will be determined on the basis of the Total Bid Price, which is calculated based upon BASE BID ALONE.
The Stadium Manager may reject any Bid which, in its opinion when compared to other Bids received or to the Stadium Manager’s internal estimates, does not accurately reflect the cost to perform the Work. The Stadium Manager may reject as non-responsive any Bid which unevenly weights or allocates costs, including but not limited to overhead and profit to one or more particular bid items.
AWARD PROCESS
Once all Bids are opened and reviewed to determine the lowest responsive and responsible Bidder, the Stadium Manager may award the contract. The apparent successful Bidder should begin to prepare the following documents: (1) the Performance Bond; (2) the Payment Bond; and (3) the required insurance certificates and endorsements. Regardless of whether the Bidder supplies the required documents and certifications in a timely manner, the Contract time will begin to run thirty (30) calendar days from the date of the notification. Once the Stadium Manager receives all of the properly drafted and executed documents and certifications from the Bidder, the Stadium Manager shall issue a Notice to Proceed to that Bidder.
EXECUTION OF CONTRACT
As required herein the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract Documents. The Stadium Manager may require appropriate evidence that the persons executing the Contract are duly empowered to do so. The Contract and bond forms to be executed by the successful Bidder are included within these Specifications and shall not be detached.
QUESTIONS
Questions regarding this Notice Inviting Bids may be directed to Procurement Lead at PROC@49ERS-SMC.COM. No other members of the Stadium Manager’s staff or governing body should be contacted about this procurement during the bidding process. Questions must be communicated through the Stadium Manager’s eProcurement Portal, https://49ers.bonfirehub.com/portal/ unless otherwise instructed by the Stadium Manager. The Stadium Manager may, in its sole discretion, disqualify any Bidder who engages in any prohibited communications.
For assistance related to technical questions on how to register with Bonfire, receive notifications via the e-procurement portal, and submit bids via the e-procurement portal, bidders should contact Bonfire at Support@GoBonfire.com. Bidders can also visit their help forum at https://bonfirehub.zendesk.com/hc
00 41 43 – BID FORMS
1.1 BID.
Bids will be received by the Forty Niners Stadium Management Company LLC via its eProcurement Portal, https://49ers.bonfirehub.com/portal until 3:00 p.m. (PT) October 15, 2025.
NAME OF BIDDER: ______________________________________________
The undersigned hereby declare that we have carefully examined the location of the proposed Work, and have read and examined the Contract Documents, including all plans, specifications, and all addenda, if any for the following Project:
LEVI’S STADIUM RADIO BOOTH CABLING PROJECT
We hereby propose to furnish all labor, materials, equipment, tools, transportation, and services, and to discharge all duties and obligations necessary and required to perform and complete the Project, as described and in strict conformity with the Drawings, and these Specifications for TOTAL BID PRICE indicated herein.
The undersigned acknowledges receipt, understanding, and full consideration of the following addenda to the Contract Documents:
Addenda No. ________________________________________________
1. Attached is the required Bid Guarantee in the amount of not less than 10% of the Total Bid Price.
2. Attached is the completed List of Subcontractors form.
3. Attached is the completed Bidder Information and Experience form.
4. Attached is the fully executed Non-Collusion Declaration form.
5. Attached is the completed Iran Contracting Act Certification form.
6. Attached is the completed Public Works Contractor Registration Certification form.
7. Attached is the completed Contractor’s Certificate Regarding Workers’ Compensation form.
BID SCHEDULE
BASE BID SCHEDULE
NO.
ITEM DESCRIPTION
UNIT OF
MEASURE
ITEM
COST
| 1. |
| Radio Booth Cabling Project - See Section 1.a of the Technical Specifications for Base Bid Item No.1 scope summary. |
| LS |
*BIDDERS ARE ADVISED THE BID ITEM(S) SPECIFIED IN THE SCHEDULE ABOVE ARE INCLUSIVE OF ALL WORK REQUIRED TO COMPLETE EACH BID ITEM INCLUDING, WITHOUT LIMITATION, ALL GENERAL CONDITIONS, MOBILIZATION, VARIOUS TRADE WORK (I.E., METALS/STRUCTURAL STEEL, FINISH WORK, SPECIALTIES, MOCKUPS, ELECTRICAL), TRANSPORTATION, MATERIAL PROCESSING AND HANDLING, EQUIPMENT, MATERIALS, DEMOLITION, DISPOSAL, SUPERVISION, AND PROJECT MANAGEMENT.
BASE BID AMOUNT
The costs for any Work shown or required in the Contract Documents, but not specifically identified as a line item are to be included in the related line items and no additional compensation shall be due to Contractor for the performance of the Work.
In case of discrepancy between the Item Cost and Bid Amount, the Item Cost shall prevail and shall be utilized as the basis for determining the lowest responsive, responsible Bidder. However, if the amount set forth as an Item Cost is ambiguous, unintelligible or uncertain for any cause, or is omitted, then the amount set forth as the Bid Amount shall prevail.
The estimated quantities for bid line items are for purposes of comparing Bids only and the Stadium Manager makes no representation that the actual quantities of work performed will not vary from the estimates. Final payment shall be determined by the Stadium Manager’s Representative from measured quantities of work performed based upon the Item Cost.
TOTAL BID PRICE
The Total Bid Price is the amount specified below, which shall be used to determine the lowest Bid. The Total Bid Price includes the Base Bid Amount ONLY.
TOTAL BID PRICE: $
For purposes of evaluating Bids, the Stadium Manager will correct any apparent errors in the extension of unit prices, any apparent…