This is a Request for Quotations (RFQ) document issued by the Lehigh-Northampton Airport Authority for the procurement of one Passenger Boarding Bridge (PBB) Pre-Conditioned Air Unit (PCA) at Lehigh Valley International Airport. The solicitation, designated LNAA-CIP-26-001, seeks a 45-ton heating and cooling unit designed for mounting on the underside of an existing JBT A3-68/141-125R passenger boarding bridge. The unit must operate at 480V/60Hz/3-phase with a designed airflow of 240 lb/min and include all required hardware, hoses, junction boxes, and controllers for narrow-body aircraft and regional jet conditioning. The RFQ also includes an add-alternate option for in-person technical support during installation. Questions must be submitted by 4:00 p.m. on Thursday, May 21, 2026, via www.PennBid.net, with sealed quotations due by 4:00 p.m. on Thursday, May 28, 2026. Quotations will be opened publicly on May 28, 2026, at 4:00 p.m. at the LNAA Boardroom. No pre-bid conference or site inspection is required. The contract duration extends until successful commissioning of the unit, with all quotes remaining valid for 120 days.
Bidders must submit a bid bond equal to ten percent of the total proposal price, made payable to the Lehigh-Northampton Airport Authority. The successful bidder must provide performance and payment bonds each equal to 100 percent of the proposal amount. The base bid price must include the pre-conditioned air unit, all required accessories, virtual technical support for installation (with installation performed by LNAA maintenance staff), unit commissioning, and all freight charges. The Authority will award the contract to the lowest responsive and responsible bidder and will make award determinations within 120 calendar days of the bid opening date. No DBE participation goals are applicable to this solicitation. The prevailing wage requirement applies, and the successful bidder must comply with all applicable federal and state nondiscrimination laws, occupational safety and health requirements, and commercial nondiscrimination policies. All bidders must register on the PennBid website to access solicitation documents and submit their proposals electronically.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Quotations
For
Passenger Boarding Bridge (PBB) Pre-Conditioned Air Units (PCA)
At
Lehigh Valley International Airport
LNAA-CIP-26-001
April 28, 2026
TECHNICAL PROVISIONS
TABLE OF CONTENTS
at Lehigh Valley International Airport
Part I General Project Information .................................................................GI.01 thru GI.06
Part II LNAA General Provisions for Bidding of Contracts.............................GP.01 thru GP.03
Part III Technical Specifications.......................................................................TS.01 thru TS.01
PART 1
GENERAL PROJECT INFORMATION
LNAA-CIP-26-001
GI-1.01 Public Advertisement GI-1.02 Contract Summary GI-1.03 Notice to Companies GI-1.04 Non-Discrimination & Affirmative Action GI-1.05 Description of Quotation GI-1.06 Contract Duration
GI-1.01 Public Advertisement
REQUEST FOR QUOTATIONS
FOR
PASSENGER BOARDING BRIDGE (PBB) PRE-CONDITIONED AIR UNITS (PCA)
AT
LEHIGH VALLEY INTERNATIONAL AIRPORT
The Lehigh-Northampton Airport Authority is soliciting responses from Companies that meet the qualifications set forth herein to submit sealed quotations to provide quotations for one (1) Passenger Boarding Bridge (PBB) Pre-Conditioned Air Unit (PCA) to the Authority. All documents and solicitation details are available at no cost at www.PennBid.net.
Questions regarding this RFQ must be submitted by 4:00 P.M., Thursday, May 21, 2026, via www.PennBid.net. The Authority will respond to questions via in a timely manner.
Quotations MUST be submitted on or before 4:00 p.m., Thursday, May 28, 2026 via www.PennBid.net. The Lehigh-Northampton Airport Authority reserves the right to accept or reject any and all quotations, re-advertise or award the contract in a manner determined solely by the Authority to be in its best interest. All quotes shall remain valid for one hundred twenty (120) days.
Sealed quotations will be opened publicly, without virtual option, at the Lehigh-
Northampton Airport Authority Boardroom located 2nd Floor, Main Terminal, 3311 Airport Rd Allentown, PA 18109 at 4:00 p.m., Thursday, May 28, 2026.
Lehigh Valley Press: April 29, 2026
The Lehigh-Northampton Airport Authority, (in accordance with Title VI of the Civil Rights Act of 1974, 7B Stat. 252, 42 USC 2000D to 2000D-4 and Title 49, Code of the Federal Regulations, Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Nondiscrimination in Federal assisted program for the Department of Transportation issued pursuant to such Act) notifies all firms that it will affirmatively insure that Disadvantaged Business Enterprises will be afforded full opportunity to submit quotes in response to this invitation and will not be discriminated against on the grounds of race, color, sex or national origin in consideration for an award.
http://www.pennbid.net/ http://www.pennbid.net/
GI-1.02 Contract Summary
ITEM DESCRIPTION
Contract Title
Passenger Boarding Bridge (PBB) Pre-
Conditioned Air Units (PCA)
Contract Number
Applicable Standard Provisions
Standard Provisions, 2nd Edition, February 2022
DBE Participation Goal
N/A
Bond Requirements
☒ Bid (10%) ☐ Performance (100%)
☐Payment* (100%)
Prevailing Wage Required
☐YES ☒ NO
Project Location
☒ABE ☐XLL ☐N43
Contract Duration
Complete Upon Commissioning
Liquidated Damages
☐YES ☒NO
Pre-Bid Conference
Site Inspection
Questions Due
Thursday, May 21, 2026 at 4:00 PM via www.PennBid.net
Bids Due
Thursday, May 28, 2026, no later than 4:00 PM via www.PennBid.net
Bid Opening
Thursday, May 28, 2026 at 4:00 PM, in-person, LNAA Board Room
*Payment Bond required if Sub-Contractors are utilized
GI-1.03 Notice to Companies
The Standard Provisions are intended to describe and establish all requirements and standards for this quotation’s contract and shall be binding upon the parties’ signatory to the Contract. By submitting a bid for this Contract, the Company agrees to adhere to the requirements of all these Provisions. Lehigh-Northampton Airport Authority shall henceforth also be referred to as “The Airport Authority” or “LNAA”.
Sealed bids for the project entitled:
at
Lehigh Valley International Airport
Contract No. LNAA-CIP-26-001
Sealed bids will be received online via www.PennBid.net by:
Thursday, May 28, 2026, at 4:00 PM Local Time
No bids will be accepted after Thursday, May 28, 2026, at 4:00PM Local Time.
Interested bidders need to register on the PennBid website. Once registered, bidders can obtain all project documents and submit and update their bids online. The proposals require a Certified Check or Bid Bond in the amount of ten percent (10%) of the total proposal price. Such proposal security shall be made payable to “Lehigh-Northampton Airport Authority” as a guarantee of good faith and is to secure the Lehigh-Northampton Airport Authority from any loss by failure to comply with any of the terms of the proposal, and is to become the property of the Lehigh-Northampton Airport Authority as just and liquidated damages in case the successful bidder refuses or fails to enter into such contract or fails or refuses to furnish a performance bond within twenty (20) days of the award. The Airport Authority has the right at its sole discretion to reject any or all bids. The award of each bid package, if it is to be awarded, shall be made within one hundred twenty (120) calendar days of the date specified for publicly opening proposals, unless otherwise specified herein. Award of each bid package shall be made by LNAA to the lowest, qualified bidder whose proposal conforms to the cited requirements of LNAA for each individual bid package. Bidders are not required to bid on all bid packages; however, they are required to bid on all items in each bid package submitted. Where discrepancies in the unit bid prices occur, and where discrepancies in the product of the quantities and unit bid prices occur, and where discrepancies in the summation of the products occur, LNAA will make the necessary corrections and the corrected values will be used in LNAA’s consideration of proposals.
The successful bidder will be required to provide performance security in forms satisfactory to the Authority Solicitor consisting of either a performance bond or irrevocable letter of credit in the amount of 100% of the proposal. The Proposer shall be responsible for obtaining and maintaining the performance security in force from the date of execution until the date of the contract termination. All Bonds shall be secured by a guaranty or Surety Company listed in the latest edition of U.S. Treasury Circular 570, and the bond amount must be within the maximum amount specified for such company in Circular 570.
Plans, specifications, and other contract documents may be secured electronically through the PennBid website.
GI-1.04 Non-Discrimination and Affirmative Action
The Bidder agrees, unless exempt, to comply with the applicable federal regulation pertaining to nondiscrimination and affirmative action (generally Part 60-1 of Title 41 of the Code of Federal Regulations), but not limited to the Equal Opportunity Clause (41 C.F.R. Paragraph 60-1.4). which is incorporated by reference, the Affirmative Action Clause for Handicapped Workers (41 C.F.R. Paragraph 60-741.4) which is incorporated by reference, and the Americans with Disabilities Act, 42 U.S.C., Section 12101 et seq.
and the applicable Federal regulations. Bidder further agrees, unless exempt, to comply with the Pennsylvania Nondiscrimination Clause (16 Pennsylvania Code Paragraph
49.101 (D), which is incorporated by reference. Pursuant to the provisions of Act No. 222, October 27, 1955, as amended by Act No. 19, February 28, 1961, and in accordance with the provisions of the Governor's Code of Fair Practice, effective June 6, 1963, and the Regulations of the Pennsylvania Human Relations Commission, as approved by the Public Works Project will contain the following items:
A. Bidder agrees that it will comply with the provisions of the Pennsylvania Human
Relations Act in providing equal employment opportunities in connection with all work performed by the Bidder or any subcontractor or supplier at the job site pursuant to the Contract.
B. Bidder agrees that it will comply with the Non-Discrimination Policy of the Authority which provides that in the performance of the Contract, the Bidder will provide equal opportunity for all citizens regardless of race, color, religion, sex, sexual orientation, gender, gender expression, gender identity, national origin, or handicap/disability.
The Lehigh-Northampton Airport Authority, in accordance with Title VI of the Civil Rights Act of 1964, 7B Stat. 252, 42 USC 2000D to 2000D-4 and Title 49, Code of the Federal Regulations, Department of Transportation, Subtitle A, Office of the Secretary , Part 21, Nondiscrimination in Federal assisted program for the Department of Transportation issued pursuant to such Act) notifies all bidders that it will affirmatively ensure that Disadvantaged Business Enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, national origin (including limited English proficiency), creed, sex (including sexual orientation and gender identity), age, or disability be excluded from consideration for an award. Moreover, any company will be required to ensure that the company will not discriminate against any employee or applicant for employment or against any subcontractor applicant because of race, color, religion, sex, or national origin.
Compliance with Regulations: The Company (hereinafter includes consultants) will comply with the Title VI List of Pertinent Nondiscrimination Acts and the Authority’s (latest edition), which are herein incorporated by reference and made a part of this contract.
Solicitations for Subcontracts, Including Procurements of Materials and Equipment:
In all solicitations, either by competitive bidding, or negotiation made by the company for work to be performed under a subcontract, including procurements of materials, or leases of equipment, each potential subcontractor or supplier will be notified by the company of the Company’s obligations under this contract and the Nondiscrimination Acts And Authorities on the grounds of race, color, or national origin.
Information and Reports: The Company will provide all information and reports required by the Acts, the Regulations, and directives issued pursuant thereto and will permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by the Authority to be pertinent to ascertain compliance with such Nondiscrimination Acts. Where any information required of a company is in the exclusive possession of another who fails or refuses to furnish the information, the Company will so certify to the Authority, as appropriate, and will set forth what efforts it has made to obtain the information.
Sanctions for Noncompliance: In the event of a Company’s noncompliance with the Non-discrimination provisions of the contract, the Authority will impose such contract sanctions as may be determined to be appropriate, including, but not limited to:
a. Withholding payments to the company under the contract until the Company complies; and/or
b. Cancelling, terminating, or suspending a contract, in whole or in part.
Incorporation of Provisions: The Company will include the provisions included herein Section GI1.03 in every subcontract, including procurements of materials and leases of equipment, unless exempt by the Acts, the Regulations and directives issued pursuant thereto. The Company will take action with respect to any subcontract or procurement as the Authority may direct as a means of enforcing such provisions including sanctions for noncompliance. Provided, that if the Company becomes involved in, or is threatened with litigation by a subcontractor, or supplier because of such direction, the Company may request the Authority to enter into any litigation to protect the interests of the Authority. In addition, the Company may request the United States to enter into the litigation to protect the interests of the United States.
GI-1.05 Description of Quotation
The Company shall provide a quotation to provide the following. Further specifications may be found in Part III: Technical Specifications.
Base Bid: One (1) Passenger Boarding Bridge Pre-Conditioned Air Unit
The BASE BID includes the following:
□ One (1) Pre-Conditioned Air Unit
□ Required accessories related to the installation and operation of the PCA
□ Virtual technical support for installation (installation to be performed by LNAA)
□ Unit commissioning
□ Freight
Add Alternate: In-Person Technical Support
The ADD ALTERNATE includes the following:
□ One (1) Subject Matter Expert to be on-site as a technical advisor to LNAA Maintenance Department during PCA installation.
All equipment is to be accordance with the specifications and other Contract
Documents and any addenda thereto, designated by the Authority.
GI-1.06 Special Requirements
GI-1.06.1 Contract Duration
The contract shall be considered fulfilled upon successful commissioning of the Pre- Conditioned Air Unit (PCA).
PART II
GENERAL PROVISIONS FOR BIDDING OF CONTRACTS
Part II General Provisions for Bidding of Contracts GP-1.00 Bidding Requirements and Conditions GP-1.01 Preparation of Bid GP-1.02 Opening & Recording of Bids GP-1.03 Mistakes in Bids GP-1.04 Minor Irregularities/Informalities GP-1.05 Rejection of Individual Bids or Proposals GP-1.06 Responsibility/Qualifications of Bidder GP-1.07 Rejection of all Bids GP-1.08 Bid Evaluation and Award GP-1.09 Tie Bids GP-1.10 Bid Protests GP-1.11 Bid Conditions GP-2.00 Project Award and Execution of the Contract GP-2.01 Basis of Contract Award GP-2.02 Contract Award and Notice to Proceed GP-2.03 Execution of Contract GP-3.00 Overall Bidder Responsibility and Acknowledgements GP-3.01 Bid Bonds GP-3.02 Performance and Payment Bonds GP-3.03 Specifications References GP-3.04 Contract Provisions GP-3.05 Indemnity GP-3.06 Pennsylvania Prevailing Wage Act GP-3.07 Occupational Safety and Health Act of 1970 GP-3.08 Commercial Non-Discrimination GP-3.09 General Bidder Responsibilities and Legal Contract Requirements
The Part II General Provisions for Bidding of Contracts is intended to establish uniformity and consistency of specifications in all matters of the Authority’s construction contracts. The General Provisions as referenced by the edition date in the Technical Provisions and Bid Forms, are part of the Contract Documents and are binding upon the party’s signatory to the bid submission forms and contract. By proposing to undertake a project and submitting a bid, the Company certifies and agrees that they have reviewed, is familiar with, and will abide by the requirements of these General Provisions.
Part II General Provisions for Bidding of Contracts
GP-1.00 Bidding Requirements and Conditions
GP-1.01 Preparation of Bid
All Companies and Subcontractors are hereby instructed to conform to the requirements outlined in the project plans and specifications for supplies, materials, goods, and services, as a basis for the preparation of all bids including alternates (add or deduct/delete).
The failure to comply with this requirement may result in the disqualification of the subject bid as non-responsive.
Should a disqualification occur due to the Company’s failure to comply with this requirement, no claim of any sort shall be made or allowed for the reimbursement of any cost associated with the preparation of the bid, or any other cost associated with preliminary work.
All bidders are required to complete and upload to www.PennBid.net the following:
1. All documents included within the Bid Book should be completed and signed. A copy of the Bid Bond must be attached in the appropriate section of www.PennBid.net.
2. A completed Schedule of Values .xlsx form.
Failure to provide the above referenced documentation can result in a non-responsive bid.
All submitted documents will be used to evaluate the bidder as being responsive, and responsible as outlined in Section GP-1.05.
The Authority is not accepting mailed bids. Bids shall be submitted via www.PennBid.net.
No Bidder shall be allowed to offer more than one (1) price on each item even though he/she may feel that there are two (2) or more types or styles that will meet specifications. Bidders must determine for themselves which to offer. If said Bidder should submit more than one (1) price on any item, all prices for that item may be rejected at the discretion of the Procurement Manager.
GP-1.02 Opening & Recording of Bids
Bids shall be opened publicly at the time and date designated in the general information and bid invitation. The bids shall be opened in the Lehigh-Northampton Airport Authority Board Room (2nd Level Main Terminal, 3311 Airport Road, Allentown, PA 18109) through www.PennBid.net. The name of each bidder, the total sum base bid price, and such other information as is deemed appropriate shall be read aloud.
http://www.pennbid.net/ http://www.pennbid.net/
Formal bids or amendments thereto received by the Authority after the time specified for bid opening shall not be accepted via www.PennBid.net. Bids cannot be received after this time and thus will not be accepted.
GP-1.03 Errors in Bids
A bidder may correct errors discovered before the time and date of the bid opening by correcting the applicable information through www.PennBid.net.
Bids that have been submitted on www.PennBid.net may be withdrawn and, if desired resubmitted, at any time prior to the specified time of opening.
If the Authority knows or has reason to conclude that a mistake may have been made, the bidder may be required to confirm the bid. Situations in which confirmation may be requested include obvious, apparent errors on the face of the bid or a bid unreasonably lower than the other bids submitted. If the bidder alleges mistake, the bid may be corrected or withdrawn upon written approval of the Authority, provided the following conditions are met:
1. If the mistake and intended correction are clearly evident on the face of the bid document, the bid shall be corrected to the intended correct bid and may not be withdrawn. Examples of mistakes that may be clearly evident on the face of the bid document are typographical errors, clerical errors, errors in extending unit prices, transposition errors, and arithmetical errors.
a. When an error is made in extending total prices, the unit bid price shall govern.
Carelessness in quoting prices, or in preparation of bid, otherwise, will not relieve the Bidder.
2. A bidder may be permitted to withdraw a low bid if:
a. A mistake is clearly evident on the face of the bid document, but the intended correct bid is not similarly evident; or
b. The bidder submits proof of evidentiary value which clearly and convincingly demonstrates that a mistake was made.
Mistakes may not be corrected after award of the Contract except when the Authority makes a determination that it would be unconscionable not to allow the mistake to be corrected. Changes in total sum prices are not permitted. Corrections shall be submitted to and approved by the Authority.
GP-1.04 Minor Irregularities/Informalities
Minor irregularities or informalities in bids, as defined below, may be waived if the Authority determines that it shall be in its best interest. The Authority may either give a bidder an opportunity to cure any deficiency resulting from a technicality or minor irregularity in its bid or waive the deficiency where it is to the Authority’s advantage to do so.
During the public opening of bids, if a bid appears to be irregular as herein specified, this fact may be announced when read and documented accordingly. The bid and the said irregularity will be considered by the Authority in accordance with these General provisions, law and regulations.
The Authority reserves the right to waive minor differences in specifications provided these differences http://www.pennbid.net/ do not violate the specifications intent nor affect the operation for which the items are being purchased, nor increase estimated maintenance and repair cost to the Authority. The Authority reserves the right to award contracts or place orders on a lump sum or individual item basis, or such combination as shall, in its judgment, be in the best interest of the Authority.
GP-1.05 Rejection of Individual Bids or Proposals
Any bid may be rejected in whole or in part when it is in the best interest of the Authority to do so.
Reasons for rejection of a bid may include but are not limited to:
1. The bid is non-responsive i.e., it does not conform in all material respects to the solicitation or bid package.
2. Unreasonable price.
3. The bidder submitting the bid is determined to be non-responsible through the
Authority’s scoring criteria. A determination of non-responsibility may be made for, but is not limited to, any of the following reasons, as identified below:
a. Bidder debarred from performing construction work or ineligible to perform the work and period of debarment or ineligibility has not expired.
b. The unit prices contained in the bid are unbalanced.
c. Evidence of collusion among bidders.
d. Inadequate ability, capacity, quantity and/or quality of experience, plant, equipment, financing, manpower or other resources required to perform the contract.
e. The sufficiency of the financial resources and ability of the Bidder to fulfil the contract or provide the service.
f. Bidder's workload which, in the judgment of the Authority, might hinder or prevent the prompt completion of the subject work if awarded.
g. Default by the bidder on other contracts.
h. Failure to pay or satisfactorily settle all reasonable and just bills due for labor and material on prior or current contracts.
i. The same person has an interest in more than one bid on a contract exclusive of being named by another bidder as a subcontractor.
j. Failure to perform satisfactorily on other contracts awarded, and the conditions leading to unsatisfactory performance remain unresolved.
k. The character, integrity, reputation, judgment, experience, and efficiency of the Bidder.
l. The Bidder’s previous and present compliance with laws and ordinances relating to the contract or service.
m. The ability of the Bidder to provide future maintenance and service for the use of the subject of the contract.
n. Whether the Bidder is in arrears to the Authority on a debt or contract or is a defaulter on surety to the Authority.
o. Such other information as may be secured having a bearing on the decision to make the award.
p. Any other reason affecting the bidder’s ability to perform, or record of business integrity.
q. Bidder not otherwise qualified and eligible to receive an award under applicable laws and regulations.
r. Bidder who has previously failed to perform properly or complete on time contracts with the Authority.
s. The bidder or offeror fails to supply information to the Authority promptly, after notification from the Authority that such information is required in connection with a determination to be made pursuant to the information listed above.
GP-1.06 Responsibility/Qualifications of Bidder
The Authority may make such investigations as it deems necessary to determine the ability of the Bidder to perform the work, and the Bidder shall furnish to the Authority all such information and data for this purpose as the Authority may request. The Authority reserves the right to reject any bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the Authority that such Bidder is properly qualified to carry out the obligation of the contract and to complete the work contemplated therein. Conditional bids will not be accepted in determining responsibility. In determining responsibility, the Procurement Manager shall review and evaluate the Company’s Qualifications and bid submittal package. If the bidder submitting the lowest numerical bid is found to be non-responsible, the Authority will afford the bidder the opportunity for a responsibility hearing. Following the responsibility hearing, the Authority and/or the Executive Director shall make a final determination as to the bidder’s responsibility. Such determination shall be final.
No proposal shall be accepted from, or contract awarded to any person, firm or corporation that is in arrears or is in default to Lehigh-Northampton Airport Authority upon any debt or contract, or that is a defaulter, as surety or otherwise, upon any obligation to said Authority, or had failed to perform faithfully any previous contract with the Authority. The Bidder, if requested, must present prior to the Notice of Award evidence satisfactory to the Procurement Manager of performance ability and possession of necessary facilities, pecuniary resources, and adequate insurance to comply with the terms of these specifications and contract documents.
The successful Bidder shall inform the Procurement Manager of any and all circumstances which may impede the progress of the work or inhibit the performance of the contract including, but not limited to bankruptcy, dissolution or liquidation, merger, sale of business, assignment, etc.
The Authority may examine the Bidder’s and any first-tier subcontractor’s records to determine and verify compliance with the contract. The Bidder and any first-tier subcontractor must grant the Authority access to these records at all reasonable times during the contract term and for three (3) years after final payment. If the contract is supported to any extent by Federal or State funds, the appropriate Federal or State authorities may also examine these records. The Bidder must include the preceding language of this paragraph in all first-time subcontracts.
GP-1.07 Rejection of all Bids
After opening of bids or proposals but before award is provided, all bids or proposals may be rejected in whole or in part when the Authority, with the approval of the Executive Director or their designee, determines that this action is fiscally advantageous or otherwise in the Authority’s best interest.
A notice of rejection of all bids shall be sent to all vendors that submitted bids through www.PennBid.net, along with written correspondence from the Authority stating as such.
GP-1.08 Bid Evaluation and Award
The Contract is to be awarded to the responsible and responsive bidder whose bid meets the requirements and evaluation criteria set forth in the invitation for bids and is either the lowest base bid price or lowest evaluated base bid price.
Bids shall be evaluated to determine which bidder offers the lowest cost to the Authority in accordance with the evaluation criteria outlined in Section GP-1.05.
Except as otherwise provided under GP-1.03 Mistakes in Bids, the Authority reserves the right to correct any and all discrepancies contained in a bid or proposal cost as follows:
1. The written total sum base bid on the bid forms shall govern in the event of a discrepancy between the written total sum base bid and the input figures.
2. The written total sum base bid on the bid forms shall govern in the event of a discrepancy between the written total sum base bid and the figures inputted directly into www.PennBid.net.
3. The unit price will govern in the event of a discrepancy between the unit price bid and the extended price (product of unit price multiplied by the quantity).
4. The sum of the extended prices will govern in the event of a discrepancy between the total lump sum bid and the extended prices.
5. If a unit price has been omitted, the unit price will be determined by dividing the extended price by the quantity.
The Authority reserves the right to make the award by item, or groups of items, or total bid if it is in the best interest of the Authority to do so unless the bidder specifies in their bid that a particular or progressive award is not acceptable.
Upon determination of the lowest bidder, review of the bid for responsiveness, and satisfaction that the bidder is responsible, the Contract may be awarded to that bidder. A contract may be awarded to a bidder offering a higher quality item than that designated in the invitation for bids if that bidder is also the lowest responsive and responsible bidder.
GP-1.09 Tie Bids
Tie bids are responsive bids from responsible bidders that are identical in price, terms and conditions and which meet all the requirements and evaluation criteria set forth in the invitation for bids.
If two (2) or more Bidders shall be tied for the lowest bid on a purchase contract, quality and service being equal, the contract shall be awarded to a local Bidder. If there is no local Bidder, or more than one local Bidder, the Authority shall award the contract to one (1) of the Bidders by drawing lots in public.
GP-1.10 Bid Protests
A bid protest must be in writing and filed with the Authority. Oral objections, whether or not acted on, are not protests.
Right to Protest: A bidder or offeror, a prospective bidder or offeror, or a prospective company that is aggrieved in connection with the solicitation or award of a contract, may protest to the Executive Director of the Authority in writing.
1. Time for
Filing: A bid protest shall be filed not later than seven (7) days after the aggrieved bidder knew or should have known of the facts giving rise to the protest except that in no event may a protest be filed later than seven days after the date the contract was awarded.
If the protestant is a prospective bidder, a protest shall be filed with the Authority prior to the bid opening time or the proposal receipt date. If a prospective bidder fails to file a protest or files an untimely protest, the bidder or prospective bidder shall be deemed to have waived its right to protest the solicitation or award of the contract in any forum.
Untimely filed protests shall be disregarded by the Authority.
2. Contents of
Protest: A protest shall state all grounds upon which the protestant asserts the solicitation or award of the contract was improper. The protestant may submit with the protest any documents or information it deems relevant to the protest.
3. Response and
Reply: Within fifteen (15) days of receipt of a protest, the Authority may submit to the protestant a response to the protest, including any documents or information deemed relevant to the protest. The protestant may file a reply to the response within ten (10) days of the date of the response.
4. Evaluation of
Protest: The Executive Director of the Authority or his designee shall review the protest and any response or reply and may request and review such additional documents or information he deems necessary to render a decision and may, at his sole discretion, conduct a hearing. The Executive Director of the Authority or his designee shall provide to the protestant and the contracting officer a reasonable opportunity to review and address any additional documents or information deemed necessary by the Executive Director of the Authority or his designee to render a decision.
5. Determination
a. Upon completing an evaluation of the protest, the Executive Director of the Authority or their designee shall issue a written determination stating the reasons for the decision.
The determination shall be issued within sixty (60) days of the receipt of the protest unless extended by consent of the Authority or his designee and the protestant. The determination shall be the final order of the Authority. If the Executive Director of the Authority or his designee determines that the solicitation or award or the contract was contrary to law, the following apply:
1. If the determination is made prior to the execution of a contract, the remedies are limited to cancellation of the solicitation or proposed award or revision of the solicitation or proposed award to comply with the law.
2. If the determination is made after the execution of a contract and the person awarded the contract has not acted fraudulently or in bad faith:
2.1. The contract may be ratified and affirmed, provided it is determined by the head of the purchasing agency or their designee that doing so is in the best interest of the Commonwealth.
2.2. The contract, with the consent of all parties, may be modified to comply with the law; or:
2.3. The contract may be terminated, and the person awarded the contract shall be compensated for the actual expenses reasonably incurred under the contract prior to the termination. Such compensation shall not include loss of anticipated profit, loss of use of money or administrative or overhead costs.
3. If the determination is made after the execution of a contract and the person awarded the contract has acted fraudulently or in bad faith:
3.1. the contract may be ratified and affirmed, provided it is determined by the head of the purchasing agency or his designee that doing so is in the best interest of the Commonwealth and without prejudice to the right of the Authority to damages as may be appropriate.
3.2. the contract, with the consent of all parties, may be modified to comply with the law; or
3.3. the contract may be declared void.
Stay of Procurement During Pendency of Protest: If a protest is filed timely under this section and until the time has elapsed for the protestant to file the Notice of Appeal with the Executive Director of the Authority, the Authority shall not proceed further with the solicitation or with the award of the contract unless and until the Executive Director of the Authority makes a written determination that the protest is clearly without merit or that award of the contract without delay is necessary to protect substantial interests of the Commonwealth.
Appeal: Within fifteen (15) days of the mailing date of the final determination denying a protest, a protestant may file with the Executive Director of the Authority notice that he, she, or it appeals the final determination and invokes the right to arbitration. Issues not raised by the protestant before the Executive Director of the Authority are deemed waived and may not be raised at the Arbitration.
The Arbitration shall be conducted by Judicial Arbitration and Mediation Services (JAMS) of Philadelphia under the JAMS Code of Procedure then in effect. The Arbitration is binding on all parties to the Arbitration. An award or decision may be entered as a judgment in any Court having jurisdiction.
Within fourteen (14) days after filing of the Notice of Appeal, the protestant and the Authority shall select an Arbitrator from the JAMS panel. If the parties are unable to agree on an Arbitrator, JAMS shall select an Arbitrator who is a retired Judge of the United States or of the Commonwealth of Pennsylvania.
Record of Determination: The record of determination for review by the Arbitrator shall consist of the solicitation or award; the contract, if any; the protest; any response or reply; any additional documents or information considered by the Executive Director of the Authority or his designee;
hearing transcripts and exhibits, if any; and the final determination.
Standard of Review: The Arbitrator shall determine the matter on the record of determination certified to him or her by the Authority. No other evidence shall be presented to the Arbitrator.
The Arbitrator shall affirm the determination of the Executive Director of the Authority or their designee unless the Arbitrator finds from the record that the determination is arbitrary and capricious, an abuse of discretion or is contrary to law.
Proceeding and Disposition by the Arbitrator: The parties to the Arbitration shall file Briefs with the Arbitrator within twenty (20) days after the appointment of the Arbitrator. The Arbitrator shall file his or her decision within forty-five (45) days after the Briefs have been filed.
Remedy: If the final determination of the Executive Director or their designee is not affirmed because it is contrary to law, then the Arbitrator shall cancel the solicitation or award, and declare void any resulting contract.
The expenses and fees of the Arbitrator, together with other fees, shall be borne equally by the protestant and the Authority.
This Section GP-1.08 shall be the exclusive procedure for protesting an Authority solicitation or award of a contract by a bidder, offeror, prospective bidder or prospective offeror, or a prospective company that is aggrieved in connection with the solicitation or award of a contract. The provisions of 2 Pa. C.
S. shall not apply to this procedure.
GP-1.11 Bid Conditions
Unless otherwise specified by the Authority or by the Bidder, the Authority reserves the right to make an award on all items, or on any of the items according to the best interests of the Authority. Bidder may restrict his/her bid to consideration in the aggregate by so stating but should name a unit price on each item bid upon; any bid in which the bidder names a total price for all the articles without quoting a price on each and every separate item identified in the schedule of values, may be rejected at the option of the Authority.
Each Bidder shall submit where necessary or when requested by the Procurement Manager, catalogs, descriptive literature, and detailed drawings, fully detailing features, designs, construction, finishes and the like necessary to fully describe the materials or work they propose to furnish.
By submitting a bid, the Bidder agrees to the following:
A. Save the Authority, its agents, and employees harmless from liability of any nature or kind for the use of any copyrighted or un-copyrighted composition, secret process, patented or unpatented, invention, article or appliance furnished or used in the performance of the contract which the Bidder is not the patentee, assignee, licensee, or owner.
B. Protect the Authority against latent defective material or workmanship and to repair or replace any damages or marring occasioned in transit or delivery.
C. Furnish adequate protection against damage to all work and to repair damages of any kind, to the building or equipment, to their own work or to the work of other contractors, for which their worker is responsible due to the negligence in the course and scope of the employment.
D. Pay for all permits, licenses and fees and give all notices and comply with all laws, ordinances, rules and regulations of the Authority and State of Pennsylvania.
GP-2.00 Project Award and Execution of the Contract
GP-2.01 Basis of Contract Award
The Authority will award this Contract to the responsible and responsive bidder whose bid meets the requirements and evaluation criteria set forth in the invitation for bids and is either the lowest price or lowest evaluated bid price, based on the total sum base bid and any combination of Add or Deduct Alternates included in the Contract Documents, whichever is in the best interest of the Airport Authority. All required documents identified in Section GP-1.01 (Bid Book and Schedule of Values .xlsx sheet) must have a formal response with submission of each bid and will be included in consideration of award.
GP-2.02 Contract Award
Basis of Award: The Authority to provide a bid evaluation and review of each company’s submitted bid for scope understanding, confirmation of required bid submittal items and contract language. This may require a meeting with each company for a submission review. Confirmation of all grant requirements (if applicable) will be included in this review. All other required bid documentation will be reviewed per the project plans and specifications to ensure conformance. This includes the review and rating of the Bidder to ensure bid responsiveness and that the bidder is responsible. After this review, the lowest responsible and responsive company will be recommended to the Lehigh- Northampton Airport Authority Board of Governors for approval (as required). Upon acceptance, the Notice of Award will be issued.
Notice of Award (NOA): NOA will initiate the process of the awarded bidder (company) to provide the necessary contract documents to further validate compliance with the project plans and specifications. Upon review by the Authority and its representative, should any of the requested documents outlined below deem the company unable to perform the project as identified during the bid submission, the NOA will be rescinded and the next lowest, responsive, and responsible company will be contacted.
The responsible Bidder shall provide the Authority with the following (all within twenty (20) calendar days):
a. Certificate of Insurance
b. Required bonds (performance/labor and material, if applicable)
c. Preliminary schedule (if applicable)
d. Name and Email of two individuals who will be signing the contractual agreement (identify
Execution and Attest for each) (only applicable if contract is required)
e. W-9 Request for Taxpayer Identification Number and Certification
f. LNAA Electronic Fund Transfer (EFT) form
Upon review and acceptance of the above-referenced documents, the Authority will provide the contractual agreement to the identified parties through DocuSign for signature and execution. The bidder will execute the contractual agreement through DocuSign within ten (10) days after receipt.
Once the agreement is fully executed, the Company may begin mobilization
GP-2.03 Execution of Contract
The Contract shall be effective only upon receipt by the Authority, executed Contract Forms, and Performance and Payment Bonds (if required), approval by the Authority’s Board of Governors, (if required), and execution of the Contract by the Authority.
As stated in Section GP-P2.02, the Authority will provide the contractual agreement to the identified parties through DocuSign for signature and execution once all the conditions of the NOA have been fulfilled. The bidder will execute the contractual agreement through DocuSign within ten (10) days after receipt.
The Authority will provide the Contractual agreement to the Bidder within ten (10) days of receiving the requested NOA documents. If the Authority fails to execute the Contract and the period of irrevocability has expired, the bidder may, as its sole remedy, withdraw its bids.
Failure of the bidder to execute the Contract and file acceptable security as defined in Section GP-3.02 within the allotted time shall be just cause for the annulment of the award and the forfeiture of the Proposal Guaranty which shall become the property of the Authority, not as a penalty but in liquidation of damages sustained. Award may then be made to the next lowest responsive, responsible bidder or the work may be re- advertised and constructed under contract or otherwise, as the Authority may decide.
GP-3.00 Overall Bidder Responsibility and Acknowledgements
GP-3.01 Bid Bonds
Bid Deposit - Bid Bond, Certified or Cashier’s Check: When required, each bid shall be accompanied by a bid bond signed by a surety company licensed to do business in the State of Pennsylvania, or by a cashier’s check, certified check or Treasurer’s check drawn on a responsible bank doing business in the United States in the amount of ten (10%) percent of the total Bid and shall be made payable to the “Lehigh-Northampton Airport Authority”.
When computing the amount of Bid for Check purposes, DO NOT deduct for trade-ins. U.S.
Postal Money Orders are acceptable in lieu of checks.
GP-3.02 Performance and Payment Bonds
Performance and Payment Bonds: I f a p p l i c a b l e , The successful Bidder must furnish the required bonds as indicated, made out to the “ Lehigh-Northampton Airport Authority”, prepared on industry standard forms, or on an approved equal if necessary, as security for the faithful performance of the Bidder’s contract, within t w e n t y (20) calendar days after receiving Notice of Award (NOA). The surety thereon must be such surety company or companies as are authorized and licensed to transact business in the State of Pennsylvania. Attorneys in fact who sign bonds must file with each bond a certified copy of his/her power of attorney to sign bonds.
The successful Bidder or Bidders upon failure or refusal to furnish, within twenty (20) calendar days after receiving Notice of Award, the required bonds shall forfeit to the Authority, as liquidated damages his/her bid bond. The Performance Bond shall be in the amount of one hundred (100%) percent of the project cost; and the Labor and Materials Payment Bond shall be in the amount of one hundred (100%) percent of sub-contracted labor and unpaid materials cost.
GP-3.03 Specifications References
Formal Specifications: The Bidder shall abide by and comply with the true intent of the specifications and not take advantage of any unintentional error or omission but shall fully complete every part as the true intent and meaning of the specifications and drawings. Whenever mention is made herein, of any article, material, or workmanship to be in accordance with laws, ordinances, building codes, underwriter’s codes, A.S.T.M. regulations or similar expressions, the requirements of these laws, ordinances, etc., shall be construed to meet or exceed specification requirements and current established noise levels for specific equipment, materials, and/or services being furnished under this contract. All deviations from the specifications must be noted in detail by the Bidder, in writing, at the time of submittal of the formal bid. The absence of a written list of specification deviations at the time of submittal of the bid will hold the Bidder strictly accountable to the Authority to the specifications as written.
Any deviation from the specifications as written not previously submitted, as required by the above, will be grounds for rejection of the material and/or equipment when delivered.
Samples: The Procurement Department reserves the right to retain or destroy the samples submitted for the purpose of evaluation and will be free from any redress or claim on the part of the Bidder if any samples are lost or destroyed. Bidders shall make all arrangements for delivery of samples to the place designated, as well as the removal of samples. The cost of delivery and removal of samples shall be borne by the Bidder. Upon notification by the Procurement Department that a sample is available for pickup, it shall be removed within thirty
(30) calendar days at the Bidder’s expense, or the Procurement Manager shall dispose of same at his/her discretion. All sample packages shall be marked “Sample for Procurement Department” and each sample shall bear the name of the Bidder, item number, project number, and shall be carefully tagged or marked in a substantial manner. Failure of the Bidder to clearly identify samples as indicated may be considered sufficient reason for rejection of bid.
Trade Names/Substitutions: In cases where an item is identified by a manufacturer’s name, trade name, catalog number, or reference it is understood that the Bidder proposes to furnish the item so identified and does not propose to furnish an “equal/substitution” unless submission of an “equal/substitution” is stated otherwise as permissible. Any Bidder who contemplates offering a product that differs from that specified must obtain the Authority’s written approval by submission of his/her request no later than the deadline for receipt of substitution requests as stated in the bid documents. The reference to the above catalog is intended to be descriptive but not restrictive and only to indicate to the prospective Bidder articles that will be satisfactory. Bids on makes and catalogs will be considered, provided each Bidder clearly states on the face of his/her proposal exactly what he/she proposes to furnish, and forwards with his/her bid, a cut, illustration, or other descriptive matter which will clearly indicate the character of the article covered by his/her bid. The Procurement Manager hereby reserves the right to approve as an equal, or to reject as not being an equal, any article the Bidder proposes to furnish which contains major or minor variations from specification requirements but may comply substantially therewith. If no particular brand, model, or make is specified, and if no data are required to be submitted with the bid, and after award and before manufacture or shipment, the successful Bidder may be required to submit working drawings or detailed descriptive data sufficient to enable the Procurement Manager to judge if each requirement of the specifications is being complied with.
GP-3.04 Contract Provisions
The entire contract agreement to be executed by the lowest, responsive, and responsible bidder as outlined in these General Provision documents is included in Part VI – Sample Contract Agreement of the entire bid package. Bidders should be familiar with the language included in the contract to be executed prior to commencement of this project, along with the provisions listed below. This list is not all encompassing but serves as a supplement.
Availability of Funds: A contract shall be deemed executory only to the extent of appropriations available to each Authority department/agency for the purchase of such articles.
The Authority’s extended obligation on those contracts that envision extended funding through successive fiscal periods shall be contingent upon actual appropriations for the succeeding fiscal year.
Contract Alterations: No alterations or variables in the terms of a contract shall be valid or binding upon the Authority unless made in writing and signed by the Authority or its authorized agent.
Default: The contract may be cancelled or annulled by the Authority in whole or in part by written notice of default to the Bidder upon non-performance or violation of contract terms. An award may be made to the next low Bidder, or articles specified may be purchased on the open market similar to those so terminated. In either event, the defaulting Bidder (or their surety) shall be liable to the Authority for costs to the Authority in excess of the defaulted contract prices:
provided, that the Bidder shall continue the performance of this contract to the extent…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .