3. Submittal Register (SMYU 26-1029).pdf

PDF 107 KB Posted

Attached to
[MATOC AREAIII WORKPLAN ONLY] SMYU 26-1029 REPLACE RADIO ANTENNA PLATFORM HILL 180
Solicitation number
W90VN625RA017
Issued by

About this file

The document is a Submittal Register for the SMYU 26-1029 project to replace a radio antenna platform at Hill 180, Osan Air Base, Republic of Korea. The register comprehensively lists 76 required submittals across multiple specification sections, including preconstruction submittals, shop drawings, product data, test reports, certificates, and closeout documents. Key submittal categories include project scheduling, safety plans, quality control, environmental protection, equipment documentation, concrete and steel fabrication details, welding procedures, coating information, and soil bearing tests.

Submittals are categorized by specification section and require various documentation such as initial project schedules, safety plans, activity hazard analyses, crane operation plans, equipment records, fabrication drawings, material certifications, test reports, and as-built documentation. Many submittals are marked with a "G" classification, indicating government review is required. The submittal register is part of a solicitation limited to existing Multiple Award Task Order Contract (MATOC) contractors for Area III, covering Osan and Suwon Air Bases, with proposals to be submitted through the Procurement Information Exchange Environment (PIEE) system.

View the file

Other files

File Type Posted
1. Statement of Work (SMYU 26-1029).pdf PDF
Solicitation - W90VN625RA017.pdf PDF
2. Drawings (SMYU 26-1029).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Trans-mittal #

Specification Section

SD

# Submittal Description Item Submitted

Paragraph

Classificati on: GOVT or A/E Revwr Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth Date RCD From

CONTR

Date FWD To

Other Revwr

Date

RCD

From Other Revwr

Action Code

Date Of Action

Mailed To

CONTR/

Date RCD From

APPR

Authority Remarks

1 01 32 01.00 10 01 Preconstruction Submittals Initial Project Schedule 3.4.2 G

2 01 32 01.00 10 01 Preconstruction Submittals Periodic Schedule Updates 3.4.3 G

3 01 32 01.00 10 01 Preconstruction Submittals Schedule Status Report 3.1.2

4 01 33 00 01 Preconstruction Submittals Submittal register 1.8 G

5 01 35 26 01 Preconstruction Submittals SAFETY PLAN /ACCIDENT

PREVENTION PLAN (APP) 1.6 G

6 01 35 26 01 Preconstruction Submittals Activity Hazard Analysis (AHA) 1.7 G

7 01 35 26 01 Preconstruction Submittals Crane Critical Lift Plan 1.6.1

8 01 35 26 01 Preconstruction Submittals Crane Operators 1.5.1.2

9 01 35 26 03 Product Data Personal Fall Arrest Equipment 3.4.1.2 G

10 01 35 26 06 Test Reports Notifications and Reports 1.11

11 01 35 26 06 Test Reports Accident Reports 1.11.2

12 01 35 26 06 Test Reports Crane Reports 1.11.3

13 01 35 26 06 Test Reports Certificate of Compliance 1.11.4

14 01 35 26 07 Certificates Confined Space Entry Permit 1.8

15 01 35 26 07 Certificates Hot work permit 1.8

16 01 35 26 07 Certificates License Certificates 1.13

17 01 45 00.00 10 01 Preconstruction Submittals Quality Control Plan 3.2 G

18 01 57 20.00 10 01 Preconstruction Submittals Environmental Protection Plan 1.7

19 01 58 00 02 Shop Drawings Construction Project Sign 1.2.1

20 01 78 00 03 Product Data As-Built Record of Equipment and Materials 1.3.2

21 01 78 00 03 Product Data Equipment-in-Place List 1.3.4

22 01 78 00 03 Product Data Warranty Management Plan 1.6.1

23 01 78 00 03 Product Data Warranty Tags 1.6.5

24 01 78 00 03 Product Data Spare Parts Data 1.4

25 01 78 00 08 Manufacturer’s Instructions Preventative Maintenance 1.5

26 01 78 00 08 Manufacturer’s Instructions Condition Monitoring (Predictive Testing) 1.5

27 01 78 00 08 Manufacturer’s Instructions Inspection 1.5

28 01 78 00 08 Manufacturer’s Instructions Instructions 1.6.1

TITLE: SMYU 26-1029 REPLACE ANTENNA PLATFORM HILL 180

SUBMITTAL REGISTER

JOB NAME:

LOCATION:

CONTRACT NO:

CONTRACTOR:

APPROVING AUTHORITY

(d)

CONTRACTOR SCHEDULE

DATES

CONTRACTOR

ACTION

29 01 78 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 1.7

30 01 78 00 11 Closeout Submittals

Record (As-Built) Drawings & design calculations, prepared and stamped by a licensed professional engineer specializing in structural engineering

1.3.1 G

31 01 78 00 11 Closeout Submittals Interim Form DD1354 1.9 G

32 01 78 00 11 Closeout Submittals Checklist for Form DD1354 1.9 G

33 03 30 00 02 Shop Drawings Fabrication drawings for foundation 1.6.2.1 G

34 03 30 00 02 Shop Drawings Reinforcing steel 1.6.2.3 G

35 03 30 00 02 Shop Drawings Synthetic reinforcing fibers 2.5.5

36 03 30 00 03 Product Data Portland Cement 2.4.1.3

37 03 30 00 03 Product Data Ready-Mix Concrete 2.3.2

38 03 30 00 05 Design Data Concrete mix design 1.6.4.1 G

39 03 30 00 05 Design Data Structural/design calculations for foundation IAW soil bearing test 1.6.1.1 G

40 03 30 00 06 Test Reports Concrete mix design 1.6.4.1 G

41 03 30 00 06 Test Reports Tolerance report 3.10.2.1

42 03 30 00 06 Test Reports Compressive strength tests 3.12.2.3

43 03 30 00 06 Test Reports Unit weight of structural lightweight concrete 3.12.2.5

44 03 30 00 06 Test Reports Slump Tests 3.12.2.1

45 03 30 00 06 Test Reports Temperature Tests 3.12.2.2

46 03 30 00 06 Test Reports Ion Concentration 3.12.2.6

47 03 30 00 07 Certificates Curing concrete elements 1.6.3.1

48 03 30 00 07 Certificates VOC Content for form release agents, curing compounds, and concrete 1.6.3.4

49 03 30 00 07 Certificates Material Safety Data Sheets 1.6.3.5

50 03 30 00 07 Certificates Classification and Quality of Concrete 2.8

51 03 30 00 07 Certificates Steel Bar 3.6.11

52 03 30 00 08 Manufacturer’s Instructions Fly ash 1.6.4.2

53 05 05 23 03 Product Data Welding Procedures 1.5

54 05 05 23 06 Test Reports Nondestructive Examination 3.3.1 G

55 05 05 23 07 Certificates Welder, Welding Operator, and Tacker Qualification 1.5.5

56 05 05 23 07 Certificates Inspector Qualification 1.5.6

57 05 12 00 02 Shop Drawings Fabrication drawings 1.5.1 G

58 05 12 00 03 Product Data Steel 2.1

59 05 12 00 03 Product Data Bolts, nuts, and washers 2.2

60 05 12 00 07 Certificates Welding procedures and qualifications 1.5.2.3

61 05 21 23 01 Preconstruction Submittals Material Safety Data Sheet 1.5.2

62 05 21 23 02 Shop Drawings Steel joist girder framing 1.5.1 G

63 05 21 23 07 Certificates Welder qualification 1.5.2

64 05 30 00 02 Shop Drawings Fabrication Drawings 1.3.5 G

65 05 50 13 02 Shop Drawings Fabrication drawings 1.4.2 G

66 05 50 14 02 Shop Drawings Detail Drawings 1.3.2 G

67 05 50 14 03 Product Data Welding of Structural Steel 2.2.2.1

68 05 50 14 03 Product Data Materials List 2.1.1

69 05 50 14 06 Test Reports Tests, Inspections, and Verifications 2.3

70 05 50 14 07 Certificates Qualification of Welders and Welding Operators 1.3.1

71 05 50 14 07 Certificates Application Qualification for Steel Studs 2.2.2.3

72 05 51 33 02 Shop Drawings Ladder fabrication and installation drawings 1.4 G

73 09 90 00 03 Product Data Coating / Manufacturer's Technical Data Sheets 2.1 G

74 09 90 00 06 Test Reports MPI Test Report 1.4.1.2 G

75 09 90 00 08 Manufacturer’s Instructions Manufacturer's Material Safety Data Sheets 1.7.2 G

76 31 00 00 06 Test Reports Soil bearing Testing to design footing G