This Statement of Work (SOW) is for the rental of a 125 kVA (100 kW) emergency generator for the Peach Springs Health Center, located in Peach Springs, Arizona, which serves the Hualapai Indian Tribe. The Colorado River Service Unit (CRSU) requires a generator with specific technical specifications, including a Tier IV engine, 208/240/480V alternator, and a portable trailer-mounted design. The generator is needed for the clinic's Life Safety system during emergency power interruptions.

Key requirements include delivery to the facility's west side, testing by the vendor's technicians, and maintenance record keeping. The period of performance is 6 months from delivery, with an additional 6-month option period. The contractor must provide manufacturer's end-user manuals, comply with specified operating hours (8:00 a.m. to 5:00 p.m., Monday-Friday), and ensure employees wear identification badges. The vendor must also provide documentation of the generator's last load bank testing to meet The Joint Commission Standard EC 02.05.07.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CRSU – Peach Spring

Statement of Work

Colorado River Service Unit Parker, AZ

10/02/2025

Statement of Work Peach Spring – Emergency Generator Rental

1. GENERAL: The Colorado River Service Unit (CRSU) serves nearly 13,000 members in the tribal communities of Parker, AZ; Peach Springs, AZ; Supai, AZ; Havasu Lake, CA; and Moapa, NV. CRSU is headquartered at Parker Indian Health Center in Parker, AZ. Our facilities are accredited through The Joint Commission.

Peach Springs, Arizona, located on Route 66 in Mohave County, is the administrative headquarters of the Hualapai (“Wall-ah-pie”) Indian Tribe. The remote facility is approximately 53 miles north of Kingman, AZ.

2. BACKGROUND: Colorado River Service Unit (CRSU) Peach Spring Clinic is requesting the rental of an emergency generator we are requesting a 125 kVA (100 kW).. This is required for the Clinic’s Life Safety system and utilized only during emergency situations.

2.1. Peach Spring Clinic

943 Hualapai Way Peach Springs, AZ 8643

3. EQUIPMENT SPECIFICATIONS:

Below is the list of the minimum requirements for the backup generator rental.

125 kVA (100 kW) Generator Specifications

Item Minimum features and specifications Quantity

Engine

Alternator (208/240/480) Tier rating Tier IV Design 4 cycle, in-line, turbocharged and after-cooled Bore 107 mm (4.21 in.)

Stroke 124.0 mm (4.88 in.)

Displacement 6.69 liters (408 in3) Cylinder block Cast iron, in-line 6 cylinder Battery capacity 2 x 760 cca Battery charging alternator 70 amps Starting voltage 24 volt, negative ground Fuel system Direct injection HPCR system Fuel filter Dual Spin on fuel filter with water separator Air cleaner type 2-stage, dry replaceable element with dust ejector Lube oil filter type(s) Single spin-on, full flow

Statement of Work

Colorado River Service Unit

Standard cooling system 122 °F (50 °C) ambient radiator

Alternator

Design Brushless, 4 pole, drip proof, revolving field Stator Double layer concentric, 2/3 winding pitch Rotor Singe bearing, flexible disc Insulation system Class H per NEMA MG1-1.65

(208/240/480 VAC)

Standard temperature rise 125/40 ºC Prime (208/480

VAC)

Exciter type Permanent Magnet Generator (PMG) Phase rotation A (U), B (V), C (W) Alternator cooling Direct drive centrifugal blower fan AC waveform Total Harmonic Distortion (THDV) < 1.5% no load, < 5% non-distorting balance linear load Telephone Influence Factor (TIF) < 50 per NEMA MG1-

22.43 Telephone Harmonic Factor (THF) < 2%

Power Capability (Assume power factor = 0.80 for 3 phase amps)

240 V, 1 phase Amps 60 Hz -419 208 V, 3 phase Amps 60 Hz – 520 480 V, 3 phase Amps 60 Hz – 226 240 V, 3 phase Amps 60 Hz – 451 400 V, 3 phase Amps 50 Hz - 233

Electrical Power panel Specifications

Voltage 120/480 Volts 120 V Duplex receptacles – 2–20-amp GFCI 240 V Twist – 3-50 amps Load lug connection (stud diameter) – ½ inch Load lug circuit breakers – 600 amps

X

Dimensions

146” to 155” x 57” to 65” x 67” to 75” (Length x Height x Width)

Weight – Min 6000 Lbs. to 8500 Lbs.

Fuel Capacity – 250 gal to 300 gal

Trailer Information Generator shall be a portable unit with trailer designed for this capability.

4. DESCRIPTION OF SERVICE:

4.1. The contractor shall deliver products to the Peach Springs Health Center.

4.2. Generator shall be sized for supplying emergency power for the duration of normal power interruption. No sustained overload capability is available for this rating.

(Equivalent to Fuel Stop Power in accordance with ISO3046, AS2789, DIN6271 and BS5514). Nominally rated.

4.3. Prime (unlimited running time): Applicable for supplying power in lieu of commercially purchased power. Prime Power is the maximum power available at a variable load for an unlimited number of hours. A 10% overload capability is available for limited time. (Equivalent to Prime Power in accordance with ISO8528

Statement of Work

Colorado River Service Unit and Overload Power in accordance with ISO3046, AS2789, DIN6271, and BS5514).

4.4. Generator shall meet these certifications:

4.4.1. CAN/CSA STD C22.2 NO. 100

4.4.2. CAN/CSA STD C22.2 NO. 14

4.5. Electrical Connections: Vendor shall supply at least 75 ft. of electrical conductors rated for outdoor application to connect supplied generator to emergency power system. This is to connect to the facilities Automatic Transfer Switch (ATS)

4.5.1. ATS information:

System Voltage: 120/208 Serial Number:30003044414 Model Number: RTSN200G3 Switch ratings: Amps: 200 Volts: 480 HZ: 60

4.6. Delivery and Setup:

4.6.1. Delivery to facility, designated location on west side of facility. Requires coordination with maintenance personnel due to location is in secure location.

4.6.2. Installation of electrical connectors will be completed by government personnel

4.6.3. Testing of generator while on an electrical load to be completed prior to vendor’s technicians leaving. This is to include phase rotation confirmation, and remote start.

4.7. Ongoing Support and Maintenance:

4.7.1. Vendor to be responsible for maintenance and maintenance records to be available upon request. Preventative maintenance schedule and documentation to be available to local staff.

4.8. Pick up and wrap up:

4.8.1. Vendor to pick up generator upon request from the government at the convenance of the government.

4.8.2. Disconnection of electrical connection to be completed by government personnel.

4.8.3. Site location to be return to prior condition.

Statement of Work

Colorado River Service Unit

5. OPERATING HOURS: The contractor shall perform all communication during normal business operating hours Monday through Friday from 8:00 a.m. to 5:00 p.m. excluding federal holidays.

6. DOCUMENTATION/REPORTING REQUIREMENTS: The Contractor shall submit an itemized list of the requested items and specifications for review.

7. EMPLOYEE IDENTIFICATION: Contractor personnel shall wear an identification badge that, at minimum, displays the company’s name, the employee’s photo, and employee’s name.

Contractor personnel shall comply with Government rules and regulations while at the facility.

8. PERIOD OF PERFORMANCE: 6 months from delivery of generator, with a 6-month option period from date of pick up.

9. DELIVERABLES: Deliverables are due fifteen (15) calendar days after completion of purchase.

9.1. Manufactures end user manuals

10. GENERAL REQUIREMENTS

10.1. Initial acceptance will be at the discretion of the acceptor during the delivery. All items required must be fully functional, present, and compatible as required.

10.2. Delivery must be made on the Delivery/Installation date shown on the order. The quotes (Offers) must provide within its quote a statement of understanding regarding delivery/installation date, which must be part of the lease agreement, and each order under the contract.

10.3. The Contractor shall take necessary steps to ensure that complete action (installation, exchange, removal, etc.) is made within the delivery schedule specified in the order issued under the lease agreement (contract). Complete delivery/installation is defined that all components/optional features/equipment simultaneously fully functioning and supplies provided according to regular schedule maintenance schedule provided with the quotation.

11. SPECIFIC REQUIREMENTS/TASKS

11.1. A copy of the last load bank testing is to be provided to the facility for our records to ensure compliance to The Joint Commission Standard EC 02.05.07.