The file's text, extracted by GovTribe without its formatting.
SECTION B-- SCHEDULE OF ITEMS
B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 15101 |
| Mobilization |
| 1 |
| L.S. |
| $__________ |
| $__________ |
| 20101 |
| Removal of Shrubbery by way of clearing and grubbing |
| 1 |
| L.S. |
| $__________ |
| $__________ |
| 15713 |
| Soil Erosion and Pollution Control |
| 1 |
| L.S. |
| $__________ |
| $__________ |
| 63501 |
| Traffic Control and Monitoring |
| 1 |
| L.S. |
| $__________ |
| $__________ |
| 55501 |
| Repair CMP wall Section |
| 1 |
| L.S. |
| $__________ |
| $__________ |
| 56302 |
| Prepare CMP Wall for painting/ painting |
| 2400 |
| S.Y |
| $__________ |
| $__________ |
| 15701 |
| Temporary Turf establishment |
| 2 |
| Acre |
| $__________ |
| $__________ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
| Company Name: |
| POC & Title: |