1. Statement of Work.pdf
PDF 1 MB Posted
- Attached to
- 127EAW22R0069 - CMP Wall Repair and Repaint
- Solicitation number
- 127EAW22R0069
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2. Fire Plan.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 5. Specifications.pdf | ||
| 3. Schedule.docx | DOCX document | |
| 127EAW22R0069 - CMP Wall Repair and Repaint.pdf | ||
| 6. Davis-Bacon Act WD # CA20220007.pdf | ||
| 4. Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
Attachment
Project 22N94-8.7 CMP Wall repair and repaint
General Information
1.0 Scope of Work
Furnish all labor, equipment, and materials, to accomplish the Work under this contract. Services consist of clearing and grubbing, Striping and repainting of CMP (Corrugated Metal Pipe) Wall, one (1) CMP BIN wall replacement section (6’x12’), removing and disposing of damaged materials, structural excavation and backfill to correct compactions specifications, and traffic control and signage.
2.0 Background
CMP wall was damaged during the 2020 North Complex due to extreme temperatures produced by the fire that passed through. During this fire a tree landed on a section of the wall damaging the wall itself. The damage could lead to potentially weakening the structural integrity of the wall with time.
Contractor Requirements
3.0 Technical Requirements / Tasks
Removal of Shrubbery by way of clearing and grubbing:
o Refer to FP-14 section 20101 for specifications regarding this task.
Soil Erosion and Pollution Control:
o Refer to FP-14 section 15701 for specifications regarding this task.
o Refer to FP-14 section 15713 for specifications regarding this task.
Traffic Control and Monitoring:
o Refer to FP-14 section 63501 for specifications regarding this task.
o Contactor shall submit a Traffic Control and Signage Plan for review 10 days prior to commencement of operations.
Plan must conform to Manual of Uniform Traffic Control Devices (MUTCD) most current version.
o Signage shall be placed at locations that allow for adequate space for truck traffic to maneuver.
Repair CMP wall Section:
o Refer to FP-14 section 55501 for specifications regarding CMP pipe selection.
o Removal of back fill material to allow access to wall section needing repair.
o Drill holes into existing CMP wall and bolt repair sections into place.
o Replace backfill material in lifts to allow for proper compaction.
Prepare CMP Wall for painting:
o Refer to FP-14 section 56302 for specifications regarding this task o Submit plan with details regarding MSDS, Containment Plan, disposal plan, safety measures, emergency spill procedures, certifications of experience Paint CMP Wall with galvanized paint:
o Refer to FP-14 section 56302 for specifications regarding this task.
4.0 Government Furnished
No Government furnished items will be provided for this contract frico Cross-Out
5.0 Submittals / Schedule
Key Submittals Item No. Deliverable Objective Due
1. Clearing Plan Clear and grub area withing the location of the wall 14 after contract award
2. Soil Erosion and Pollution Control
Inspect soil erosion and pollution controls in place per
FP-14, 15713
14 after contract award
3. Project Specific Fire Plan Plan outlining specific task not covered in the supplied fire plan
14 after contract award
4. Traffic Control and Monitoring plan
Traffic Control and Signage Plan with detailed locations and types of traffic control devices being used in accordance with MTUCD
10 days prior to commencement of operations
5. CMP Wall for prep and painting Plan
Detailed plan with MSDS, Containment Plan, disposal plan, safety measures, emergency spill procedures, certifications of experience.
14 days prior to commencement of operations
6.0 Travel
Travel to location form any accommodations will take approximately 1.5 hours. Directions to location:
From the feather river ranger district office, travel northeast on Mitchell Ave toward 3rd AVE for 1.2 mi, turn right onto Bridge St 0.2 mi, continue onto Oro Quincy hwy. 2.5 mi, turn left onto ca-162 e 3.8 mi, turn right onto Forbestown Rd 6.2 mi, turn left onto Lumpkin Rd 12.8 mi, slight left onto La Porte Rd 2.8 mi
7.0 Contractor’s Key Personnel
Competent personal with the following:
o SSPC competent person certificate o Certificate of completion of 29 CFR 1926.62 o Minimum of 2 years industry field painting experience o Minimum of 90 day of field supervisory/ management experiences in paint removal projects.
8.0 Security Requirements
None
9.0 Data Rights
None
10.0 Section 508 – Electronic and Information Technology Standards None