About this file

This document provides revised bid items for a federal construction project to replace roofs and overhangs at a Department of Veterans Affairs medical center. The project includes general construction, necessary demolition, alterations, mechanical and electrical work to replace several roofs and overhangs. Bids are requested for the base bid including all work, and three alternate deduct bids that would remove specific roof replacements and soffit work from the scope. Bidders must submit pricing for all bid items, and award will be made to the lowest priced bidder for the highest priority bid item for which funds are available. The project completion period is 290 calendar days from notice to proceed. The first 60 days are reserved for submittals, with no on-site work permitted during this period without approval.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA-- 541-18-103 Replace CARES Tower Roof and Overhangs, newest first.
File Type Posted
1. RFI Tracker with VA Responses (Updated as of 20200527).docx DOCX document
2. Photographs of Existing Conditions (Taken in March 2018).pdf PDF
1a. Response to RFI #12 Record Drawings.pdf PDF
36C25020B0020 0004.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF BID ITEM(S)

**Note: The Government intends to make award on BID ITEM 1; however, should the bids received exceed the funds available, award will be on BID ITEM 2, BID ITEM 3, or BID ITEM 4 in this order of priority, based on available funding. Bidders are required to submit a price for every bid item.

A. BID ITEM 1 (Base Bid): All work in the drawings and specifications. The contractor shall provide all materials, labor, tools, equipment, insurance, supervision, and any other items required to complete project “Replace CARES Tower Roof and Overhangs”, Project No. 541-18- 103 at the Louis Stokes Department of Veterans Affairs Medical Center, 10701 East Boulevard, Cleveland, OH 44106. Work includes general construction, necessary demolition, alterations, mechanical and electrical work, and certain other items shown and specified. All work shall be completed within 290 calendar days after receipt of Notice to Proceed.

B. BID ITEM 2: (Alternate Deduct 1): All work in BID ITEM 1, except DELETE Roof 2 Replacement and DELETE PROVIDE Roof 2 Sealer/Coating as indicated on the drawings. All work shall be completed within 290 calendar days after receipt of Notice-to-Proceed.

C. BID ITEM 3: (Alternate Deduct 2): All work in BID ITEM 1, except DELETE work as specified in BID ITEM 2. In addition, DELETE Soffit B Replacement as indicated on the drawings. All work shall be completed within 290 calendar days after receipt of Notice-to-Proceed.

D. BID ITEM 4: (Alternate Deduct 3): All work in BID ITEM 1, except DELETE work as specified in BID ITEM 2 and BID ITEM 3. In addition, DELETE Roof 5 Replacement as indicated on the drawings. All work shall be completed within 290 calendar days after receipt of Notice-to- Proceed.

NOTE: The first sixty (60) days after receipt of the Notice to Proceed shall be used for the following:

1. Submission and approval of the Submittal Register, Project Schedule, Safety Plan, Scaffolding Plan, and any other submittals required before actual on-site construction activities can begin.

2. Contractor will not be permitted to mobilize and/or perform/complete any construction es VA Medical Center facility during this sixty (60) day period unless approved by the Contracting Officer.