3.Final Change Order Notice.pdf

PDF 1 MB Posted

Attached to
CHANGE ORDER NOTICE Hologic NG/NT Testing and Kits
Solicitation number
27-482DPH-OFCDI-B-53956
Issued by
Illinois

About this file

This is a Change Order Notice issued by the Chief Procurement Office for General Services on behalf of the Illinois Department of Public Health (IDPH) for Hologic NG/NT Testing and Kits under BidBuy Reference Number 27-482DPH-OFCDI-B-53956. The change order addresses a publication error in the original Invitation for Bid (IFB) process for Contract 68500013N and realigns contract quantities to reflect actual programmatic needs for statewide sexually transmitted infection (STI) testing. The Carbondale Laboratory, which conducts Neisseria gonorrhoeae (NG) and Chlamydia trachomatis (CT) screening using the Hologic Panther NAAT platform under a reagent rental agreement, requires increased annual testing volumes. The original IFB incorrectly listed annual quantities at 15,000 NG/CT tests and 15,000 collection kits per year. The amended contract increases the annual testing volume to 25,000 tests (an additional 10,000 tests per year) and the annual kit volume to 30,000 collection kits (an additional 15,000 kits per year) to meet actual laboratory demand.

The original contract maximum was $525,000, with the change order increasing the cost by $375,000 (an additional $75,000 per year), resulting in a revised total contract cost of $900,000 over the remaining five-year initial term with potential for a ten-year contract duration. All other contract terms, conditions, unit pricing, and vendor obligations remain unchanged, including the reagent rental structure that provides free instrumentation, preventive maintenance, repairs, replacement parts, installation, training, and technical support. The change order was required to ensure sufficient supplies and uninterrupted statewide STI testing operations and meets the threshold for posting on BidBuy for 14 days as it increases contract cost by more than $25,000.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Please wait...

If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.

You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.

For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.

Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.

Change Order Notice Chief Procurement Office for General Services Change Order Notice V.25.1 Page of Notice of renegotiated contracts and change orders that increase the cost of a contract by more than $25,000 or the time of completion by a total of 180 days or more shall be posted on the Bulletin/BidBuy for 14 days.

This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.

Detailed explanation for this change order:

11.0.0.20130303.1.892433.887364

CurrentPage:
PageCount:
DropDownList1: DPH - Public Health
ProcurementTitle: CHANGE ORDER NOTICE Hologic NG/NT Testing and Kits
BBREFNO.: 27-482DPH-OFCDI-B-53956
thedetails: This change order is required to correct a publication error made during the original Invitation for Bid (IFB) process and to align the contract quantities with actual programmatic needs for statewide sexually transmitted infection (STI) testing. When Contract 68500013N was bid and awarded, the annual quantities published in BidBuy for NG/CT test kits and collection devices were inadvertently listed incorrectly. Although the IFB stated that all quantities were estimates for bidding purposes only, the published numbers did not reflect the actual laboratory testing volumes required by the Illinois Department of Public Health (IDPH) Carbondale Laboratory.

The Carbondale Laboratory conducts statewide Neisseria gonorrhoeae (NG) and Chlamydia trachomatis (CT) screening using the Hologic Panther NAAT platform provided under a reagent rental agreement. This amendment updates the contract quantities to reflect actual testing demand, which is significantly higher than the 15,000 NG/CT tests and 15,000 collection kits per year originally listed in the IFB publication. The laboratory requires an additional 10,000 NG/CT tests per year, thereby increasing the annual testing volume from 15,000 to 25,000. It also requires an additional 15,000 collection kits per year, thereby increasing the annual kit volume from 15,000 to 30,000. The increased annual quantities result in an additional $75,000 per year, totaling $375,000 over the remaining five year initial term.

This change order updates the contract maximum, corrects the annual quantities of reagents and collection devices, and revises the scope to reflect the required volumes. These corrected quantities ensure sufficient supplies and uninterrupted statewide STI testing operations for the full potential ten year contract duration.

Original Cost: $525,000.00 Amount of Change: $375,000.00 Revised Cost: $900,000.00

All other terms, conditions, unit pricing, and vendor obligations remain unchanged. The reagent rental structure, including free instrumentation, preventive maintenance, repairs, replacement parts, installation, training, and technical support—continues exactly as originally awarded.