This solicitation seeks demolition services for two US Coast Guard aids to navigation. The contractor shall demolish rip rap for River Light 161 in the Hudson River, New York and demolish the submerged structure at Peddocks Island Channel Light 4P in Quincy Bay, Massachusetts. The work includes all labor, materials, equipment, transportation, disposal and supervision required according to the specifications (62 pages) and drawings (8 sheets) for Project Schedule Number 15705194. The applicable wage rates are also incorporated into the solicitation. The Department of Homeland Security US Coast Guard is the agency seeking these demolition services.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
SHORE INFRASTRUCTURE LOGISTICS CENTER
SPECIFICATIONS FOR
DEMO D1 ATON VARIOUS LOCATIONS (FY22 RPOP)
PSN: 15705194
LT Matthew R. Fann, PE, PMP David N. Glass, PE
PROJECT ENGINEER BRANCH CHIEF
Michael P. Carosotto, PE, PMP
TECHNICAL DIRECTOR, BY DIRECTION
COMMANDING OFFICER
UNITED STATES COAST GUARD
CIVIL ENGINEERING UNIT PROVIDENCE
475 KILVERT STREET, SUITE 100
WARWICK, RHODE ISLAND 02886
Demo D1 ATON Various Locations 15705194
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
00 01 15 LIST OF DRAWINGS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 32 00 CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES
01 33 00 SUBMITTAL PROCEDURES
01 35 29 SAFETY, AND OCCUPATIONAL HEALTH REQUIREMENTS
01 45 00.00 10 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 77 00 CLOSEOUT PROCEDURES
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
35 10 35 DIVING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
Document 00 01 15 Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause
"DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
SHEET ID SHEET NO LEVEL
II/SITE
DESIGNATION
SITE SHEET TITLE
G-001 01 - ALL COVER SHEET
G-002 02 - ALL GENERAL NOTES
SD-001 03 - HUDSON RIVER LIGHT 161 OVERALL SITE PLAN
SD-002 04 - HUDSON RIVER LIGHT 161 OVERALL SITE SECTION
SD-003 05 - HUDSON RIVER LIGHT 161 SONAR IMAGES
SD-004 06 - PEDDOCKS ISLAND
CHANNEL LIGHT 4P
OVERALL SITE PLAN
SD-005 07 - PEDDOCKS ISLAND
CHANNEL LIGHT 4P
OVERALL SITE SECTION
SD-006 08 - PEDDOCKS ISLAND
CHANNEL LIGHT 4P
SONAR IMAGES
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
03/20
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The project consists of demo of 2 Aids to Navigation (ATON) assets in Hudson
River, NY and Quincy Bay, MA. Base bid consists of ATON asset locations A &
B listed below.
1.1.2 Location
The work is located in US Coast Guard District One (D1) Area of Operation
(AOR). The ATON asset locations are listed below:
A. Hudson River, NY
LAT/LONG: 42-21-24.12N, 073-47-32.64W
B. Quincy Bay, MA
LAT/LONG: 42-17-37.80N, 070-57-24.29W
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.3 LOCATION OF UNDERGROUND UTILITIES
Not used.
1.3.1 Notification Prior to Excavation
1.4 QUALITY ASSURANCE
1.4.1 Federal and Other Authorities Having Jurisdiction
All work shall be in compliance with Federal, State of New York and State of
Massachusetts regulations and requirements.
Section 01 11 00 Page 2
1.4.2 Commissioning, Functional Performance Tests
1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
1.6 SALVAGE MATERIAL AND EQUIPMENT
1.7 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.8 PRECONSTRUCTION MEETING
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the contract for construction, safety program, preparation of the schedule of values, shop drawings, and other submittals, scheduling/programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
1.9 CONSTRUCTION KICKOFF MEETING
After award of the contract, and when contracts for the major subcontractors listed below have been executed by the prime contractor, and prior to commencement of any work at the site, meet with the COR to discuss and develop a mutual understanding relative to work restrictions, safety requirements and temporary environmental controls, temporary facilities and controls, preparation of the project schedule, and other submittals, scheduling programming including phasing requirements, closeout procedures and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
1.10 PROJECT COMMUNICATION - CONSTRUCTION PROJECT MEETINGS
Construction Project Meetings (aka 'Job Meetings') will be held on a regular basis at the project location to advise of the work planned for the project, optimize communications with the construction team and USCG
Project Managers. Meetings will typically be convened at the job-site.
Participation via conference call may be acceptable for some attendees, at the discretion of the COR. A schedule for these meetings will initially be established at the Pre-Construction Conference, with dates and times to be arranged for the mutual convenience of all, to the extent practical.
In addition to the Prime Contractor's project manager, key personnel from sub-contractors shall also attend. The need for these meetings shall be at the discretion of the Coast Guard Construction Project Manager, but it is anticipated that initially, at a minimum, these meetings shall occur
Section 01 11 00 Page 3 on predetermined bases until all submittals are approved. Meetings shall increase to weekly as the period for on-site construction approaches, and continue on a weekly basis until no longer required, at the discretion of the COR.
1.11 BUY AMERICAN ACT COMPLIANCE
1.12 BASIS OF DESIGN; AND BRAND NAME OR EQUAL
1.12.1 Basis of Design
1.12.2 Brand Name or Equal
1.13 INSPECTION
The Contractor shall keep the Contracting Officer or duly appointed representative fully informed of contract operations and plans so that a representative may arrange to be present at various times that work is being performed.
1.13.1 Contractor's Daily Log
The Contractor shall be complete the USCG Daily Log form at the end of each working day and deliver it to the Government Inspector. The Government
Inspector will attest to its accuracy by initialing the form and forwarding that form to CEU Providence. The form will be provided to the Contractor by the Contracting Officer's Representative.
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section --
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
1.1 CONTRACTOR ACCESS AND USE OF PREMISES
1.1.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor equipment shall be conspicuously marked for identification.
1.1.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer Monday through Friday, excluding Government holidays.
1.1.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the
Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.2 SECURITY REQUIREMENTS
Not Used.
Section 01 32 00 Page 1
SECTION 01 32 00
CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES
02/15
1.1 SUBMITTALS
Government approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Schedule/Schedule of Values
1.2 CONSTRUCTION SCHEDULE
At the Pre-Construction Conference, submit a Construction Schedule and
Schedule of Values in accordance with FAR Clause 52.236.15. The Schedule of
Values shall be based on the actual breakdown of the bid price. The cost of insurance shall not be listed as a separate item but included as part of each item of work. The actual cost of Bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the
Contracting Officer. For contracts under $25,000, a Schedule of Values is not required. In addition, keep the Government Inspector informed daily of the expected delivery dates for major pieces of equipment and materials.
Construction Schedule and Schedule of Values shall be incorporated into one form which clearly indicates the start and completion dates and unit value of all major work components. The sample form provided in this section may be used. Optional forms may be used provided they include, at a minimum, all information conveyed on the sample form.
Construction Schedule/Schedule of Values form shall incorporate at a minimum the following activities:
a. Bonds
b. Mobilization
c. Demobilization
d. Pre-Construction Submittals
e. Work Activities
f. In-Progress Submittals
g. Final Government Inspection
h. Close-Out Submittals; i.e. Testing, Balancing Reports, Warranties, Operation and Maintenance Manuals, Posted Instructions
i. As-Built Drawings
Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related site work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods.
These activity periods shall not be exclusive of the contract performance period. No site work shall commence until the respective submittals have been approved.
file://///lei-hou-fs02/data/LEI%20Projects/USCG/NavigationLight%20Demo/Specifications/100%25Submittal/01%2033%2000.docx
Section 01 32 00 Page 2
The value of all major work components within the project shall be identified on the Construction Schedule/Schedule of Values on a unit quantity and unit cost basis, e.g. number of squares and cost per square of roofing, number of lineal feet and cost per lineal foot of conduit, number of panels and cost per panel etc. Lump sum items shall only be paid for when 100% complete.
The Construction Schedule/Schedule of Values as approved by the Government is not a substitute for quantities conveyed by the specification and drawings and those required for a complete job. Omissions and errors on the
Construction Schedule/Schedule of Values are the responsibility of the
Contractor.
Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer.
1.3 UPDATED SCHEDULES
Update the construction schedule and equipment delivery schedule at monthly intervals or when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.
3.1 PROGRESS UPDATES
3.1.1 General
A revised Construction Schedule/Schedule of Values shall be issued by the
Contractor on a predetermined basis. In addition, any revisions to the
Construction Schedule/Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction
Schedule/Schedule of Values.
3.1.2 Modifications
When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule/Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification. Revise the Construction Schedule portion of the form to annotate the progress change. Enter all modifications in this manner in sequential order.
Section 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including
(but not limited to) catalog cuts, diagrams, operating charts or curves;
test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's
Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
Submittals that are required prior to or commencing with the start of work on site. Submittals that are required prior to or at the start of construction
(work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Section 01 33 00 Page 2
List Of Proposed Subcontractors
List Of Proposed Products
Baseline Network Analysis Schedule (NAS)
Submittal Register
Schedule Of Prices
Accident Prevention Plan
Health And Safety Plan
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
Demolition plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Section 01 33 00 Page 3
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or
Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Text of posted operating instructions
SD-08 Manufacturer's Instructions
SD-09 Manufacturer's Field Reports
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party
Certification (TPC).
Special requirements necessary to properly close out a construction contract.
For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Civil Engineering Unit Providence Contracting Officer.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
accordance with this section.
Section 01 33 00 Page 4
Submittal Register
Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout.
1.4 FORWARDING SUBMITTALS
1.5 PREPARATION
1.5.1 Transmittal Form
Transmit each submittal, except sample installations and sample panels to the office of the approving authority using the transmittal form prescribed by the Contracting Officer. Include all information prescribed by the transmittal form and required in paragraph IDENTIFYING SUBMITTALS. Use the submittal transmittal forms to record actions regarding samples.
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Identifying Submittals
The Contractor's Quality Control Manager must prepare, review and stamp submittals, including those provided by a subcontractor, before submittal to the Government.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location
b. Construction contract number
c. Dates of the drawings and revisions
d. Name, address, and telephone number of Subcontractor, supplier, manufacturer, and any other Subcontractor associated with the submittal.
e. Section number of the specification by which submittal is required
f. Submittal description (SD) number of each component of submittal
Section 01 33 00 Page 5
g. For a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission
h. Product identification and location in project.
1.5.3 Submittal Format
1.5.3.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.3.2 Format for SD-02 Shop Drawings
Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by
42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.
Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Present shop drawings sized 8 1/2 by 11 inches as part of the bound volume for submittals. Present larger drawings in sets. Submit an electronic copy of drawings in PDF format.
1.5.3.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the
Government contract number in the margin, immediately below the title block, for each drawing.
Reserve a blank space, no smaller than two inches on the right-hand side of each sheet for the Government disposition stamp.
1.5.3.3 Format of SD-03 Product Data
Section 01 33 00 Page 6
1.5.3.3.1 Product Information
1.5.3.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American
National Standards Institute (ANSI), ASTM International (ASTM), National
Electrical Manufacturer's Association (NEMA), Underwriters Laboratories
(UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.3.3.3 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the construction effort.
Submit the manufacturer's instructions before installation.
1.5.3.4 Format of SD-04 Samples
1.5.3.4.1 Sample Characteristics
Furnish samples in the following sizes, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:
a. Sample of Equipment or Device: Full size.
1.5.3.4.2 Sample Incorporation
1.5.3.4.3 Comparison Sample
1.5.3.5 Format of SD-05 Design Data
Provide design data and certificates on 8 1/2 by 11 inch paper. Provide a bound volume for submittals containing numerous pages.
1.5.3.6 Format of SD-06 Test Reports
Provide reports on 8 1/2 by 11 inch paper in a complete bound volume.
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
Section 01 33 00 Page 7
1.5.3.7 Format of SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inch paper. Provide a bound volume for submittals containing numerous pages.
1.5.3.8 Format of SD-08 Manufacturer's Instructions
1.5.3.8.1 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American
National Standards Institute (ANSI), ASTM International (ASTM), National
Electrical Manufacturer's Association (NEMA), Underwriters Laboratories
(UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.3.9 Format of SD-09 Manufacturer's Field Reports
1.5.3.10 Format of SD-11 Closeout Submittals
When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.4 Source Drawings for Shop Drawings
1.5.4.1 Source Drawings
The entire set of source drawing files (DWG) will not be provided to the
Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.5.4.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the
Contractor and without liability or legal exposure to the Government. The
Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with
Section 01 33 00 Page 8 the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not construction documents.
Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the
Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the
Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).
1.5.5 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. In addition to the electronic submittal, provide three hard copies of the submittals. Compile the submittal file as a single, complete document, to include the Transmittal
Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. If documents are scanned, optical character resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file.
When required, the electronic file must include a valid electronic signature or a scan of a signature.
E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer. Provide electronic documents over
10 MB on an optical disc or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:
https://safe.apps.mil/.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of SD-01 Preconstruction Submittal Copies
Unless otherwise specified, submit three sets of administrative submittals.
1.6.2 Number of SD-02 Shop Drawing Copies
Submit three copies of submittals of shop drawings requiring review and approval by a QC organization. Submit three copies of shop drawings requiring review and approval by the Contracting Officer.
Section 01 33 00 Page 9
1.6.3 Number of SD-03 Product Data Copies
Submit in compliance with quantity requirements specified for shop drawings.
1.6.4 Number of SD-04 Samples
a. Submit three samples, or three sets of samples showing the range of variation, of each required item. One approved sample or set of samples will be retained by the approving authority and one will be returned to the Contractor.
1.6.5 Number of SD-05 Design Data Copies
1.6.6 Number of SD-06 Test Report Copies
Submit in compliance with quantity and quality requirements specified for shop drawings, other than field test results that will be submitted with QC reports.
1.6.7 Number of SD-07 Certificate Copies
1.6.8 Number of SD-08 Manufacturer's Instructions Copies
1.6.9 Number of SD-09 Manufacturer's Field Report Copies
1.6.10 Number of SD-10 Operation and Maintenance Data Copies
Submit three copies of O&M data to the Contracting Officer for review and approval.
1.6.11 Number of SD-11 Closeout Submittals Copies
Unless otherwise specified, submit three sets of administrative submittals.
1.7 INFORMATION ONLY SUBMITTALS
Submittals without a "G" designation must be certified by the QC manager and submitted to the Contracting Officer for information-only. Approval of the
Contracting Officer is not required on information only submittals. The
Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the
Contractor. Normally, submittals for information only will not be returned.
However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications;
will not prevent the Contracting Officer from requiring removal and
Section 01 33 00 Page 10 replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe. For Design-Build construction, the Government will retain three copies of information-only submittals.
1.8 PROJECT SUBMITTAL REGISTER AND DATABASE
A sample Project Submittal Register showing items of equipment and materials for when submittals are required by the specifications is provided as
"Appendix A - Submittal Register."
1.8.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. Use an electronic submittal register program furnished by the Government. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by
Government; retain data that is output in columns (a), (g), (h), and (i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
Column (f): Lists the approving authority for each submittal.
The database and submittal management program will be furnished to the
Contractor on a writable compact disk (CD-R), for operation on a Windows-based personal computer.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.8.2 Design-Build Submittal Register
1.8.3 Preconstruction Use of Submittal Register
Submit the submittal register as an electronic database, using the submittal management program furnished to Contractor. Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following
Section 01 33 00 Page 11 fields on the register database submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.8.4 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in the program used by the Contractor with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record
Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
Column (q) Date approval was received.
1.8.5 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
1.8.6 Action Codes
Entries for columns (j) and (o) are to be used as follows (others may be prescribed by the Transmittal Form):
1.8.6.1 Government Review Action Codes
"A" - "Approved as submitted"; "Completed"
"B" - "Approved, except as noted on drawings"; "Completed"
"C" - "Approved, except as noted on drawings; resubmission required"; "Resubmit"
Section 01 33 00 Page 12
1.8.6.2
1.8.6.3
"D" - "Returned by separate correspondence"; "Completed"
"E" - "Disapproved (See attached)"; "Resubmit"
"F" - "Receipt acknowledged"; "Completed"
"G" - "Other (Specify)"; "Resubmit"
"X" - "Receipt acknowledged, does not comply with contract requirements"; "Resubmit"
Government Review Action Codes
"A" - "Approved as submitted"
"AN" - "Approved as noted"
"RR" - "Disapproved as submitted"; "Completed"
"NR" - "Not Reviewed"
"RA" - "Receipt Acknowledged"
Contractor Action Codes (Design-Bid-Build)
DESIGN BID BUILD SUBMITTALS
SubmittalClassificati ons shownin UFGS
Sections
Submittal
Classification
Corresponding
SpecsIntactSubmittal
Register Code which is populated in the SI
SubmittalRegister.Softw are Limitations:
(Thesoftware shows one character delineation in the SpecsIntact
Submittal Register)
RMS The followingSubmitt al
Classifications are populated in
RMS when theSpecsIntact
Submittal
DataFile is pulled into RMS)
G Submittal requiresGovernme nt Approval
G GA
BLANK Submittal is For
Information Only
(FIO)
BLANK FIO
S Submittal is for documentationof
Sustainable requirements
S S/FIO
Section 01 33 00 Page 13
1.8.6.4 Contractor Action Codes (Design-Build)
Not used.
1.8.7 Delivery of Copies
Submit an updated electronic copy of the submittal register to the
Contracting Officer with each invoice request, unless a paper copy is requested by the Contracting Officer. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.
1.9 VARIATIONS
Variations from contract requirements require Contracting Officer approval pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for
Construction, and will be considered where advantageous to the Government.
1.9.1 Considering Variations
Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation that results in lower cost, consider submission of the variation as a Value Engineering
Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the
Government.
1.9.2 Proposing Variations
When proposing variation, deliver a written request to the Contracting
Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. Include the
DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals that include variations proposed by the Contractor. Set forth in writing the reason for any variations and note such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.
1.9.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.9.4 Review Schedule Extension
In addition to the normal submittal review period, a period of 14 calendar working days will be allowed for the Government to consider submittals with variations.
Section 01 33 00 Page 14
1.10 SCHEDULING
Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.
b. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the
Contractor of supplying submittals required by the contract documents but that have been omitted from the register or marked "N/A."
c. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.
Contracting Officer review will be completed within 14 calendar working days after the date of submission.
d. Except as specified otherwise, allow a review period, beginning with receipt by the approving authority, that includes at least 7 working days for submittals for QC manager approval and 14 working days for submittals where the Contracting Officer is the approving authority.
The period of review for submittals with Contracting Officer approval begins when the Government receives the submittal from the QC organization.
1.10.1 Reviewing, Certifying, and Approving Authority
Within 15 calendar days of Notice To Proceed, provide the following schedule of submittals for approval by the Contracting Officer:
a. A schedule of shop drawings and technical submittals required by the specifications and drawings. Indicate the specification or drawing reference requiring the submittal; the material, item, or process for which the submittal is required; the "SD" number and identifying title of the submittal; the anticipated submission date, and the approval need date.
b. A separate schedule of other submittals required under the contract but not listed in the specifications or drawings. Indicate the contract requirement reference, the type or title of the submittal, the anticipated submission date, and the approval need date (if approval is required).
Section 01 33 00 Page 15
The QC Manager is responsible for reviewing all submittals and certifying that they are in compliance with contract requirements. The approving authority on submittals is the QC Manager unless otherwise specified. At each "Submittal" paragraph in individual specification sections, a notation
"G" following a submittal item indicates that the Contracting Officer is the approving authority for that submittal item. Provide an additional copy of the submittal to the Government Approving authority
1.10.2 Constraints
Conform to provisions of this section, unless explicitly stated otherwise for submittals listed or specified in this contract.
Submit complete submittals for each definable feature of the work. At the same time, submit components of definable features that are interrelated as a system.
When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, the submittal will be returned without review.
Approval of a separate material, product, or component does not imply approval of the assembly in which the item functions.
1.10.3 QC Organization Responsibilities
a. Review submittals for conformance with project design concepts and compliance with contract documents.
b. Process submittals based on the approving authority indicated in the submittal register.
(1) When the QC manager is the approving authority, take appropriate action on the submittal from the possible actions defined in paragraph APPROVED SUBMITTALS.
(2) When the Contracting Officer is the approving authority or when variation has been proposed, forward the submittal to the
Government, along with a certifying statement, or return the submittal marked "not reviewed" or "revise and resubmit" as appropriate. The QC organization's review of the submittal determines the appropriate action.
c. Ensure that material is clearly legible.
d. Stamp each sheet of each submittal with a QC certifying statement or an approving statement, except that data submitted in a bound volume or on one sheet printed on two sides may be stamped on the front of the first sheet only.
(1) When the approving authority is the Contracting Officer, the QC organization will certify submittals forwarded to the Contracting
Officer with the following certifying statement:
"I hereby certify that the (equipment) (material) (article) shown and marked in this submittal is that proposed to be incorporated with
Contract Number 15705194 is in compliance with the contract drawings
Section 01 33 00 Page 16 and specification, can be installed in the allocated spaces, and is submitted for Government approval.
Certified by Submittal Reviewer _____________________, Date _______
(Signature when applicable)
Certified by QC Manager _____________________________, Date ______"
(Signature)
(2) When approving authority is the QC manager, the QC manager will use the following approval statement when returning submittals to the
Contractor as "Approved" or "Approved as Noted."
"I hereby certify that the (material) (equipment) (article) shown and marked in this submittal and proposed to be incorporated with Contract
Number 15705194 is in compliance with the contract drawings and specification, can be installed in the allocated spaces, and is approved for use.
Certified by Submittal Reviewer ______________________, Date ______
(Signature when applicable)
Approved by QC Manager _______________________________, Date _____"
(Signature)
e. Sign the certifying statement or approval statement. The QC organization member designated in the approved QC plan is the person signing certifying statements. The use of original ink for signatures is required. Stamped signatures are not acceptable.
f. Update the submittal register as submittal actions occur, and maintain the submittal register at the project site until final acceptance of all work by the Contracting Officer.
g. Retain a copy of approved submittals and approved samples at the project site.
h. For "S" submittals, provide a copy of the approved submittal to the
Government Approving authority.
1.10.4 Government Reviewed Design
1.11 GOVERNMENT APPROVING AUTHORITY
When the approving authority is the Contracting Officer, the Government will:
a. Note the date on which the submittal was received from the QC manager.
b. Review submittals for approval within the scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
Section 01 33 00 Page 17
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with comments and markings appropriate for the action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date submittals. Three copies of the submittal will be retained by the
Contracting Officer and three copies of the submittal will be returned to the Contractor. If the Government performs a conformance review of other
Designer of Record approved submittals, the submittals will be identified and returned, as described above.
1.11.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize proceeding with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize proceeding with the work covered provided that the Contractor takes no exception to the corrections.
c. Submittals marked "not approved," "disapproved," or "revise and resubmit" indicate incomplete submittal or noncompliance with the contract requirements or design concept. Resubmit with appropriate changes. Do not proceed with work for this item until the resubmittal is approved.
d. Submittals marked "not reviewed" indicate that the submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.
1.12 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES.
The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the
Contractor's expense.
If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.13 APPROVED SUBMITTALS
Section 01 33 00 Page 18
The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory. the design, general method of construction, materials, detailing, and other information appear to meet the Solicitation and Accepted Proposal.
Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.14 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements.