3-Combined Project Budget, Scope of Work and Funding Worksheet Instruction Sheet.docx

DOCX document 34 KB Posted

Attached to
2028 Capital Outlay Application - New Construction 11/4
Solicitation number
US.261440
Issued by
New Mexico

About this file

This is an instruction sheet for completing the Combined Project Budget, Scope of Work and Funding Worksheet for the 2028 Capital Outlay Application administered by New Mexico's Aging and Long Term Services Department. The application targets senior centers seeking capital outlay funding for new construction projects, which are defined as construction of new facilities, structures, or major new site or infrastructure improvements supporting senior services. Applicants must submit a single completed worksheet per project or project phase, clearly distinguishing between the current phase included in the application and the full project scope from initial planning through final completion. The application requires detailed documentation of existing conditions and needs, specific proposed work with measurable quantities, deliverables, exclusions, dependencies, scheduling, and service continuity plans. For new construction projects, applicants must provide proof of completed planning and design documents, including assessments, engineering evaluations, drawings, specifications, and current cost estimates.

The instruction sheet establishes specific documentation and disclosure requirements for applicants to demonstrate project readiness and fiscal capacity. Applicants must provide an itemized project budget distinguishing between current-phase costs and full-project costs, identify all funding sources with their status (requested, secured, pending, or anticipated), and disclose any funding gaps and contingency plans. Renovations of $225,000 or less may not require planning and design documentation depending on scope, but all project sizes must identify permitting requirements and approval status. The worksheet requires applicants to reconcile funding sources, avoid duplicate cost and funding allocations, confirm that scope and budget descriptions align, and attach all supporting documentation including estimates, design documents, permits, inspection reports, and funding commitments. Applicants must also demonstrate the fiscal agent's capacity to manage the project, advance funds before reimbursement, and support ongoing operations and maintenance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions for Completing the Combined Project Budget, Scope of Work and Funding Worksheet 2028 Capital Outlay Application guidance Complete one worksheet for the project or project phase included in your application. Explain what the requested funding will accomplish, how costs were estimated, what other funding is available, and whether the work is ready to proceed.

Distinguish the current phase (the work included in this application) from the full project (all phases from initial planning through final completion). Enter N/A for items that do not apply. Explain information that is not yet available.

1. Applicant and Project Information Provide the legal entity name, facility name, physical project address, project title and primary contact information. Use the same names throughout the application and attachments.

Select all applicable project types: renovation, code compliance, new addition or a combination.

Identify whether the request is for planning and design or renovation/construction.

For a phased project, provide a phase number and descriptive title, such as Phase 1 — Planning and Design or Phase 2 — Senior Center Renovation.

2. Scope of Work Describe the specific work included in this application. Avoid general statements such as “improve the facility.”

Worksheet item
What to include
Existing conditions and need
Describe the problem, location, effect on services and intended beneficiaries.
Proposed work
Explain what will be repaired, replaced, renovated, evaluated or constructed.
Work item and location
Identify the room, building area, site location or system affected.
Quantity or extent
Provide square footage, room counts, fixture counts or other measurable quantities. Label estimates.
Deliverable
Identify the completed result, such as a report, design documents, renovated space or completed addition.
Exclusions and dependencies
Identify excluded work and activities that must occur before this work can begin.
Relationship to full project
Explain connections to completed and future phases.
Independent use
Explain whether the completed phase can be used before future phases are finished.
Schedule and service continuity
Provide start and completion dates, closures, relocation plans and measures to maintain services.

Example scope description Renovate two existing restrooms within the senior center, including replacement of fixtures, modification of interior layouts and installation of associated finishes. This request does not include kitchen renovation or construction of additional space. Final quantities and costs will be supported by the attached scope and estimate.

3. Planning, Permitting and Readiness Identify completed planning and design, remaining activities and the parties responsible.

Renovations of $225,000 or less: Planning and design may not be necessary depending on scope. Explain the basis for the determination. Permits may still be necessary and must be identified.

Renovations greater than $225,000: Attach proof of completed planning and design appropriate to the proposed renovation.

New additions: Attach proof of completed planning and design for the construction included in the request.

If planning and design are incomplete, identify that work as the initial phase rather than presenting renovation or construction as ready to proceed.

Planning and design documentation may include assessments, environmental testing, engineering evaluations, drawings, specifications, cost estimates and other applicable preconstruction documents.

Permits and approvals For each required permit or approval, identify the issuing authority, status (not started, submitted or approved), anticipated approval date and responsible party. Attach approvals already obtained.

If no permits are required, identify who made that determination and the basis. If requirements are unknown, explain how and when they will be confirmed. Complete this section for smaller renovations as well.

Code compliance Describe the deficiency, proposed correction, reviewing authority and any correction deadline. Attach available inspection reports, notices or assessments.

4. Project Budget Provide itemized estimates for the current phase and the full project.

Budget column
How to complete
Current phase
Enter all costs of this application phase, including costs paid by other sources.
Full project
Enter the cost of all phases from beginning to end, including the current phase and applicable prior-phase costs.

The current phase is included in the full project. Do not add these columns together. For a single-phase project, the amounts may match.

Enter amounts for applicable cost categories and use N/A where appropriate.

Identify the estimate source, preparer and preparation/update date. Attach supporting quotes or estimates.

Explain contingency amounts and their basis.

Distinguish costs already incurred from costs remaining to complete the project.

Do not assume listed costs are eligible for funding; verify eligibility against final program requirements.

5. Funding Sources and Reconciliation List this application request separately from other sources. Identify the amounts allocated to the current phase and to other phases.

Status
Description
Requested
The amount sought through this application; submission does not make it secured.
Secured
Funding supported by an award, commitment or other documentation confirming availability. Identify conditions or restrictions.
Pending
A request has been submitted but a funding decision has not been received.
Anticipated
A potential source that has not yet been confirmed or formally requested.

Do not allocate the same dollars to more than one phase. Do not present funds already spent as available for future work.

Current-phase calculations

Line
Instructions
A — Current-phase cost
Enter the full cost of the phase included in this application.
B — Application request
Enter the amount requested in this application.
C — Other secured funding
Enter confirmed funding allocated to the phase, excluding this request.
D — Other pending/anticipated funding
Enter unconfirmed funding allocated to the phase.
E — Unidentified funding gap
Calculate A − B − C − D. If negative, explain excess funding or adjust allocations.
F — Amount not yet secured
Calculate A − C. This includes the application request and other unconfirmed amounts.

A project may have no unidentified gap and still lack secured funding. Explain the plan if pending or anticipated funds are not awarded, and identify restrictions and availability dates.

Full-project calculations Compare total full-project cost with identified funding across all phases on the same beginning-to-end basis. Count the application request once. Separately identify funding already spent on prior phases. Disclose the remaining gap and explain how it will be addressed.

6. Attachments and Applicant Review List attachments by recognizable document name and indicate what each supports. Include applicable estimates, planning/design documents, permits, inspection reports, funding commitments and schedules.

☐ Scope, budget, funding request and schedule describe the same work.

☐ Current-phase costs are distinguished from full-project costs.

☐ Required planning/design documentation is attached.

☐ Permitting requirements and status are identified, including for smaller renovations.

☐ Costs and funding sources are not duplicated.

☐ Funding gaps, outstanding approvals and remaining work are disclosed.

The preparer should enter their name and title, review the acknowledgment, and sign and date the completed worksheet.

Draft Assumptions to Confirm Before Release These instructions assume the $225,000 threshold applies to total renovation project cost rather than only the amount requested. Projects costing exactly $225,000 fall in the lower category. These instructions also treat new additions as new construction for planning-and-design documentation. Confirm these points and all final application requirements before release.