This instruction sheet provides guidance for completing the Combined Project Budget, Scope of Work and Funding Worksheet for the 2028 Capital Outlay Application administered by New Mexico's Aging and Long Term Services Department for senior center capital projects. The worksheet requires applicants to describe the specific work included in their current funding request phase, distinguish it from the full project scope, and provide detailed scope descriptions including existing conditions, proposed work, work locations, quantities, deliverables, exclusions, dependencies, and schedule information. Applicants must identify completed planning and design documentation, permitting requirements and status, and code compliance issues. For renovations exceeding $225,000 and all new additions, proof of completed planning and design must be attached. The application requires itemized budget estimates for both the current phase and the full project, with clearly identified cost categories, contingency explanations, and supporting documentation such as quotes and estimates.
The funding section requires applicants to list the requested amount separately from other funding sources, categorizing funding as requested, secured, pending, or anticipated, and to complete reconciliation calculations that distinguish current-phase costs from full-project costs while avoiding duplication of funding across phases or misrepresentation of previously spent funds. Applicants must disclose funding gaps and explain plans for obtaining unconfirmed funding sources, including any restrictions and availability dates. The worksheet requires attachment of applicable estimates, planning and design documents, permits, inspection reports, funding commitments, and schedules, with applicants certifying that scope, budget, funding, and schedule descriptions align, that planning and design documentation is included when required, and that all costs and funding sources are properly distinguished and not duplicated.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-2028 CO Certification Letter Template.docx | DOCX document | |
| 5-2028 Capital Outlay Application Manual with Examples.pdf | ||
| 4-Combined Project Budget, Scope of Work and Funding Worksheet.docx | DOCX document | |
| 1-2028 CO Certification Letter Instructions.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions for Completing the Combined Project Budget, Scope of Work and Funding Worksheet 2028 Capital Outlay Application guidance Complete one worksheet for the project or project phase included in your application. Explain what the requested funding will accomplish, how costs were estimated, what other funding is available, and whether the work is ready to proceed.
Distinguish the current phase (the work included in this application) from the full project (all phases from initial planning through final completion). Enter N/A for items that do not apply. Explain information that is not yet available.
1. Applicant and Project Information Provide the legal entity name, facility name, physical project address, project title and primary contact information. Use the same names throughout the application and attachments.
Select all applicable project types: renovation, code compliance, new addition or a combination.
Identify whether the request is for planning and design or renovation/construction.
For a phased project, provide a phase number and descriptive title, such as Phase 1 — Planning and Design or Phase 2 — Senior Center Renovation.
2. Scope of Work Describe the specific work included in this application. Avoid general statements such as “improve the facility.”
| Worksheet item |
| What to include |
| Existing conditions and need |
| Describe the problem, location, effect on services and intended beneficiaries. |
| Proposed work |
| Explain what will be repaired, replaced, renovated, evaluated or constructed. |
| Work item and location |
| Identify the room, building area, site location or system affected. |
| Quantity or extent |
| Provide square footage, room counts, fixture counts or other measurable quantities. Label estimates. |
| Deliverable |
| Identify the completed result, such as a report, design documents, renovated space or completed addition. |
| Exclusions and dependencies |
| Identify excluded work and activities that must occur before this work can begin. |
| Relationship to full project |
| Explain connections to completed and future phases. |
| Independent use |
| Explain whether the completed phase can be used before future phases are finished. |
| Schedule and service continuity |
| Provide start and completion dates, closures, relocation plans and measures to maintain services. |
Example scope description Renovate two existing restrooms within the senior center, including replacement of fixtures, modification of interior layouts and installation of associated finishes. This request does not include kitchen renovation or construction of additional space. Final quantities and costs will be supported by the attached scope and estimate.
3. Planning, Permitting and Readiness Identify completed planning and design, remaining activities and the parties responsible.
Renovations of $225,000 or less: Planning and design may not be necessary depending on scope. Explain the basis for the determination. Permits may still be necessary and must be identified.
Renovations greater than $225,000: Attach proof of completed planning and design appropriate to the proposed renovation.
New additions: Attach proof of completed planning and design for the construction included in the request.
If planning and design are incomplete, identify that work as the initial phase rather than presenting renovation or construction as ready to proceed.
Planning and design documentation may include assessments, environmental testing, engineering evaluations, drawings, specifications, cost estimates and other applicable preconstruction documents.
Permits and approvals For each required permit or approval, identify the issuing authority, status (not started, submitted or approved), anticipated approval date and responsible party. Attach approvals already obtained.
If no permits are required, identify who made that determination and the basis. If requirements are unknown, explain how and when they will be confirmed. Complete this section for smaller renovations as well.
Code compliance Describe the deficiency, proposed correction, reviewing authority and any correction deadline. Attach available inspection reports, notices or assessments.
4. Project Budget Provide itemized estimates for the current phase and the full project.
| Budget column |
| How to complete |
| Current phase |
| Enter all costs of this application phase, including costs paid by other sources. |
| Full project |
| Enter the cost of all phases from beginning to end, including the current phase and applicable prior-phase costs. |
The current phase is included in the full project. Do not add these columns together. For a single-phase project, the amounts may match.
Enter amounts for applicable cost categories and use N/A where appropriate.
Identify the estimate source, preparer and preparation/update date. Attach supporting quotes or estimates.
Explain contingency amounts and their basis.
Distinguish costs already incurred from costs remaining to complete the project.
Do not assume listed costs are eligible for funding; verify eligibility against final program requirements.
5. Funding Sources and Reconciliation List this application request separately from other sources. Identify the amounts allocated to the current phase and to other phases.
| Status |
| Description |
| Requested |
| The amount sought through this application; submission does not make it secured. |
| Secured |
| Funding supported by an award, commitment or other documentation confirming availability. Identify conditions or restrictions. |
| Pending |
| A request has been submitted but a funding decision has not been received. |
| Anticipated |
| A potential source that has not yet been confirmed or formally requested. |
Do not allocate the same dollars to more than one phase. Do not present funds already spent as available for future work.
Current-phase calculations
| Line |
| Instructions |
| A — Current-phase cost |
| Enter the full cost of the phase included in this application. |
| B — Application request |
| Enter the amount requested in this application. |
| C — Other secured funding |
| Enter confirmed funding allocated to the phase, excluding this request. |
| D — Other pending/anticipated funding |
| Enter unconfirmed funding allocated to the phase. |
| E — Unidentified funding gap |
| Calculate A − B − C − D. If negative, explain excess funding or adjust allocations. |
| F — Amount not yet secured |
| Calculate A − C. This includes the application request and other unconfirmed amounts. |
A project may have no unidentified gap and still lack secured funding. Explain the plan if pending or anticipated funds are not awarded, and identify restrictions and availability dates.
Full-project calculations Compare total full-project cost with identified funding across all phases on the same beginning-to-end basis. Count the application request once. Separately identify funding already spent on prior phases. Disclose the remaining gap and explain how it will be addressed.
6. Attachments and Applicant Review List attachments by recognizable document name and indicate what each supports. Include applicable estimates, planning/design documents, permits, inspection reports, funding commitments and schedules.
☐ Scope, budget, funding request and schedule describe the same work.
☐ Current-phase costs are distinguished from full-project costs.
☐ Required planning/design documentation is attached.
☐ Permitting requirements and status are identified, including for smaller renovations.
☐ Costs and funding sources are not duplicated.
☐ Funding gaps, outstanding approvals and remaining work are disclosed.
The preparer should enter their name and title, review the acknowledgment, and sign and date the completed worksheet.
Draft Assumptions to Confirm Before Release These instructions assume the $225,000 threshold applies to total renovation project cost rather than only the amount requested. Projects costing exactly $225,000 fall in the lower category. These instructions also treat new additions as new construction for planning-and-design documentation. Confirm these points and all final application requirements before release.
2028 Capital Outlay Application | Combined worksheet instructions | 11.2026