This document is an Addendum No. 1 issued by Ada County Procurement for Bid 25072, a re-bid for the Ada County Sheriff's Office Radio Sites Power System Battery Replacement project. The bid is due on August 29, 2025, by 4:00 p.m. local time, and can be submitted through the Ada County Procurement Bonfire Portal. The addendum serves to provide additional information and clarify details for potential bidders, with instructions that it should be considered part of the original project documents and that bidders must acknowledge receipt of the addendum in their submissions.

The addendum includes a response to a pre-bid question regarding the current battery specifications at the three radio sites. Specifically, the existing batteries are identified as GNB Absolyte GP3-100G21-1000AH and GP6-90G15-608AH. This information is crucial for bidders to understand the current equipment and potentially propose compatible replacement batteries. The document emphasizes that bidders should make necessary adjustments to their estimates based on the information provided in this addendum and that failure to acknowledge the addendum may result in the bid being deemed non-responsive.

View the file

Other files

File Type Posted
1-Bid25072 Specifications.pdf PDF
2-Bid25072 Bidders Bid Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ada County Procurement

200 West Front Street procurement@adacounty.id.gov

Boise, Idaho 83702-7300 (208) 287-7140

DATE: August 25, 2025 TO: All Plan Holders FROM: Ada County Procurement

NO. OF PAGES: 2

Bid 25072 Re-Bid Ada County Sheriff’s Office Radio Sites Power System Battery Replacement

BIDS DUE: August 29, 2025, by 4:00 p.m. local time

Ada County Procurement Bonfire Portal - https://adacounty.bonfirehub.com

ADDENDUM NO. 1

NOTICE TO BIDDERS:

1. This addendum shall be considered part of the documents for the above-mentioned project as though it had been issued at the same time and shall be incorporated integrally therewith. Where provisions of the following supplementary data differ from those of the original documents, this addendum shall govern and take precedent.

2. Bidders are hereby notified that they shall make any necessary adjustment in their estimates on account of this addendum. It will be construed that each bid is submitted with full knowledge of all modifications and supplemental data specified herein.

3. Bidders must acknowledge in their bids that all addenda have been received, or the bid may be deemed non-responsive.

Please See Attached:

Questions received prior to the August 21, 2025, 4:00 p.m. local time cut-off

ADA COUNTY PROCUREMENT

https://adacounty.bonfirehub.com/

Ada County Procurement

Questions received prior to the August 21, 2025, 4:00 p.m. local time cut-off

1. What are the battery manufacturer and model number currently in use at each of the radio sites?

Answer: The current batteries that are in use at the three (3) radio sites are as follows:

GNB Absolyte GP3-100G21-1000AH & GP6-90G15-608AH.