3-Addendum No. 1 4140087 Frackville Spring Nice 9-18-2026.pdf

PDF 651 KB Posted

Attached to
Spring & Nice Streets Stormwater Project 4140. 087
Solicitation number
Not on record
Issued by
Schuylkill County, Pennsylvania

About this file

This addendum document issued by the Borough of Frackville on September 18, 2026, provides clarifications and modifications to the bidding documents for the Spring & Nice Streets Stormwater Project (Entech No. 4140.087). The addendum addresses four primary items: inclusion of Appendix F (Worker Protection and Investment Certification Form) that was missing from the original PennBid documents; modification of Section C700 Supplemental Conditions to permit installation floater policies as an alternative to builder's risk insurance; revision of Section 011500 regarding measurement and payment for trenching, excavation, bedding, and backfill; and resolutions to contractor questions raised during the pre-bid meeting held on September 15, 2026. The project completion requirements establish that work shall be substantially complete within 60 calendar days and fully completed within 75 calendar days from the Notice to Proceed date. Bids are due by 10:00 am local time on October 1, 2026, via the PennBid electronic bidding system, with bid security required at 10% of the total bid amount.

The addendum specifically clarifies that precast knockout-style inlet boxes and grates may be used as alternates to the specified PennDOT Type M inlet boxes, provided they meet minimum requirements including 4,000 psi concrete compressive strength and applicable PHL-93 or HS-25 roadway loading requirements, with field testing for leakage and Engineer approval required. The Worker Protection and Investment Certification Form requires contractor certification of compliance with Pennsylvania's Unemployment Compensation Law, Workers' Compensation Law, and applicable state labor and workforce safety laws including the Prevailing Wage Act, Construction Workplace Misclassification Act, and Minimum Wage Act, with penalties for false certifications including contract termination and three-year debarment from future Commonwealth contracts.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

BOROUGH OF FRACKVILLE

SPRING & NICE STREETS STORMWATER PROJECT

Entech No. 4140.087

September 18, 2026

The following addendum items hereby become an integral part and take precedence over the original drawings and project manual as though originally included therein at length and shall be so honored in the preparation of the Contractor’s bid and execution of the Contract.

Item 1.1 Project Manual Appendix F

Insert attached Appendix F that was listed in Table of Contents but missing from pdf bidding documents on PennBid.

Item 1.2 Project Manual C700 Supplemental Conditions

Modify Section C700 Supplemental Conditions with condition below:

6.04 Builder’s Risk and Other Property Insurance

SC-6.04 Add the following new paragraph immediately after Paragraph 6.04.A

An installation floater policy may be provided in lieu of the builder’s risk insurance policy required by Paragraph 6.04, provided that the installation floater provides coverage meeting the applicable requirements of Paragraph 6.04 of the General Conditions.

Item 1.3 Project Manual Section 011500, Measurement & Payment

Modify Section 011500. Part 2, Item 2.6.C by removing last sentence of paragraph and replacing with the revision below:

Trenching, excavation, bedding, and backfill will be paid under Item 5.

A copy of the Pre-Bid Meeting Sign-in sheet is attached for your reference.

Questions and Clarifications:

Topics and Resolutions from PennBid Questions and Pre-Bid Meeting

Addendum No.1 Borough of Frackville Spring & Nice Streets Stormwater Project September 18, 2026

Topic: A Contractor requested clarification regarding whether Appendix F – Worker Protection and Investment Certification Form would be provided with the Contract Documents.

Resolution: Appendix F – Worker Protection and Investment Certification Form is included with this Addendum and shall be completed as required.

Topic: A Contractor requested clarification regarding whether an Installation Floater would be acceptable in lieu of the Builder’s Risk insurance specified in the Contract Documents.

Resolution: An Installation Floater will be accepted in lieu of a Builder’s Risk policy.

The applicable Special Provisions have been revised accordingly.

Topic: A Contractor requested clarification regarding the Project completion requirements and whether a specific completion date must be met.

Resolution: The Contract Times will commence on the date established by the Notice to Proceed. The Work shall be substantially complete within sixty (60) calendar days and completed and ready for final payment within seventy-five (75) calendar days after the Contract Times commence.

Topic: A Contractor requested clarification regarding whether a precast knockout-style inlet box and grate may be used as an alternate to the PennDOT Type M inlet and inlet box specified in the Contract Documents.

Resolution: A precast knockout-style inlet box and grate will be considered as an alternate, provided it meets the same applicable minimum requirements as the specified PennDOT Type M inlet and inlet box, including the requirements of PennDOT RC-45M and RC-46M, a minimum concrete compressive strength of 4,000 psi, and the applicable PHL-93 or HS-25 roadway loading requirements.

If the knockout-style inlet box is proposed, it shall replace the specified PennDOT Type M inlet and inlet box for the applicable Bid Item and shall be included at the price bid for that item. The Contractor shall clearly indicate on the Bid Form/Bid Tab if the proposed bid price is based on use of the alternate knockout-style inlet box.

The proposed alternate shall be subject to the same shop drawing submittal and Engineer approval requirements as the specified precast inlet box and shall accommodate the pipe sizes, locations, and invert elevations shown on the Contract Drawings. All structure joints and pipe penetrations shall be properly sealed, and the completed structure and connections shall be field tested for leakage following installation. Any visible leakage shall be repaired and retested to the satisfaction of the Engineer.

END OF ADDENDUM #1

WORKER PROTECTION AND INVESTMENT CERTIFICATION FORM

A. Pursuant to Executive Order 2021-06, Worker Protection and Investment (October 21, 2021), the Commonwealth is responsible for ensuring that every worker in Pennsylvania has a safe and healthy work environment and the protections afforded them through labor laws. To that end, contractors and grantees of the Commonwealth must certify that they are in compliance with Pennsylvania’s Unemployment Compensation Law, Workers’ Compensation Law, and all applicable Pennsylvania state labor and workforce safety laws including, but not limited to:

1. Construction Workplace Misclassification Act

2. Employment of Minors Child Labor Act

3. Minimum Wage Act

4. Prevailing Wage Act

5. Equal Pay Law

6. Employer to Pay Employment Medical Examination Fee Act

7. Seasonal Farm Labor Act

8. Wage Payment and Collection Law

9. Industrial Homework Law

10. Construction Industry Employee Verification Act

11. Act 102: Prohibition on Excessive Overtime in Healthcare

12. Apprenticeship and Training Act

13. Inspection of Employment Records Law

B. Pennsylvania law establishes penalties for providing false certifications, including contract termination; and three-year ineligibility to bid on contracts under 62 Pa. C.S. § 531 (Debarment or suspension).

CERTIFICATION

I, the official named below, certify I am duly authorized to execute this certification on behalf of the contractor/grantee identified below, and certify that the contractor/grantee identified below is compliant with applicable Pennsylvania state labor and workplace safety laws, including, but not limited to, those listed in Paragraph A, above. I understand that I must report any change in the contractor/grantee’s compliance status to the Purchasing Agency immediately. I further confirm and understand that this Certification is subject to the provisions and penalties of 18 Pa. C.S. § 4904 (Unsworn falsification to authorities).

Signature Date

Name (Printed)

Title of Certifying Official (Printed)

Contractor/Grantee Name (Printed)

BOP-2201

Published: 02/07/2022 mdando Text Box Appendix F