About this file
This document is Addendum No. 1 to Request for Proposals RFP-653 for Ellis Building Interior Renovations issued by Monroe County, Florida on October 27, 2026. The addendum addresses a critical omission from the original RFP documents: the complete set of construction drawings titled "Ellis Building Renovation" by William P. Horn Architect, P.A., signed and sealed on July 9, 2026. These drawings, which are referenced in Section 00120, Item 2 and Section 00500, 9.1 of the original RFP, were inadvertently omitted from the documents initially posted on Bonfire and are now attached as part of this addendum. The scope of work encompasses interior renovations to the second floor of the Ellis Building located at the Plantation Key Government Center campus, including revised room layouts, new wall construction, new suspended ceilings and lighting, new flooring installation, new ADA-compliant breakrooms, a new lobby counter, new interior doors, and minor electrical, plumbing, and mechanical work in accordance with the attached drawings.
No pricing terms, set-asides, response dates, due dates, site visits, bidder's meetings, award dates, contract term, renewal options, or funding information is specified in this addendum. The document confirms that all other items referenced in the original RFP documents remain unchanged and in effect.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-Notice to Publish-Ellis Bldg Interior Renovation.docx | DOCX document | |
| 1-RFP - Ellis Building Renovation FINAL.pdf | ||
| 4-Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
ELLIS BUILDING INTERIOR RENOVATIONS
MONROE COUNTY, FLORIDA
RFP-653
ADDENDUM NO. 01
October 27, 2026
The information contained in this Addendum alters the information contained in the RFQ and is hereby made a part of the RFQ.
Question #1: Section 00120, Item 2 and Section 00500, 9.1 reference construction drawings titled “Ellis Building Renovation” by William P. Horn Architect, P.A., signed and sealed 07/09/2026. These drawings are not included in the documents currently posted on Bonfire. Please post the complete drawing set.
Response #1: The drawings were inadvertently omitted from the RFP documents and are now attached as part of this Addendum.
All other items remain as called for in the documents.
End of Addendum No 1.