3 - 2024-04-28 - River View Express Line - Bid Sheet.xls
XLS spreadsheet 44 KB Posted
- Attached to
- River View Sewer Improvements
- Solicitation number
- SM-030
- Issued by
- Gilpin County, Colorado
About this file
This is a bid sheet for the River View Sewer Improvements project issued by the Town of Gypsum, Colorado, involving the installation of approximately 3,000 linear feet of 24" sewer express line and an 8" raw water pumpback line through the Eagle River Estates neighborhood. The project is scheduled with a mandatory pre-bid meeting on May 8, 2025, at 2:00 PM, and bid opening on May 20, 2025, at 9:00 AM. The Town Council will select the winning bidder on May 27, 2025, with a notice to proceed upon contract document completion. The project requires work to be completed by September 19, 2025, with full acceptance and two-year warranty start by September 26, 2025. Work hours are restricted to 7 AM - 7 PM Monday through Friday, with no weekend work unless approved, and a specific blackout period during Gypsum Daze (July 17-19).
The bid sheet includes detailed line items for mobilization, demolition, excavation, utilities, concrete, paving, and finishing work, with quantities specified for each category. The project involves complex infrastructure work, including manhole installations, sewer line placement, water service relocations, and surface restoration. Contractors are responsible for storm water management, erosion control, traffic control, and maintaining access to residences. Quality control measures include testing by Ground Engineering, adherence to Gypsum Public Works Manual and CDOT standards, and specific requirements for trench backfilling and temporary surface maintenance. Contractors must provide performance and two-year warranty bonds, and are required to post door hangers and coordinate with local residents prior to commencing work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5 - River View Sewer Express Line - Bid Form.docx | DOCX document | |
| 4 - 2025-04-28 - River View Express Line - Bid Sheet.pdf | ||
| 2 - PLANS - 04-23-2025 - RiverViewSewerImprv_BidSet_Phase1.pdf | ||
| 7 - River View Sewer Express Line - Short Form Agreement.docx | DOCX document | |
| 9 - PERFORMANCE AND WARRANTY BOND.doc | DOC document | |
| 6 - River View Sewer Express Line - Bid Bond.doc | DOC document | |
| 8 - Project Manual - 04-28-2025.pdf | ||
| 1- Invitation to Bid- Web Posting for 2025-04-28.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Sheet
| BID Sheet - River View Sewer Improvements | April 28, 2025 | ||||
| Bid schedule critical times and dates: | |||||
| a | Mandatory Pre-bid meeting Thursday, May 8, 2025 at 2:00 PM at Community Development Conference Room | ||||
| b | Bid all items below as winner takes all. | ||||
| c | Bid Opening = Tuesday, May 20th at 9:00 AM, at the Community Development conference room. | ||||
| d | Town Council (T.C.) selection on May 27, 2025 at a 7 PM public meeting | ||||
| e | Notice to Proceed- as soon as all contract documents are signed and received from the Council selected bidder. | ||||
| f | Work completed and ready for punchlist No Later Than (NLT) Sept 19, 2025 | ||||
| g | 100% complete and accepted for Two-Year Warranty start NLT Sept 26, 2025 | ||||
| h | Standards and Definitions: | ||||
| i | All construction & testing per the Gypsum Public Works Manual, and CDOT standards. | ||||
| j | Disposal of removed materials shall be offsite unless otherwise noted. Gun Club is full. | ||||
| l | The contractor is responsible for the driveability of the backfilled trench. The temporary trench surface shall be asphalt millings maintained by the contractor until final paving can be completed. The surface shall be regrade and recompact as necessary to avoid potholes and excessive bumps prior to actual paving. | ||||
| l | The contractor shall post door hangers for residences along the route of the express line 1 week before the start of work. The door hangar shall be approved by the Engineer before being published. | ||||
| m | Working hours are 7 am - 7 pm Monday to Friday. No weekend work allowed unless otherwise approved. | ||||
| n | Soils, asphalt and concrete Quality Acceptance testing will be performed by Ground Engineering for the Town. | ||||
| o | Subsurface Utility Exploration (SUE Plans) are attached for reference to the plans. All locations to be confirmed. | ||||
| p | See Gypsum Public Works Manual for Sanitary Sewer details. | ||||
| q | Accesses to residencies to remain open at all times. | ||||
| r | Electronic CAD and XML files will be provided are for information only. In the event of conflict between the electronic files and the plans, the plans will take precedence. The contractor shall notify the Engineer of any conflicts between the electronic files and the plans. | ||||
| s | No work will be allowed July 17-19 for Gypsum Daze. | ||||
| River View Sewer Express Line | |||||
| GENERAL & DEMO DESCRIPTION | QNTY | Unit | Unit Price | Total | |
| 1 | Mobilization | 1 | LS | $ - 0 | $ - 0 |
| 2 | Clearing and Grubbing | 1 | LS | $ - 0 | $ - 0 |
| 3 | Construction Stormwater management and Erosion Control Measures | 1 | LS | $ - 0 | $ - 0 |
| 4 | Removal of Asphalt Mat (Full Depth) - Sawcut and remove full depth for sewer line installation. | 3,000.00 | SY | $ - 0 | $ - 0 |
| 5 | Removal of asphalt mat (Planing) - 2" deep by 2' wide for T patch on both sides of the trench | 1,500.00 | SY | $ - 0 | $ - 0 |
| 6 | Removal of Concrete Valley Pan (36' wide x 10' long in two places) | 80.00 | SY | $ - 0 | $ - 0 |
| 7 | Removal of Mountable Curb and Gutter with attached sidewalk (as needed and approved) | 50.00 | SY | $ - 0 | $ - 0 |
| 8 | Potholing | 60.00 | HR | $ - 0 | $ - 0 |
| 9 | Construction Surveying | 1.00 | LS | $ - 0 | $ - 0 |
| 10 | EXCAVATION & UTILTIIES DESCRIPTION | QNTY | Unit | Unit Price | Total |
| 11 | Dewatering | 1 | LS | $ - 0 | $ - 0 |
| 12 | Bypass pumping (as required) | 1 | LS | $ - 0 | $ - 0 |
| 13 | Sanitary Sewer Manhole 60 in diameter (including pipe connections, bedding, backfill, rims and rings to grade) Manhole rim to be 1/4" below final asphalt grade. Manholes shall be water tight including a bituthene wrap around the outside of the manhole. | 11 | EA | $ - 0 | $ - 0 |
| 14 | 24" C900 Sewer Line (Including excavation, pipe bedding, and backfill) with field loc gaskets | 2,988 | LF | $ - 0 | $ - 0 |
| 15 | Clay dam (per details) (15-20% bentonite and select 3/4" minus native material) | 20 | EA | $ - 0 | $ - 0 |
| 16 | 8" Fuseable HDPE DR-17 pipe (Including excavation, pipe bedding and backfill) - For pumpback line, in the same trench as the sewer line | 3,000 | LF | $ - 0 | $ - 0 |
| 17 | Relocate water service (includes, removal of pipe, additional pipe, fittings, trenching, backfill to relocate the existing water service to accommodate the new sewer main) | 20 | EA | $ - 0 | $ - 0 |
| 18 | Adjust Manhole rim to grade (as needed for other utilities) | 5 | EA | $ - 0 | $ - 0 |
| 19 | Adjust valve box rim to grade (as needed for other utilities) | 5 | EA | $ - 0 | $ - 0 |
| 20 | CONCRETE, PAVING, & FINISHES DESCRIPTION | QNTY | Unit | Unit Price | Total |
| 21 | Asphalt Millings - Temporary cover for trench, 4" thick, compacted and removed prior to paving. After removal the millings become the property of the contractor. | 630 | TN | $ - 0 | $ - 0 |
| 22 | Aggregate Base Course (Class 6) - 8" Thick under asphalt and curb and gutter, 4" thick under sidewalk, Per CDOT Standards | 1,197 | TN | $ - 0 | $ - 0 |
| 23 | Conrete Valley Pan (10' wide x 36' long - 2 locations) (with #4's @ 12" o.c. each way) (including forming, reinforcing, finishing) | 80 | SY | $ - 0 | $ - 0 |
| 24 | 4' Sidewalk monolithic with mountable curb and gutter, 6" Thick Concrete. (as needed and approved) | 50 | SY | $ - 0 | $ - 0 |
| 25 | 4" Hot Mix Asphalt (Grading SX-75) (PG 58-28) including tack between layers | 825 | TN | $ - 0 | $ - 0 |
| 26 | Traffic Control per MUTCD. All flaggers to be certified. | 1 | LS | $ - 0 | $ - 0 |
| 27 | SUB TOTAL = | $ - 0 | |||
| River View Sewer Express Line | |||||
| Subtotal | $ - 0 | ||||
| 28 | (formula uses 1.5%, so change if yours is different) Performance & Two Year Warranty Bond = | $ - 0 | |||
| 29 | Amount to be read at the bid opening = | $ - 0 | |||
| _____________________________________ ___________________________ , 2025 | |||||
| Printed Name of Bidder Signature | Date | ||||
| _________________________________________________________________ | |||||
| Company Name |